Contractor dossier
29 projects on file, including joint ventures this contractor is part of.
Total projects
29
Total budget
₱226.4M
Average progress
98.4%
Completion rate
96.6%
Average risk score
27.3
Low risk on average, out of 100
Flagged as unusual
1
3.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 29 | ₱226.4M | 27.3 | 1 | 98.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱47.8M | 19.4 | 0 | 100.0% |
| Roads | 10 | ₱114.3M | 29.0 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱40.3M | 38.7 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱24M | 93.4 | 1 | 53.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0144CONSTRUCTION OF ROAD ALONG BRGY. VILLAFLOR, PUERTO GALERA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱24M | 53% | High risk93 | Flagged0.023 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0144CONSTRUCTION OF ROAD ALONG BRGY. VILLAFLOR, PUERTO GALERA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱24M | 53% | High risk93 | Flagged0.023 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25ED0144CONSTRUCTION OF ROAD ALONG BRGY. VILLAFLOR, PUERTO GALERA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱24M | 53% | High risk93 | Flagged0.023 |
| 2 | 19ED0081CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG MAG-ASAWANG TUBIG RIVER, SAN ANDRES PUTIK, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱16.5M | 100% | Medium risk39 | —-0.075 |
| 3 | 20ED0028CONSTRUCTION OF RIVER CONTROL AT BRGY. SAN ANDRES PUTIK TO BRGY. TAGUMPAY, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱18.8M | 100% | Medium risk39 | —-0.077 |
| 4 | 25ED0050CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY TIBAG - BARANGAY PACHOCA, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱4.9M | 100% | Medium risk38 | —-0.072 |
| 5 | 21ED0109CONSTRUCTION OF MULTI - PURPOSE BUILDING (ISOLATION FACILITIES), BACO, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱11.8M | 100% | Medium risk38 | —-0.085 |
| 6 | 22ED0122CONSTRUCTION OF ROAD WITH DRAINAGE, SITIO INTERIOR - KALAYAAN, BARANGAY BALATERO, PUERTO GALERA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱14.7M | 100% | Medium risk38 | —-0.089 |
| 7 | 21ED0107CONSTRUCTION OF ROAD, SITIO BINARILAN, BRGY. CANUBING 1 - SITIO ILAYA, BRGY. MALAD, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱24.5M | 100% | Medium risk38 | —-0.094 |
| 8 | 23ED0017ROAD WIDENING ALONG CSR JCT - MINAS RD - K0046+000 - K0046+800, VICTORIA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱25.2M | 100% | Medium risk38 | —-0.094 |
| 9 | 22ED0125CONSTRUCTION OF ROAD AT BALATERO MUNICIPAL GROUND, BRGY. BALATERO, PUERTO GALERA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱9.8M | 100% | Medium risk37 | —-0.089 |
| 10 | 21ED0178CONCRETING OF ROAD, BRGY. BUHANGIN, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱24.5M | 100% | Medium risk37 | —-0.095 |
| 11 | 21ED0192CONCRETING OF VARIOUS ROAD, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱9.8M | 100% | Medium risk37 | —-0.093 |
| 12 | 21EB0103CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. GEN. EMILIO AGUINALDO, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱3.9M | 100% | Low risk21 | —-0.083 |
| 13 | 21ED0142CONSTRUCTION OF BALITE MULTI - PURPOSE BUILDING, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱3.9M | 100% | Low risk21 | —-0.085 |
| 14 | 23ED0099CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING PHASE II (GYM TYPE) OF BARANGAY IBABA WEST, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.9M | 100% | Low risk20 | —-0.086 |
| 15 | 21ED0041CONSTRUCTION OF MULTI - PURPOSE BUILDING (BARANGAY HALL), BARANGAY CATININGAN, SOCORRO, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.9M | 100% | Low risk20 | —-0.086 |
| 16 | 21ED0030CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT), BARANGAY CAMILMIL E/S, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.9M | 100% | Low risk20 | —-0.085 |
| 17 | 19ED0082CONSTRUCTION OF MULTI - PURPOSE BUILDING (TECHNOLOGY TRAINING CENTER) IN VICTORIA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.9M | 100% | Low risk20 | —-0.086 |
| 18 | 21ED0014CONCRETING OF ROAD, BARANGAY BARUYAN, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2M | 100% | Low risk20 | —-0.087 |
| 19 | 21ED0170CONSTRUCTION/IMPROVEMENT OF MULTI - PURPOSE BUILDING (COVERED COURT), BRGY. CANUBING II, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.4M | 100% | Low risk19 | —-0.085 |
| 20 | 21ED0047REHABILITATION OF MULTI - PURPOSE BUILDING (COVERED COURT), BARANGAY BALINGAYAN, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.084 |
| 21 | 21ED0092CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT) FILEMON F. SAMACO E/S, BRGY. COMUNAL, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.4M | 100% | Low risk19 | —-0.086 |
| 22 | 20ED0010CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT), SITIO ST. BENEDICT, BRGY. PACHOCA, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.086 |
| 23 | 20ED0068CONSTRUCTION OF MULTI - PURPOSE BUILDING (BARANGAY HALL), BRGY. BATINO, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱2.4M | 100% | Low risk19 | —-0.086 |
| 24 | 19ED0076CONCRETING OF ROAD, BRGY. SAN ANTONIO, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱947K | 100% | Low risk16 | —-0.086 |
| 25 | 19ED0068CONSTRUCTION OF ROAD AT BRGY. SAN ANTONIO, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱947.4K | 100% | Low risk16 | —-0.086 |