Contractor dossier
94 projects on file, including joint ventures this contractor is part of.
Total projects
94
Total budget
₱12.4B
Average progress
77.9%
Completion rate
64.9%
Below 70%
Average risk score
60.3
High risk on average, out of 100
Flagged as unusual
18
19.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 51 | ₱7.1B | 60.9 | 10 | 78.8% |
| Region IV-A | 37 | ₱4.9B | 60.2 | 8 | 73.6% |
| Cordillera Administrative Region | 3 | ₱183.7M | 54.1 | 0 | 95.4% |
| Region VIII | 2 | ₱186M | 59.9 | 0 | 100.0% |
| National Capital Region | 1 | ₱47M | 50.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 69 | ₱10.4B | 60.3 | 15 | 83.0% |
| Roads | 11 | ₱797.9M | 52.8 | 0 | 60.6% |
| Flood Control and Drainage | 6 | ₱280.8M | 51.5 | 0 | 100.0% |
| Bridges, Roads | 3 | ₱348.6M | 62.0 | 0 | 43.2% |
| GAA 2025 SSP | 2 | ₱204.4M | 95.9 | 2 | 1.2% |
| OTHER | 2 | ₱96.2M | 72.7 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱298.6M | 93.8 | 1 | 0.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25A00305SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BOLINAO TO SANTIAGO ISLAND, BOLINAO, PANGASINAN (PACKAGE 1) | Region I | Region I | On-Going | ₱93.6M | 1% | High risk96 | Flagged0.055 |
| 25A00306SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BOLINAO TO SANTIAGO ISLAND, BOLINAO, PANGASINAN (PACKAGE 2) | Region I | Region I | On-Going | ₱110.8M | 1% | High risk96 | Flagged0.057 |
| 25A00427CONSTRUCTION OF NEW BRIDGES, PANCIAN VIADUCT ALONG MANILA NORTH RD (PHASE IV) | Region I | Region I | On-Going | ₱298.6M | 1% | High risk94 | Flagged0.066 |
| 19A00118CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG CITY BY-PASS ROAD, BRIDGE PACKAGE, ILOCOS NORTE | Region I | Region I | On-Going | ₱892.9M | 38% | High risk74 | Flagged0.066 |
| 23DL0079ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF MISSING LINKS/ NEW ROADS 1. MSR JCT CANDA - HONDAGUA ROMA POINT - QUEZON ROAD, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱51.1M | 100% | High risk73 | —-0.039 |
| 22A00004REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES, PATAPAT VIADUCT (B00547LZ) ALONG MANILA NORTH ROAD (PHASE III) | Region I | Region I | Completed | ₱178.5M | 100% | High risk73 | —-0.017 |
| 19DL0124A. ORGANIZATIONAL OUTCOME 1. ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 1. NETWORK DEVELOPMENT PROGRAM B. CONSTRUCTION OF MISSING LINKS/ NEW ROADS 4. MSR JCT CANDA-HONDAGUA ROMA POINT - QUEZON ROAD, PACKAGE B, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱45.1M | 100% | High risk72 | —-0.040 |
| 19A00134BRIDGE REHABILITATION : REHABILITATION OF PATAPAT VIADUCT/BRIDGE, PAGUDPUD, ILOCOS NORTE | Region I | Region I | Completed | ₱144.7M | 100% | High risk72 | —-0.023 |
| 20D00048FY 2020 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF MISSING LINKS / NEW ROADSMSR JCT CANDA HONDAGUA ROMA POINTQUEZON ROAD, PACKAGE A, QUEZON | Region IV-A | Region IV-A | Completed | ₱193M | 100% | High risk68 | —-0.005 |
| 19D00029FY 2019 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS MSR JCT CANDA- HONDAGUA ROMA POINT-QUEZON ROAD PACKAGE A, QUEZON | Region IV-A | Region IV-A | Completed | ₱142.8M | 100% | High risk67 | —-0.038 |
| 24D00012CONSTRUCTION OF BYPASS AND DIVERSION ROADS GUINAYANGAN - TAGKAWAYAN DIVERSION ROAD, PACKAGE B, QUEZON | Region IV-A | Region IV-A | On-Going | ₱276.8M | 22% | High risk67 | Flagged0.032 |
| 24D00014CONSTRUCTION OF MISSING LINKS / NEW ROADS MSR JCT CANDA - HONDAGUA ROMA POINT ROAD, PACKAGE B, QUEZON | Region IV-A | Region IV-A | On-Going | ₱369.8M | 58% | High risk67 | Flagged0.024 |
| 23D00081CONSTRUCTION OF BY-PASS AND DIVERSION ROADS GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, (CONSTRUCTION OF BRIDGE), QUEZON | Region IV-A | Region IV-A | On-Going | ₱277.7M | 100% | High risk67 | Flagged0.018 |
| 24D00011CONSTRUCTION OF BYPASS AND DIVERSION ROADS GUINAYANGAN - TAGKAWAYAN DIVERSION ROAD, PACKAGE A, QUEZON | Region IV-A | Region IV-A | On-Going | ₱284.7M | 89% | High risk67 | Flagged0.011 |
| 21D00059FY 2021 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONST.N OF MISSING LINKS/ NEW ROADS MSR JCT CANDA-HONDAGUA ROMA POINT -QUEZON ROAD, INCL. BRIDGE (QUEZON SIDE), QUEZON | Region IV-A | Region IV-A | Completed | ₱270.2M | 100% | High risk67 | —-0.010 |
| 21D00058ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS MSR JCT CANDA-HONDAGUA ROMA POINT-QUEZON ROAD, INCL. BRIDGE (LOPEZ SIDE), QUEZON | Region IV-A | Region IV-A | Completed | ₱270.2M | 100% | High risk67 | —-0.015 |
| 18D00036ENSURE SAFE & RELIABLE NAT'L. ROAD & NETWORK DEVELOPMENT PROGRAM, CONST. OF MISSING LINKS/NEW ROADS, MSR JCT. CANDA-HONDAGUA ROMA POINT-QUEZON ROAD PACKAGE B, INCL. BRIDGE, QUEZON | Region IV-A | Region IV-A | Completed | ₱235.8M | 100% | High risk67 | —-0.016 |
| 25D00012CONSTRUCTION OF MISSING LINKS/ NEW ROADS MSR JCT CANDA - HONDAGUA-ROMA POINT ROAD, PACKAGE C | Region IV-A | Region IV-A | On-Going | ₱181.1M | 33% | High risk66 | Flagged0.006 |
| 23D00013CONSTRUCTION OF MISSING LINKS / NEW ROADSMSR JCT CANDA - HONDAGUA ROMA POINT-QUEZON ROAD, INCL. BRIDGE (LOPEZ SIDE), (PHASE 1), QUEZON | Region IV-A | Region IV-A | Completed | ₱179.7M | 100% | High risk66 | —-0.035 |
| 23D00012CONSTRUCTION OF MISSING LINKS / NEW ROADSMSR JCT CANDA-HONDAGUA ROMA POINT-QUEZON ROAD, (LOPEZ SIDE), (PHASE 2), QUEZON | Region IV-A | Region IV-A | Completed | ₱179.5M | 100% | High risk66 | —-0.035 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19A00118CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG CITY BY-PASS ROAD, BRIDGE PACKAGE, ILOCOS NORTE | Region I | Region I | On-Going | ₱892.9M | 38% | High risk74 | Flagged0.066 |
| 25A00427CONSTRUCTION OF NEW BRIDGES, PANCIAN VIADUCT ALONG MANILA NORTH RD (PHASE IV) | Region I | Region I | On-Going | ₱298.6M | 1% | High risk94 | Flagged0.066 |
| 25A00306SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BOLINAO TO SANTIAGO ISLAND, BOLINAO, PANGASINAN (PACKAGE 2) | Region I | Region I | On-Going | ₱110.8M | 1% | High risk96 | Flagged0.057 |
| 25A00305SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BOLINAO TO SANTIAGO ISLAND, BOLINAO, PANGASINAN (PACKAGE 1) | Region I | Region I | On-Going | ₱93.6M | 1% | High risk96 | Flagged0.055 |
| 24A00070REPLACEMENT OF PERMANENT WEAK BRIDGES, CARLOS P. ROMULO BR. (B00885LZ) ALONG CAMILING-WAWA-BAYAMBANG-MALASIQUI-STA. BARBARA RD | Region I | Region I | On-Going | ₱280.6M | 2% | High risk63 | Flagged0.036 |
| 24D00012CONSTRUCTION OF BYPASS AND DIVERSION ROADS GUINAYANGAN - TAGKAWAYAN DIVERSION ROAD, PACKAGE B, QUEZON | Region IV-A | Region IV-A | On-Going | ₱276.8M | 22% | High risk67 | Flagged0.032 |
| 25A00303WIDENING OF PERMANENT BRIDGES - AMBURAYAN PARALLEL BR. ALONG MANILA NORTH RD | Region I | Region I | On-Going | ₱47.7M | 0% | High risk64 | Flagged0.030 |
| 25A00312REPLACEMENT OF PERMANENT WEAK BRIDGES - CARLOS P. ROMULO BR. (B00885LZ) ALONG CAMILING-WAWA-BAYAMBANG-MALASIQUI-STA. BARBARA ROAD, PHASE II | Region I | Region I | On-Going | ₱187.2M | 1% | High risk63 | Flagged0.026 |
| 24D00014CONSTRUCTION OF MISSING LINKS / NEW ROADS MSR JCT CANDA - HONDAGUA ROMA POINT ROAD, PACKAGE B, QUEZON | Region IV-A | Region IV-A | On-Going | ₱369.8M | 58% | High risk67 | Flagged0.024 |
| 23D00081CONSTRUCTION OF BY-PASS AND DIVERSION ROADS GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, (CONSTRUCTION OF BRIDGE), QUEZON | Region IV-A | Region IV-A | On-Going | ₱277.7M | 100% | High risk67 | Flagged0.018 |
| 24A00006CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG-SAN FERNANDO-SAN JUAN BYPASS ROAD, (BAUANG SECTION), PACKAGE 2, LA UNION | Region I | Region I | On-Going | ₱290.5M | 99% | High risk61 | Flagged0.016 |
| 24D00013CONSTRUCTION OF MISSING LINKS / NEW ROADSMSR JCT CANDA - HONDAGUA ROMA POINT ROAD, PACKAGE A, QUEZON | Region IV-A | Region IV-A | On-Going | ₱380.9M | 93% | High risk66 | Flagged0.014 |
| 23A00152CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BAUANG-SAN FERNANDO-SAN JUAN BYPASS ROAD, (BAUANG SECTION), PACKAGE 1, LA UNION | Region I | Region I | On-Going | ₱173.3M | 99% | High risk61 | Flagged0.014 |
| 24A00362SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF BRIDGE CONNECTING BOLINAO TO SANTIAGO ISLAND (PACKAGE A), BOLINAO, PANGASINAN | Region I | Region I | On-Going | ₱28.3M | 2% | Medium risk46 | Flagged0.012 |
| 24D00011CONSTRUCTION OF BYPASS AND DIVERSION ROADS GUINAYANGAN - TAGKAWAYAN DIVERSION ROAD, PACKAGE A, QUEZON | Region IV-A | Region IV-A | On-Going | ₱284.7M | 89% | High risk67 | Flagged0.011 |
| 25D00012CONSTRUCTION OF MISSING LINKS/ NEW ROADS MSR JCT CANDA - HONDAGUA-ROMA POINT ROAD, PACKAGE C | Region IV-A | Region IV-A | On-Going | ₱181.1M | 33% | High risk66 | Flagged0.006 |
| 25D00013CONSTRUCTION OF NEW BRIDGES LOPEZ VIADUCT ALONG MAHARLIKA HIGHWAY (PHASE III) | Region IV-A | Region IV-A | On-Going | ₱131M | 16% | High risk65 | Flagged0.005 |
| 25D00146CONSTRUCTION OF MISSING LINKS/ NEW ROADS MSR JCT CANDA - HONDAGUA ROMA POINT - QUEZON ROAD, QUEZON, PACKAGE B | Region IV-A | Region IV-A | On-Going | ₱93.6M | 0% | High risk64 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 22DL0181ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF MISSING LINKS/ NEW ROADS 5. MSR JCT CANDA - HONDAGUA ROMA POINT - QUEZON ROAD, PACKAGE A, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱52.1M | 100% | Medium risk52 | —-0.100 |
| 77 | 25D00050ROAD WIDENING - PRIMARY ROADS MAHARLIKA HIGHWAY - K0218 + 771 - K0219 + 004, K0220 + 455 - K0221 +153, K0221 + 168 - K0221 + 559, K0221 + 596 - K0221 + 829 | Region IV-A | Region IV-A | On-Going | ₱51.3M | 10% | Medium risk52 | —-0.045 |
| 78 | 23D00203CONSTRUCTION OF LOPEZ VIADUCT ALONG DAANG MAHARLIKA, LOPEZ, QUEZON | Region IV-A | Region IV-A | On-Going | ₱49.4M | 65% | Medium risk51 | —-0.012 |
| 79 | 20DL0129A. ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 2. NETWORK DEVELOPMENT PROGRAM B. CONSTRUCTION OF BY-PASS AND DIVERSION ROADS 2. GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, PACKAGE B, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱46.9M | 100% | Medium risk51 | —-0.062 |
| 80 | 21DL0165ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS 1. GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, GUINAYANGAN SECTION, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.061 |
| 81 | 20OB0419CONSTRUCTION/REHABILITATION OF FORTUNE-MODESTA BRIDGE, BRGY. FORTUNE, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱47M | 100% | Medium risk51 | —-0.065 |
| 82 | 20DL0137A. ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 2. NETWORK DEVELOPMENT PROGRAMC. CONSTRUCTION OF MISSING LINKS/ NEW ROADS 3. MSR JCT CANDA - HONDAGUA ROMA POINT - QUEZON ROAD, QUEZON PACKAGE A | Region IV-A | Quezon 4th DEO | Completed | ₱46.9M | 100% | Medium risk50 | —-0.103 |
| 83 | 20A00024REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES, AMBURAYAN BR. (B00598LZ) ALONG MANILA NORTH RD (PHASE III) | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk50 | —-0.047 |
| 84 | 19A00022CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS- CONSTRUCTION OF CALUNGBUYAN BRIDGE ALONG SANTA-RANCHO ROAD, SANTA, ILOCOS SUR | Region I | Region I | Completed | ₱56.8M | 100% | Medium risk50 | —-0.079 |
| 85 | 23DN0033CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, APIA RIVER, BARANGAY CALAWIS ANTIPOLO CITY (SECOND DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.087 |
| 86 | 19A00017CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL SYSTEM ALONG ABRA RIVER (UPSTREAM AND DOWNSTREAM) OF CALUNGBUYAN BRIDGE, SANTA, ILOCOS SUR | Region I | Region I | Completed | ₱57.1M | 100% | Medium risk49 | —-0.062 |
| 87 | 25D00035CONSTRUCTION OF BY-PASS AND DIVERSION ROADS GUINAYANGAN -TAGKAWAYAN DIVERSION ROAD, PACKAGE D, QUEZON | Region IV-A | Region IV-A | On-Going | ₱46.5M | 15% | Medium risk48 | —-0.011 |
| 88 | 19DL0176A. ORGANIZATIONAL OUTCOME 1. ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 2. NETWORK DEVELOPMENT PROGRAM A. CONSTRUCTION OF BY-PASS AND DIVERSION ROADS 2. GUINAYANGAN-TAGKAWAYAN DIVERSION ROAD, PACKAGE B, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱45.1M | 100% | Medium risk48 | —-0.063 |
| 89 | 18A00112CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF NEW PERMANENT BRIDGE, TINAAN BRIDGE ALONG STA MARIA-BABALLASIOAN ROAD LEADING TO PINSAL FALLS, ILOCOS SUR | Region I | Region I | Completed | ₱43.4M | 100% | Medium risk48 | —-0.045 |
| 90 | 25D00062WIDENING OF PERMANENT BRIDGES INALAKANAN BR. (B02590LZ) ALONG MAHARLIKA HIGHWAY | Region IV-A | Region IV-A | On-Going | ₱18.7M | 15% | Medium risk47 | —-0.012 |
| 91 | 24A00362SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF BRIDGE CONNECTING BOLINAO TO SANTIAGO ISLAND (PACKAGE A), BOLINAO, PANGASINAN | Region I | Region I | On-Going | ₱28.3M | 2% | Medium risk46 | Flagged0.012 |
| 92 | 22A00317REHABILITATION/RECONSTRUCTION OF VARIOUS INFRASTRUCTURES DAMAGED BY EARTHQUAKE IN REGION 1, REHABILITATION OF FLOOD CONTROL SYSTEM ALONG ABRA RIVER, CALUNGBUYAN BRIDGE, SANTA, ILOCOS SUR | Region I | Region I | Completed | ₱28.3M | 100% | Medium risk45 | —-0.067 |
| 93 | 19A00124CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION/IMPROVEMENT OF STA. MARIA-BABALLASIOAN ROAD INCLUDING TINAAN BRIDGE LEADING TO PINSAL FALLS, STA. MARIA, ILOCOS SUR | Region I | Region I | Completed | ₱19.3M | 100% | Medium risk44 | —-0.086 |
| 94 | 18A00135REHABILITATION OF FLOOD CONTROL AND DRAINAGE STRUCTURES ALONG ABRA RIVER, SANTA, ILOCOS SUR | Region I | Region I | Completed | ₱8.5M | 100% | Medium risk43 | —-0.067 |