2 projects on file, including joint ventures this contractor is part of.
Total projects
2
Total budget
₱28.8M
Average progress
100.0%
Completion rate
100.0%
Average risk score
49.0
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 2 | ₱28.8M | 49.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 1 | ₱10.9M | 68.9 | 0 | 100.0% |
| Bridges | 1 | ₱17.9M | 29.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17CH0010CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RETAI | Region III | Pampanga 2nd DEO | Completed | ₱10.9M | 100% | High risk69 | —-0.062 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17CH0010CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RETAI | Region III | Pampanga 2nd DEO | Completed | ₱10.9M | 100% | High risk69 | —-0.062 |
| 2 | 18CI0109CONST/REPAIR/REHAB/IMPROVEMENT OF VARIOUS INFRA INC. LOCAL PROJECTS;LOCAL ROADS AND BRIDGES;LOCAL BRIDGES-CONST OF BRIDGE WITH SLOPE PROTECTION AT BRGY SAPANG BALEN,MABALACAT,PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱17.9M | 100% | Low risk29 | —-0.067 |