Opening the dossier…
Opening the dossier…
Contractor dossier
492 projects on file, including joint ventures this contractor is part of.
Total projects
492
Total budget
₱12.2B
Average progress
97.7%
Completion rate
91.9%
Average risk score
29.7
Low risk on average, out of 100
Flagged as unusual
33
6.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 476 | ₱12.1B | 29.8 | 33 | 97.6% |
| Region VII | 16 | ₱54.7M | 26.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 199 | ₱4.9B | 24.9 | 1 | 100.0% |
| Buildings and Facilities | 123 | ₱610.5M | 15.2 | 0 | 100.0% |
| Flood Control and Drainage | 78 | ₱3.2B | 29.9 | 0 | 99.6% |
| OTHER | 23 | ₱1.4B | 78.3 | 12 | 90.2% |
| Bridges | 23 | ₱527.3M | 30.3 | 0 | 100.0% |
| Water Provision and Storage | 17 | ₱84.3M | 18.0 | 0 | 100.0% |
| GAA 2025 SSP | 14 | ₱418.2M | 92.7 | 13 | 63.3% |
| GAA 2025 OO-2 | 11 | ₱712.6M | 88.9 | 4 | 75.6% |
| GAA 2025 OO-1 | 4 | ₱303.7M | 91.1 | 3 | 75.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MC0044CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 2, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱112.2M | 53% | High risk95 | Flagged0.038 |
| 25MD0050ROAD WIDENING - DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT), VILLARICA, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱84.2M | 23% | High risk94 | Flagged0.029 |
| 25MD0029MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱140.4M | 88% | High risk94 | Flagged0.019 |
| 25MC0046CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 4, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱31.5M | 91% | High risk94 | Flagged0.015 |
| 25MC0071CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ILOMAVIS, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 99% | High risk93 | Flagged0.011 |
| 25MC0080CONSTRUCTION OF ROAD, BARANGAY LUVIMIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱9.6M | 18% | High risk93 | Flagged0.039 |
| 25MD0049CONSTRUCTION OF FLOOD CONTROL STRUCTURE, LIBUNGAN RIVER, CAMANSI BRIDGE (UPSTREAM, DOWNSTREAM AND BOTH SIDES), CAMANSI, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱93.6M | 43% | High risk93 | Flagged0.006 |
| 25MC0042CONSTRUCTION OF ROAD - BENOLIGAN - ONICA - DALAPITAN ROAD, KIDAPAWAN CITY AND MATALAM, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱28.5M | 92% | High risk93 | Flagged0.017 |
| 25MD0038CONSTRUCTION OF BALOGO RIVER FLOOD CONTROL STRUCTURE, ANICK SECTION, BARANGAY ANICK, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱94.4M | 94% | High risk93 | —-0.006 |
| 25MD0034CONSTRUCTION OF BRIDGE APPROACHES AT RARADANGAN TO MACABASA, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱56.1M | 100% | High risk93 | —-0.020 |
| 25MD0039CONSTRUCTION OF BRIDGE APPROACHES CONNECTING CAMANSI AND BARANGAY PACAO, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 36% | High risk93 | Flagged0.032 |
| 25MD0061CONSTRUCTION OF BRIDGE APPROACHES AT POLAYAGAN TO MAPUROK, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 22% | High risk93 | Flagged0.038 |
| 25MD0031CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱94.7M | 87% | High risk93 | —-0.004 |
| 25MC0082CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) PHASE 1, BARANGAY SAGUING, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱5.8M | 9% | High risk93 | Flagged0.043 |
| 25MC0091CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY DAGUPAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 31% | High risk92 | Flagged0.034 |
| 25MC0040CONSTRUCTION OF CONCRETE ROAD - BINOLIGAN - AMAZION, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱38M | 77% | High risk92 | Flagged0.024 |
| 25MC0013RECONSTRUCTION TO CONCRETE PAVEMENT ALONG PACO - ROXAS - ARAKAN VALLEY - JCT DAVAO - BUKIDNON RD - K1659 + 667 - K1660 + 263, K1660 + 286 - K1661 + 134, ANTIPAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱26.5M | 90% | High risk92 | Flagged0.002 |
| 25MC0068CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY INDANGAN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 92% | High risk92 | Flagged0.015 |
| 25MD0065CONSTRUCTION OF LIBUNGAN RIVER FLOOD CONTROL PROJECT (UPSTREAM AND DOWNSTREAM OF MAPUROK BRIDGE - POLAYAGAN SECTION), POLAYAGAN, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱74.9M | 42% | High risk92 | Flagged0.003 |
| 25MD0046INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS, GUARDRAILS) ALONG MIDSAYAP-MAKAR RD, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱4.9M | 95% | High risk91 | Flagged0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MC0102CONSTRUCTION OF SCHOOL BUILDING (ONE (1) STOREY THREE (3) CLASSROOM), AT ASUNCION ELEMENTARY SCHOOL, BARANGAY POBLACION, MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱7.2M | 52% | High risk87 | Flagged0.058 |
| 25MC0104CONSTRUCTION OF SCHOOL BUILDING (ONE (1) STOREY TWO (2) CLASSROOM), AT NEW CEBU ELEMENTARY SCHOOL, BARANGAY NEW CEBU MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 45% | High risk81 | Flagged0.057 |
| 25MC0103CONSTRUCTION OF SCHOOL BUILDING (ONE (1) STOREY THREE (3) CLASSROOM), AT STO. NIÑO ELEMENTARY SCHOOL, BARANGAY STO. NIÑO MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱7.2M | 78% | High risk87 | Flagged0.051 |
| 17MC0193REHABILITATION OF MALABUAN-BATO-MALUNGON-LACOBE FMR, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Terminated | ₱63.8M | 100% | Medium risk52 | Flagged0.046 |
| 25MC0082CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) PHASE 1, BARANGAY SAGUING, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱5.8M | 9% | High risk93 | Flagged0.043 |
| 25MC0080CONSTRUCTION OF ROAD, BARANGAY LUVIMIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱9.6M | 18% | High risk93 | Flagged0.039 |
| 25MC0044CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 2, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱112.2M | 53% | High risk95 | Flagged0.038 |
| 25MD0061CONSTRUCTION OF BRIDGE APPROACHES AT POLAYAGAN TO MAPUROK, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 22% | High risk93 | Flagged0.038 |
| 25MC0091CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY DAGUPAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 31% | High risk92 | Flagged0.034 |
| 25MD0039CONSTRUCTION OF BRIDGE APPROACHES CONNECTING CAMANSI AND BARANGAY PACAO, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱56.1M | 36% | High risk93 | Flagged0.032 |
| 25MD0050ROAD WIDENING - DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT), VILLARICA, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱84.2M | 23% | High risk94 | Flagged0.029 |
| 25MC0040CONSTRUCTION OF CONCRETE ROAD - BINOLIGAN - AMAZION, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱38M | 77% | High risk92 | Flagged0.024 |
| 25MD0056CONSTRUCTION OF RETAINING WALL ALONG KITAO CREEK, CENTRAL KATINGAWAN, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱4.9M | 71% | High risk91 | Flagged0.022 |
| 25MD0029MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱140.4M | 88% | High risk94 | Flagged0.019 |
| 25MC0042CONSTRUCTION OF ROAD - BENOLIGAN - ONICA - DALAPITAN ROAD, KIDAPAWAN CITY AND MATALAM, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱28.5M | 92% | High risk93 | Flagged0.017 |
| 25MC0046CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 4, BARANGAY MALIBATUAN, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱31.5M | 91% | High risk94 | Flagged0.015 |
| 25MC0068CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY INDANGAN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | On-Going | ₱4.8M | 92% | High risk92 | Flagged0.015 |
| 16MD0110CONST. OF SINAPANGAN-KALUNGKUNGAN FMR, SINPAPANGAN, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱24.3M | 100% | High risk83 | Flagged0.013 |
| 25MD0059JCT. DAVAO - COTABATO (CROSSING BAGUER) - SITIO DALUMANGKOM - SITIO LAMPAKI ROAD, PIGKAWAYAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱65.5M | 58% | High risk78 | Flagged0.013 |
| 24MD0049MIDSAYAP - LIBUNGAN BYPASS ROAD, COTABATO | Region XII | Cotabato 1st DEO | On-Going | ₱106.1M | 92% | High risk81 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 451 | 20MC0063CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BULACANON, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3.9M | 100% | Low risk7 | —-0.085 |
| 452 | 21MC0040CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NEW BULATUKAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱4M | 100% | Low risk7 | —-0.085 |
| 453 | 18MC0002CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. TUAEL, PRESIDENT ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3.5M | 100% | Low risk7 | —-0.087 |
| 454 | 21MC0006CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAGCUNGAN, PRESIDENT ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3M | 100% | Low risk7 | —-0.086 |
| 455 | 18MD0132CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DELANGALEN CENTRAL ELEMENTARY SCHOOL, POBLACION 1, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.8M | 100% | Low risk7 | —-0.088 |
| 456 | 18MD0134CONSTRUCTION OF A LIVELIHOOD CENTER MULTI-PURPOSE/COVERED COURT, STA., CRUZ, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.7M | 100% | Low risk7 | —-0.089 |
| 457 | 18MC0074CONSTRUCTION OF MULTI PURPOSE BUILDING, (SAYABAN ELEMENTARY SCHOOL), ILOMAVIS, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | Completed | ₱3.3M | 100% | Low risk7 | —-0.084 |
| 458 | 20MC0068CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAGUING, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3M | 100% | Low risk7 | —-0.085 |
| 459 | 18MC0120CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS CENTER), BRGY. SUDAPIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | Completed | ₱3.5M | 100% | Low risk7 | —-0.085 |
| 460 | 18MC0001CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. SAN VICENTE, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3.5M | 100% | Low risk7 | —-0.086 |
| 461 | 20MC0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, SIKITAN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | Completed | ₱3.5M | 100% | Low risk7 | —-0.086 |
| 462 | 18MC0003CONSTRUCTION OF MULTI-PURPOSE BUILDING AT SIBAWAN HIGH SCHOOL, BRGY. SIBAWAN, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3.5M | 100% | Low risk7 | —-0.085 |
| 463 | 22MC0009CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LOMONAY, PRESIDENT ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2.9M | 100% | Low risk7 | —-0.086 |
| 464 | 21MD0039CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MIRASOL (DAR OFFICE), BARANGAY MIRASOL, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk7 | —-0.087 |
| 465 | 21MD0037CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POLAYAGAN, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk7 | —-0.087 |
| 466 | 19MD0131CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE 2, POBLACION, MUNICIPAL HALL SITE, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.4M | 100% | Low risk7 | —-0.087 |
| 467 | 21MD0059CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk7 | —-0.089 |
| 468 | 19MD0074CONSTRUCTION OF MULTI-PURPOSE BUILDING (MPB), BRGY. ELBOCEAN, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk6 | —-0.089 |
| 469 | 19MD0075CONSTRUCTION OF MULTI-PURPOSE BUILDING (MPB), BRGY. SAN ISIDRO, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk6 | —-0.089 |
| 470 | 23MC0036CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PRESIDENT ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2.5M | 100% | Low risk6 | —-0.084 |
| 471 | 18MC0073COMPLETION OF MULTI PURPOSE BUILDING (WITH BLEACHERS) BRGY. LUVIMIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | Completed | ₱2.5M | 100% | Low risk6 | —-0.084 |
| 472 | 25MC0053CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SUDAPIN, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.083 |
| 473 | 25MC0056CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALABUAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.081 |
| 474 | 20MC0047CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (DISASTER EVACUATION & TRAINING CENTER), POBLACION, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.084 |
| 475 | 25MC0057CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MANONGOL, KIDAPAWAN CITY | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.080 |