Contractor dossier
6 projects on file, including joint ventures this contractor is part of.
Total projects
6
Total budget
₱362.1M
Average progress
37.4%
Completion rate
0.0%
Below 70%
Average risk score
67.2
High risk on average, out of 100
Flagged as unusual
1
16.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 6 | ₱362.1M | 67.2 | 1 | 37.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 5 | ₱263.2M | 63.9 | 0 | 37.6% |
| OTHER | 1 | ₱98.9M | 83.7 | 1 | 36.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24J00153CONSTRUCTION OF MAMPANG - RIO HONDO COASTAL ROAD, ZAMBOANGA CITY (PACKAGE 4) | Region IX | Region IX | On-Going | ₱98.9M | 36% | High risk84 | Flagged0.033 |
| 24J00146CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF BUNGUIAO-QUINIPUT ROAD, ZAMBOANGA CITY, PHASE 2 | Region IX | Region IX | On-Going | ₱89.6M | 31% | High risk71 | —-0.020 |
| 24J00147CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF NRJ SANGALI BYPASS ROAD, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱67.5M | 31% | High risk66 | —-0.021 |
| 24J00011CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - VITALI-SIBULAO-BYPASS ROAD PROJECT (ALTERNATE ROAD OF N1) PACKAGE 4, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱80.8M | 21% | High risk66 | —-0.014 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24J00153CONSTRUCTION OF MAMPANG - RIO HONDO COASTAL ROAD, ZAMBOANGA CITY (PACKAGE 4) | Region IX | Region IX | On-Going | ₱98.9M | 36% | High risk84 | Flagged0.033 |
| 2 | 24J00146CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF BUNGUIAO-QUINIPUT ROAD, ZAMBOANGA CITY, PHASE 2 | Region IX | Region IX | On-Going | ₱89.6M | 31% | High risk71 | —-0.020 |
| 3 | 24J00147CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF NRJ SANGALI BYPASS ROAD, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱67.5M | 31% | High risk66 | —-0.021 |
| 4 | 24J00011CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - VITALI-SIBULAO-BYPASS ROAD PROJECT (ALTERNATE ROAD OF N1) PACKAGE 4, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱80.8M | 21% | High risk66 | —-0.014 |
| 5 | 24JA0095BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION/RECONSTRUCTION OF CONCRETE ROAD BARANGAY BOALAN TO BARANGAY SALAAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱19.6M | 15% | Medium risk59 | —-0.017 |
| 6 | 24JA0063SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF CONCRETE ROAD AT ZONE 4, BARANGAY CULIANAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱5.8M | 90% | Medium risk57 | —-0.043 |