Opening the dossier…
Opening the dossier…
Contractor dossier
261 projects on file, including joint ventures this contractor is part of.
Total projects
261
Total budget
₱1.8B
Average progress
99.9%
Completion rate
97.3%
Average risk score
17.5
Low risk on average, out of 100
Flagged as unusual
4
1.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 138 | ₱961.7M | 13.7 | 3 | 100.0% |
| Region XI | 81 | ₱659.6M | 25.4 | 1 | 99.8% |
| Region X | 42 | ₱147.1M | 14.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 176 | ₱1.3B | 14.9 | 1 | 100.0% |
| Roads | 42 | ₱318.7M | 26.0 | 2 | 99.7% |
| Water Provision and Storage | 35 | ₱83.7M | 15.2 | 0 | 100.0% |
| Bridges | 5 | ₱66.1M | 40.6 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱26.1M | 17.9 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱3M | 86.6 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17ME0114CONST. OF (1) STOREY, (3) CL BLDG. @ LUMIGO IS, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱3.7M | 100% | Low risk2 | Flagged0.008 |
| 25LD0077CONSTRUCTION (COMPLETION) OF MPB, BRGY. BATO, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱3M | 100% | High risk87 | Flagged0.005 |
| 17ME0128CONCRETING OF LU'AN, LUN MASLA TO PARAG PROPER FMR, K0+000-K0+495, K0+485+656, K0+640-K0+959.50, MALAPATAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱9.9M | 100% | Medium risk35 | Flagged0.003 |
| 20M00198CONCRETING OF BRGY. MALAYAN FMR WITH RCBC PHASE II, BRGY. MALAYAN, MLANG, NORTH COTABATO | Region XII | Region XII | Completed | ₱9.7M | 100% | Medium risk34 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 201 | 21MI0037CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BARANGAY LINAO, MATALAM, NORTH COTABATO | Region XII | Cotabato 3rd DEO | Completed | ₱3.8M | 100% | Low risk7 | —-0.086 |
| 202 | 19MC0059CONSTRUCTION OF MULTI-PURPOSE BUILDING (MALATAB HIGH SCHOOL), BRGY. MALATAB, ANTIPAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3.3M | 100% | Low risk7 | —-0.086 |
| 203 | 18MC0057CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. GREENHILLS, PRES. ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3.5M | 100% | Low risk7 | —-0.086 |
| 204 | 21MC0044CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN TAMESIS ST. BARANGAY POBLACION, KIDAPAWAN CITY, COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱3M | 100% | Low risk7 | —-0.085 |
| 205 | 18MC0121CONSTRUCTION OF MULTI PURPOSE BUILDING, POBLACION TULUNAN, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.085 |
| 206 | 21MB0061CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYM), PUBLIC MARKET, BARANGAY SULIT, POLOMOLOK, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱4.2M | 100% | Low risk6 | —-0.083 |
| 207 | 18MC0031CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. NATUTUNGAN, MATALAM, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.085 |
| 208 | 19MC0194CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BARANGAY BUAYAN, MLANG, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.084 |
| 209 | 18MC0142CONSTRUCTION OF MULTI-PURPOSE BUILDING, BNBL-NIA, BAGONTAPAY, M'LANG, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.085 |
| 210 | 18MC0079CONSTRUCTION OF MULTI-PURPOSE BUILDING, LA FORTUNA, M'LANG, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.085 |
| 211 | 18MC0144CONSTRUCTION OF MULTIPURPOSE BUILDING, NEW ABRA, MATALAM, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk6 | —-0.087 |
| 212 | 21MB0084CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH) AT BARANGAY PULABATO, TAMPAKAN, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱4M | 100% | Low risk6 | —-0.084 |
| 213 | 20M00191CONSTRUCTION / COMPLETION / REHABILITATION OF MULTI-PURPOSE BUILDING IN BRGY. MANUBUAN, MATALAM, NORTH COTABATO | Region XII | Region XII | Completed | ₱2.4M | 100% | Low risk6 | —-0.086 |
| 214 | 21MB0058CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY GYMNASIUM), BARANGAY DANLAG, TAMPAKAN, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱3M | 100% | Low risk6 | —-0.085 |
| 215 | 18ME0025CONST./REHAB. OF PUBLIC MARKET BLDG., GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱3.7M | 100% | Low risk6 | —-0.078 |
| 216 | 20MB0081CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK MALINAWON, CALUMPANG, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱3M | 100% | Low risk6 | —-0.081 |
| 217 | 18MC0026CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. MAGBOK, TULUNAN, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱1.9M | 100% | Low risk5 | —-0.084 |
| 218 | 20MB0032CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK 23 ESTABILLO, BRGY. LAGAO, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱2.3M | 100% | Low risk5 | —-0.079 |
| 219 | 19MB0052CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAAN BANWANG ELEMENTARY SCHOOL, BRGY. UPPER LABAY, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.082 |
| 220 | 19MG0028CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW GYM), BRGY. TUDOK, T'BOLI, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.086 |
| 221 | 19MG0016CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW GYM). SITIO DUNGAN LAHEK, BRGY. SARAVIA, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.084 |
| 222 | 18MC0258CONSTRUCTION OF SCHOOL BUILDINGS IN ELEMENTARY AND SECONDARY CLASSROOMS (CLUSTER 2) COTABATO DIVISION CLUSTER | Region XII | Cotabato 2nd DEO | Completed | ₱2.7M | 100% | Low risk4 | —-0.037 |
| 223 | 17LD0072CONSTRUCTION OF CLASSROOMS, 1STY 2CL WITH TOILET, BINATON ES, CITY OF DIGOS, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2.9M | 100% | Low risk4 | —-0.017 |
| 224 | 17LD0078CONSTRUCTION OF CLASSROOMS, 1STY 2CL LIBERTAD NHS, BLDG B., BANSALAN, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2.6M | 100% | Low risk4 | —-0.017 |
| 225 | 17LD0077CONSTRUCTION OF CLASSROOMS, 1STY 2CL LIBERTAD NHS, BLDG. A, BANSALAN, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2.6M | 100% | Low risk4 | —-0.017 |