29 projects on file, including joint ventures this contractor is part of.
Total projects
29
Total budget
₱416.9M
Average progress
82.4%
Completion rate
58.6%
Below 70%
Average risk score
54.8
Medium risk on average, out of 100
Flagged as unusual
8
27.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 29 | ₱416.9M | 54.8 | 8 | 82.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 17 | ₱206.9M | 53.3 | 5 | 78.3% |
| Buildings and Facilities | 6 | ₱112.8M | 42.3 | 0 | 98.3% |
| OTHER | 3 | ₱72.8M | 88.0 | 3 | 64.1% |
| Flood Control and Drainage | 3 | ₱24.5M | 55.4 | 0 | 91.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 24JA0155REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD AT BARANGAY QUINIPUT, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱9.6M | 54% | High risk87 | Flagged0.061 |
| 24JA0123CONCRETING OF SITIO MUTI- SITIO LUNAWI, BRGY. LANZONES FMR, BRGY. LANZONES, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.9M | 90% | High risk87 | Flagged0.054 |
| 24JA0169CONSTRUCTION OF ROAD NRJ BOALAN-TUGBUNGAN PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱19.3M | 0% | High risk70 | Flagged0.050 |
| 24JA0153WIDENING OF PUTIK-LUNZURAN ROAD, ZAMBOANGA CITY PACKAGE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 17JA0037CONCRETING OF ROAD ALONG JCT. LUYAHAN-PASONANCA TO JCT BY-PASS ROAD IN BARANGAY PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.8M | 100% | High risk66 | —-0.048 |
| 22JA0026CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.5M | 90% | High risk62 | —-0.015 |
| 24JA0128CONCRETING OF SITIO MUROK, BRGY. PASONANCA FMR, BRGY. PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.9M | 50% | High risk61 | Flagged0.014 |
| 23JA0091CONCRETING OF SITIO LIPOCON, BRGY. BOLONG FMR PHASE II, BRGY. BOLONG, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱14.9M | 100% | High risk60 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 24JA0155REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD AT BARANGAY QUINIPUT, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱9.6M | 54% | High risk87 | Flagged0.061 |
| 24JA0123CONCRETING OF SITIO MUTI- SITIO LUNAWI, BRGY. LANZONES FMR, BRGY. LANZONES, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.9M | 90% | High risk87 | Flagged0.054 |
| 24JA0169CONSTRUCTION OF ROAD NRJ BOALAN-TUGBUNGAN PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱19.3M | 0% | High risk70 | Flagged0.050 |
| 24JA0153WIDENING OF PUTIK-LUNZURAN ROAD, ZAMBOANGA CITY PACKAGE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 24JA0148CONSTRUCTION OF LUNZURAN-LUYAHAN TO ZAMBOANGA CITY BY-PASS ROAD ZAMBOANGA CITY PACKAGE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱4.8M | 0% | Medium risk52 | Flagged0.027 |
| 24JA0128CONCRETING OF SITIO MUROK, BRGY. PASONANCA FMR, BRGY. PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.9M | 50% | High risk61 | Flagged0.014 |
| 17JA0109CONSTRUCTION OF PASONANCA FMR, PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.9M | 100% | Medium risk58 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 2 | 24JA0155REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD AT BARANGAY QUINIPUT, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱9.6M | 54% | High risk87 | Flagged0.061 |
| 3 | 24JA0123CONCRETING OF SITIO MUTI- SITIO LUNAWI, BRGY. LANZONES FMR, BRGY. LANZONES, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.9M | 90% | High risk87 | Flagged0.054 |
| 4 | 24JA0169CONSTRUCTION OF ROAD NRJ BOALAN-TUGBUNGAN PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱19.3M | 0% | High risk70 | Flagged0.050 |
| 5 | 24JA0153WIDENING OF PUTIK-LUNZURAN ROAD, ZAMBOANGA CITY PACKAGE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 6 | 17JA0037CONCRETING OF ROAD ALONG JCT. LUYAHAN-PASONANCA TO JCT BY-PASS ROAD IN BARANGAY PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.8M | 100% | High risk66 | —-0.048 |
| 7 | 22JA0026CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.5M | 90% | High risk62 | —-0.015 |
| 8 | 24JA0128CONCRETING OF SITIO MUROK, BRGY. PASONANCA FMR, BRGY. PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.9M | 50% | High risk61 | Flagged0.014 |
| 9 | 23JA0091CONCRETING OF SITIO LIPOCON, BRGY. BOLONG FMR PHASE II, BRGY. BOLONG, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱14.9M | 100% | High risk60 | —-0.032 |
| 10 | 23JA0006ASSET PRESERVATION - CONSTRUCTION/UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - ZAMBOANGA CITY-LABUAN-LIMPAPA RD - K1970 + 000 - K1970 + 625, K1970 + 626 - K1971 + 260 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱23.1M | 100% | Medium risk58 | —-0.038 |
| 11 | 17JA0109CONSTRUCTION OF PASONANCA FMR, PASONANCA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.9M | 100% | Medium risk58 | Flagged0.002 |
| 12 | 24JA0062SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF CONCRETE ROAD AT TORRES DRIVE, BARANGAY MAMPANG, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱7.8M | 89% | Medium risk57 | —-0.043 |
| 13 | 24JA0094SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES- RECONSTRUCTION OF ROAD AT BARANGAY LANZONES, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.8M | 100% | Medium risk57 | —-0.080 |
| 14 | 23JA0030BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES: CONSTRUCTION OF ROAD, BARANGAY DULIAN (UPPER PASONANCA), ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Region IX | Zamboanga City 2nd DEO | On-Going | ₱4.9M | 93% | Medium risk57 | —-0.034 |
| 15 | 24JA0068BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF DRAINAGE STRUCTURE AT STO. NIÑO PUTIK, BARANGAY PUTIK, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱9.8M | 74% | Medium risk56 | —-0.021 |
| 16 | 21JA0123CONSTRUCTION OF SLOPE PROTECTION, SITIO UWAK RIVER, SAN ROQUE, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.9M | 100% | Medium risk55 | —-0.067 |
| 17 | 20JA0016CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAN ROQUE, BARANGAY SAN ROQUE, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.8M | 100% | Medium risk55 | —-0.068 |
| 18 | 18JA0093BUILDING AND OTHER STRUCTURES - MULTI-PURPOSE/ FACILITIES - CONSTRUCTION/REPAIR/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS: CONSTRUCTION OF 2 STOREY MULTI-PURPOSE BUILDING FOR PNP PUBLIC SAFETY COLLEGE (PPSC), PASONANCA, Z.C. | Region IX | Zamboanga City 2nd DEO | Completed | ₱8.4M | 100% | Medium risk54 | —-0.075 |
| 19 | 24JA0148CONSTRUCTION OF LUNZURAN-LUYAHAN TO ZAMBOANGA CITY BY-PASS ROAD ZAMBOANGA CITY PACKAGE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱4.8M | 0% | Medium risk52 | Flagged0.027 |
| 20 | 18JA0107CONCRETING OF ROAD (UPPER PASONANCA) FMR, BRGY. DULIAN (UPPER PASONANCA), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱7.7M | 100% | Medium risk50 | —-0.031 |
| 21 | 20JA0098CONCRETING OF BRGY. SAN ROQUE FMR, BRGY. SAN ROQUE, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.7M | 100% | Medium risk49 | —-0.029 |
| 22 | 20JA0088CONCRETING OF BRGY. DULIAN FMR, BRGY. DULIAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱11.8M | 100% | Medium risk49 | —-0.029 |
| 23 | 19JA0169CONCRETING OF SINUBONG FMR, BRGY. SINUBONG, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱5.7M | 100% | Medium risk47 | —-0.029 |
| 24 | 17JA0145CONSTRUCTION OF THREE (3) STOREY NINE (9) CLASSROOM SCHOOL BUILDING AT STA. MARIA CENTRAL SCHOOL, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱24.1M | 100% | Medium risk42 | —-0.006 |
| 25 | 16JA0130CONSTRUCTION OF TWO (2) STOREY SIX (6) CLASSROOM SCHOOL BUILDING AT GUISAO ELEMENTARY SCHOOL, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱8M | 100% | Medium risk41 | —-0.009 |