492 projects on file, including joint ventures this contractor is part of.
Total projects
492
Total budget
₱12.2B
Average progress
97.7%
Completion rate
91.9%
Average risk score
29.7
Low risk on average, out of 100
Flagged as unusual
33
6.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 476 | ₱12.1B | 29.8 | 33 | 97.6% |
| Region VII | 16 | ₱54.7M | 26.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 199 | ₱4.9B | 24.9 | 1 | 100.0% |
| Buildings and Facilities | 123 | ₱610.5M | 15.2 | 0 | 100.0% |
| Flood Control and Drainage | 78 | ₱3.2B | 29.9 | 0 | 99.6% |
| OTHER | 23 | ₱1.4B | 78.3 | 12 | 90.2% |
| Bridges | 23 | ₱527.3M | 30.3 | 0 | 100.0% |
| Water Provision and Storage | 17 | ₱84.3M | 18.0 | 0 | 100.0% |
| GAA 2025 SSP | 14 | ₱418.2M | 92.7 | 13 | 63.3% |
| GAA 2025 OO-2 | 11 | ₱712.6M | 88.9 | 4 | 75.6% |
| GAA 2025 OO-1 | 4 | ₱303.7M | 91.1 | 3 | 75.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MC0044CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 2, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱112.2M | 53% | High risk95 | Flagged0.038 |
| 25MD0050ROAD WIDENING - DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT), VILLARICA, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱84.2M | 23% | High risk94 | Flagged0.029 |
| 25MD0029MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱140.4M | 88% | High risk94 | Flagged0.019 |
| 25MC0046CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 4, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱31.5M | 91% | High risk94 | Flagged0.015 |
| 25MC0071CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ILOMAVIS, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 99% | High risk93 | Flagged0.011 |
| 25MC0080CONSTRUCTION OF ROAD, BARANGAY LUVIMIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱9.6M | 18% | High risk93 | Flagged0.039 |
| 25MD0049CONSTRUCTION OF FLOOD CONTROL STRUCTURE, LIBUNGAN RIVER, CAMANSI BRIDGE (UPSTREAM, DOWNSTREAM AND BOTH SIDES), CAMANSI, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱93.6M | 43% | High risk93 | Flagged0.006 |
| 25MC0042CONSTRUCTION OF ROAD - BENOLIGAN - ONICA - DALAPITAN ROAD, KIDAPAWAN CITY AND MATALAM, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱28.5M | 92% | High risk93 | Flagged0.017 |
| 25MD0038CONSTRUCTION OF BALOGO RIVER FLOOD CONTROL STRUCTURE, ANICK SECTION, BARANGAY ANICK, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱94.4M | 94% | High risk93 | —-0.006 |
| 25MD0034CONSTRUCTION OF BRIDGE APPROACHES AT RARADANGAN TO MACABASA, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱56.1M | 100% | High risk93 | —-0.020 |
| 25MD0039CONSTRUCTION OF BRIDGE APPROACHES CONNECTING CAMANSI AND BARANGAY PACAO, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 36% | High risk93 | Flagged0.032 |
| 25MD0061CONSTRUCTION OF BRIDGE APPROACHES AT POLAYAGAN TO MAPUROK, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 22% | High risk93 | Flagged0.038 |
| 25MD0031CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱94.7M | 87% | High risk93 | —-0.004 |
| 25MC0082CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) PHASE 1, BARANGAY SAGUING, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱5.8M | 9% | High risk93 | Flagged0.043 |
| 25MC0091CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY DAGUPAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 31% | High risk92 | Flagged0.034 |
| 25MC0040CONSTRUCTION OF CONCRETE ROAD - BINOLIGAN - AMAZION, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱38M | 77% | High risk92 | Flagged0.024 |
| 25MC0013RECONSTRUCTION TO CONCRETE PAVEMENT ALONG PACO - ROXAS - ARAKAN VALLEY - JCT DAVAO - BUKIDNON RD - K1659 + 667 - K1660 + 263, K1660 + 286 - K1661 + 134, ANTIPAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱26.5M | 90% | High risk92 | Flagged0.002 |
| 25MC0068CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY INDANGAN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 92% | High risk92 | Flagged0.015 |
| 25MD0065CONSTRUCTION OF LIBUNGAN RIVER FLOOD CONTROL PROJECT (UPSTREAM AND DOWNSTREAM OF MAPUROK BRIDGE - POLAYAGAN SECTION), POLAYAGAN, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱74.9M | 42% | High risk92 | Flagged0.003 |
| 25MD0046INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS, GUARDRAILS) ALONG MIDSAYAP-MAKAR RD, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱4.9M | 95% | High risk91 | Flagged0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MC0102CONSTRUCTION OF SCHOOL BUILDING (ONE (1) STOREY THREE (3) CLASSROOM), AT ASUNCION ELEMENTARY SCHOOL, BARANGAY POBLACION, MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱7.2M | 52% | High risk87 | Flagged0.058 |
| 25MC0104CONSTRUCTION OF SCHOOL BUILDING (ONE (1) STOREY TWO (2) CLASSROOM), AT NEW CEBU ELEMENTARY SCHOOL, BARANGAY NEW CEBU MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 45% | High risk81 | Flagged0.057 |
| 25MC0103CONSTRUCTION OF SCHOOL BUILDING (ONE (1) STOREY THREE (3) CLASSROOM), AT STO. NIÑO ELEMENTARY SCHOOL, BARANGAY STO. NIÑO MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱7.2M | 78% | High risk87 | Flagged0.051 |
| 17MC0193REHABILITATION OF MALABUAN-BATO-MALUNGON-LACOBE FMR, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Terminated | ₱63.8M | 100% | Medium risk52 | Flagged0.046 |
| 25MC0082CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) PHASE 1, BARANGAY SAGUING, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱5.8M | 9% | High risk93 | Flagged0.043 |
| 25MC0080CONSTRUCTION OF ROAD, BARANGAY LUVIMIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱9.6M | 18% | High risk93 | Flagged0.039 |
| 25MC0044CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 2, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱112.2M | 53% | High risk95 | Flagged0.038 |
| 25MD0061CONSTRUCTION OF BRIDGE APPROACHES AT POLAYAGAN TO MAPUROK, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 22% | High risk93 | Flagged0.038 |
| 25MC0091CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY DAGUPAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 31% | High risk92 | Flagged0.034 |
| 25MD0039CONSTRUCTION OF BRIDGE APPROACHES CONNECTING CAMANSI AND BARANGAY PACAO, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 36% | High risk93 | Flagged0.032 |
| 25MD0050ROAD WIDENING - DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT), VILLARICA, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱84.2M | 23% | High risk94 | Flagged0.029 |
| 25MC0040CONSTRUCTION OF CONCRETE ROAD - BINOLIGAN - AMAZION, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱38M | 77% | High risk92 | Flagged0.024 |
| 25MD0056CONSTRUCTION OF RETAINING WALL ALONG KITAO CREEK, CENTRAL KATINGAWAN, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱4.9M | 71% | High risk91 | Flagged0.022 |
| 25MD0029MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱140.4M | 88% | High risk94 | Flagged0.019 |
| 25MC0042CONSTRUCTION OF ROAD - BENOLIGAN - ONICA - DALAPITAN ROAD, KIDAPAWAN CITY AND MATALAM, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱28.5M | 92% | High risk93 | Flagged0.017 |
| 25MC0046CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 4, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱31.5M | 91% | High risk94 | Flagged0.015 |
| 25MC0068CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY INDANGAN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 92% | High risk92 | Flagged0.015 |
| 16MD0110CONST. OF SINAPANGAN-KALUNGKUNGAN FMR, SINPAPANGAN, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱24.3M | 100% | High risk83 | Flagged0.013 |
| 25MD0059JCT. DAVAO - COTABATO (CROSSING BAGUER) - SITIO DALUMANGKOM - SITIO LAMPAKI ROAD, PIGKAWAYAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱65.5M | 58% | High risk78 | Flagged0.013 |
| 24MD0049MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱106.1M | 92% | High risk81 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 276 | 25MD0011CONSTRUCTION OF ROAD, BARANGAY POBLACION 6 ALONG IRRIGATION CANAL-BARANGAY POBLACION 1, BARANGAY POBLACION 6, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.089 |
| 277 | 22MC0020CONSTRUCTION OF WATER SYSTEM, BARANGAY KIYAAB, ANTIPAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱5M | 100% | Low risk25 | —-0.054 |
| 278 | 22MD0013CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF PUROK 7-UPPER GLAD 1 ROAD, BARANGAY UPPER GLAD 1, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.085 |
| 279 | 23MD0015CONSTRUCTION OF ROAD, POBLACION 1 - POBLACION 2 - UPPER GLAD 1 ROAD, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.085 |
| 280 | 23MD0003CONSTRUCTION OF ROAD, DUALING - HABITAT ROAD DUALING, ALEOSAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.085 |
| 281 | 22MD0007CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF JCT PROVINCIAL ROAD LOWER KATINGAWAN- BAGUMBA ROAD, BARANGAY BAGUMBA, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.089 |
| 282 | 22MC0073CONSTRUCTION OF BRIDGE CONNECTING BRGY. BIRADA AND BRGY. MANONGOL, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱24.5M | 100% | Low risk25 | —-0.051 |
| 283 | 20MC0039JCT. MATIGOL TO SITIO INAMONG ROAD LEADING TO MATIGOL FALLS, BRGY. DATU LADAYON, ARAKAN, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱7.2M | 100% | Low risk25 | —-0.088 |
| 284 | 20MH0022CONSTRUCTION OF RIVER BANK PROTECTION/FLOOD CONTROL(UPSTREAM), BRGY. BIWANG, BAGUMBAYAN, SULTAN KUDARAT BRGY. BIWANG, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱38M | 100% | Low risk25 | —-0.076 |
| 285 | 20MC0040NATIONAL HIGHWAY-DEL CARMEN -SAGCUNGAN ROAD IN SUPPORT TO DAIRY AND ORGANIC PRODUCTS PROCESSING, PRESIDENT ROXAS, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱9.8M | 100% | Low risk25 | —-0.089 |
| 286 | 22MC0031CONSTRUCTION OF CONCRETE ROAD - NATIONAL HIGHWAY-DEL CARMEN-SAGCUNGAN ROAD IN SUPPORT TO DAIRY AND ORGANIC PRODUCTS PROCESSING, PRESIDENT ROXAS, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱9.8M | 100% | Low risk25 | —-0.090 |
| 287 | 21MC0021CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF ROAD, LOMONAY-DEL CARMEN, PRESIDENT ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱17.6M | 100% | Low risk25 | —-0.090 |
| 288 | 20MC0041SAN ISIDRO-SAN ROQUE-ESTADO MATALAM ROAD CONNECTING NATIONAL HIGHWAY TO BOI REGISTERED COMPANIES, KIDAPAWAN CITY, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱19.6M | 100% | Low risk25 | —-0.090 |
| 289 | 23MC0015PAVING OF UNPAVED ROAD ALONG MAGPET-NOWA-DOROLUMAN-GREENFIELD ROAD - K1646+345 - K1646+705, MAGPET, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱10.4M | 100% | Low risk25 | —-0.090 |
| 290 | 23MD0006CONSTRUCTION OF ROAD, BARANGAY KIMAGANGO - MALAMOTE ROAD, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.085 |
| 291 | 22MC0023CONSTRUCTION OF WATER SYSTEM, MATIAS, CAMUTAN, ANTIPAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.054 |
| 292 | 18MC0099WIDENING OF PERMANENT BRIDGES-KABACAN BR. 2(B00264MN) ALONG PACO-ROXAS-ARAKAN VALLEY JCT DAVAO-BUKIDNON ROAD, PRES. ROXAS, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱31.1M | 100% | Low risk25 | —-0.051 |
| 293 | 20MC0035ACCESS ROAD LEADING TO TWIN FALLS, BRGY. MANONGOL, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱7.8M | 100% | Low risk25 | —-0.087 |
| 294 | 22MC0048CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO TWIN FALLS, BRGY. MANONGOL, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱7.3M | 100% | Low risk25 | —-0.088 |
| 295 | 24MC0060CONSTRUCTION OF CONCRETE ROAD - NATIONAL HIGHWAY-DEL CARMEN-SAGCUNGAN ROAD IN SUPPORT TO DAIRY AND ORGANIC PRODUCTS PROCESSING, PRES. ROXAS, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱15.8M | 100% | Low risk24 | —-0.089 |
| 296 | 18MC0071PAVING OF SHOULDERS ALONG KIDAPAWAN-ILOMAVIS TOURIST RD, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱6.8M | 100% | Low risk24 | —-0.087 |
| 297 | 24MD0014CONSTRUCTION OF NICAAN - SITIO ANTARA ROAD, NICAAN, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱5.9M | 100% | Low risk24 | —-0.089 |
| 298 | 22MD0074CONSTRUCTION OF BRIDGE - CONSTRUCTION OF BRIDGE IN SILIK, PIKIT, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱29.2M | 100% | Low risk24 | —-0.057 |
| 299 | 22MC0060WIDENING OF PERMANENT BRIDGES - PACO BR. (B00255MN) ALONG PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD, KIDAPAWAN CITY, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱30.4M | 100% | Low risk24 | —-0.049 |
| 300 | 22MC0053WIDENING OF PERMANENT BRIDGES - ILUSTRE BR. (B00271MN) ALONG PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON ROAD, PRES. ROXAS, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱20.6M | 100% | Low risk24 | —-0.058 |