Contractor dossier
21 projects on file, including joint ventures this contractor is part of.
Total projects
21
Total budget
₱165M
Average progress
77.0%
Completion rate
47.6%
Below 70%
Average risk score
46.5
Medium risk on average, out of 100
Flagged as unusual
4
19.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 21 | ₱165M | 46.5 | 4 | 77.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 11 | ₱48.9M | 46.3 | 1 | 84.1% |
| Roads | 8 | ₱98.7M | 44.7 | 1 | 77.8% |
| OTHER | 1 | ₱14.5M | 86.1 | 1 | 69.4% |
| Water Provision and Storage | 1 | ₱2.9M | 24.2 | 1 | 0.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PG0077CONCRETING OF SITIO BANAAW TO SITIO TAMMANGAN, BARANGAY WANGWANG FMR, BARANGAY WANGWANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱14.5M | 69% | High risk86 | Flagged0.047 |
| 25PG0070CONSTRUCTION OF GUMHANG MULTI-PURPOSE BUILDING, BARANGAY GUMHANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.9M | 0% | High risk70 | Flagged0.001 |
| 25PG0001REHAB./RECON'STN./UPGRADING OF DAMAGED PAVED ROADS ALONG KIANGAN-TINOC-BUGUIAS RD. K0351+274-K0351+395, K0353+834-K0353+874,K0355+291-K0355+327,K0355+453-K0355+498,K0357+957-K0358+610, TINOC,IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱21.9M | 0% | High risk62 | Flagged0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PG0077CONCRETING OF SITIO BANAAW TO SITIO TAMMANGAN, BARANGAY WANGWANG FMR, BARANGAY WANGWANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱14.5M | 69% | High risk86 | Flagged0.047 |
| 24PG0064CONSTRUCTION OF RAINWATER COLLECTORS IN PUBLIC FACILITIES, ASIPULO, HINGYON, HUNGDUAN, KIANGAN, LAGAWE AND TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱2.9M | 0% | Low risk24 | Flagged0.003 |
| 25PG0070CONSTRUCTION OF GUMHANG MULTI-PURPOSE BUILDING, BARANGAY GUMHANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.9M | 0% | High risk70 | Flagged0.001 |
| 25PG0001REHAB./RECON'STN./UPGRADING OF DAMAGED PAVED ROADS ALONG KIANGAN-TINOC-BUGUIAS RD. K0351+274-K0351+395, K0353+834-K0353+874,K0355+291-K0355+327,K0355+453-K0355+498,K0357+957-K0358+610, TINOC,IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱21.9M | 0% | High risk62 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PG0077CONCRETING OF SITIO BANAAW TO SITIO TAMMANGAN, BARANGAY WANGWANG FMR, BARANGAY WANGWANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱14.5M | 69% | High risk86 | Flagged0.047 |
| 2 | 25PG0070CONSTRUCTION OF GUMHANG MULTI-PURPOSE BUILDING, BARANGAY GUMHANG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.9M | 0% | High risk70 | Flagged0.001 |
| 3 | 25PG0001REHAB./RECON'STN./UPGRADING OF DAMAGED PAVED ROADS ALONG KIANGAN-TINOC-BUGUIAS RD. K0351+274-K0351+395, K0353+834-K0353+874,K0355+291-K0355+327,K0355+453-K0355+498,K0357+957-K0358+610, TINOC,IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱21.9M | 0% | High risk62 | Flagged0.001 |
| 4 | 25PG0071CONSTRUCTION OF LGU MULTI-PURPOSE BUILDING, BARANGAY POBLACION, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.8M | 78% | Medium risk50 | —-0.042 |
| 5 | 25PG0033CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LUHONG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.8M | 83% | Medium risk50 | —-0.044 |
| 6 | 25PG0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO COCOY, BARANGAY TUCUCAN, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.8M | 86% | Medium risk50 | —-0.044 |
| 7 | 24PG0032CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY AHIN, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.080 |
| 8 | 24PG0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY IMPUGONG, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.082 |
| 9 | 25PG0039CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱4.9M | 78% | Medium risk49 | —-0.041 |
| 10 | 22PG0032CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY TUKUCAN, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.082 |
| 11 | 24PG0054CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN DENGAO ELEMENTARY SCHOOL EXTENSION (ALAM-AM ELEMENTARY SCHOOL), AHIN, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.046 |
| 12 | 23PG0036CONSTRUCTION OF ACCESS ROAD FROM AHIN TO DENGAO, AHIN, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.084 |
| 13 | 24P00039CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - KIANGAN-TINOC-BUGUIAS RD - (S00634LZ) CHAINAGE 42685 - CHAINAGE 43246, CHAINAGE 44572 - CHAINAGE 44870, CHAINAGE 45301 - CHAINAGE 46081, CHAINAGE 46905 - CHAINA | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱21.5M | 89% | Medium risk45 | —-0.046 |
| 14 | 25PG0044CONST'N./UPGRADING/REHAB. OF DRAINAGE ALONG NAL'S. RDS.-TERTIARY ROADS-BAN-HUNG-BENG BDRY. RD.-K0386+218,K0389+336-K0389+354,K0394+522,K0396+727,K0397+142-K0397+225,K0397+992,K0398+405,K0398+693,K0402+295, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱20M | 39% | Medium risk45 | —-0.040 |
| 15 | 25PG0043REHABILITATION/RECONSTRUCTION OF ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BANAUE-HUNGDUAN-BENGUET BDRY. RD.-K0372+730-K0372+771,K0378+490-K0378+513,K0379+177-K0379+191,K0380+533-K0380+572,K0382+569-K0382+596, HUNGDUAN, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱9.6M | 94% | Medium risk45 | —-0.050 |
| 16 | 23PG0006REHAB./RECONSTRUCTION OF NATIONAL ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BAN-HUNG-BENG BDRY. RD.-K0396+496-K0396+525,K0397+052-K0397+081, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱5.5M | 100% | Medium risk45 | —-0.084 |
| 17 | 23PG0010REHAB./RECONSTRUCTION OF NAT'L. ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BANAUE-HUNGDUAN-BENGUET BDRY. RD.-K0405+438-K0405+506,K0405+883-K0405+900, K0405+926-K0405+977, K0407+(-052)-K0407+(-039), TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱12.8M | 100% | Medium risk44 | —-0.085 |
| 18 | 24PG0033CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY AP-APID, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.082 |
| 19 | 23PG0009REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS W/SLIP, SLOPE COLLAPSE AND LANDSLIDE ALONG BANAUE-HUNGDUAN-BENGUET BDRY. RD.-K0404+004-K0404+035, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱2.6M | 100% | Low risk25 | —-0.084 |
| 20 | 24PG0064CONSTRUCTION OF RAINWATER COLLECTORS IN PUBLIC FACILITIES, ASIPULO, HINGYON, HUNGDUAN, KIANGAN, LAGAWE AND TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | On-Going | ₱2.9M | 0% | Low risk24 | Flagged0.003 |
| 21 | 24PG0038CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TUCUCAN, TINOC, IFUGAO | Cordillera Administrative Region | Ifugao 1st DEO | Completed | ₱2M | 100% | Low risk24 | —-0.081 |