66 projects on file, including joint ventures this contractor is part of.
Total projects
66
Total budget
₱2.5B
Average progress
97.2%
Completion rate
78.8%
Average risk score
41.2
Medium risk on average, out of 100
Flagged as unusual
1
1.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Negros Island Region | 61 | ₱1.9B | 39.8 | 1 | 97.9% |
| Region VI | 5 | ₱572.5M | 58.1 | 0 | 87.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱95.7M | 16.9 | 0 | 99.9% |
| Flood Control and Drainage | 21 | ₱1.5B | 53.5 | 0 | 99.3% |
| Roads | 12 | ₱624.7M | 48.8 | 0 | 89.5% |
| Bridges | 8 | ₱55.2M | 47.2 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱96.5M | 93.6 | 0 | 81.7% |
| GAA 2025 OO-1 | 1 | ₱26.9M | 90.8 | 0 | 95.0% |
| OTHER | 1 | ₱39.6M | 74.0 | 1 | 78.5% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GM0011CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG ILOG - BUNGOL RIVER, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | On-Going | ₱96.5M | 82% | High risk94 | —-0.008 |
| 25GO0012OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF SIDEWALK - BACOLOD-SN CARLOS RD - K0012 + 000 - K0013 + 580 | Negros Island Region | Bacolod City DEO | On-Going | ₱26.9M | 95% | High risk91 | —-0.010 |
| 24GO0089CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANSILINGAN, PHASE 2, BACOLOD CITY | Negros Island Region | Bacolod City DEO | On-Going | ₱39.6M | 79% | High risk74 | Flagged0.000 |
| 17RD0054CONSTRUCTION OF REVETMENT WALL ALONG ILOG-HILABANGAN RIVER CONTROL, SITIO PARIL, BRGY. VI, KABANKALA | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱46.5M | 100% | High risk66 | —-0.043 |
| 24GO0017CONSTRUCTION OF REVETMENT WITH FLOODWALL IN LOYGOY RIVER, PHASE 2, BACOLOD CITY, NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱144.8M | 100% | High risk65 | —-0.040 |
| 24GO0018CONSTRUCTION OF REVETMENT IN LUPIT RIVER, PHASE 8, BACOLOD CITY, NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱144.8M | 100% | High risk65 | —-0.043 |
| 22G00065CONSTRUCTION OF REVETMENT WITH FLOODWALL ALONG LUPIT RIVER, PHASE 6, BACOLOD CITY | Region VI | Region VI | Completed | ₱125.5M | 100% | High risk64 | —-0.050 |
| 24GO0016CONSTRUCTION OF FLOOD CONTROL STRUCTURE , BRGY. PAHANOCOY, PHASE 4, BACOLOD CITY, NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | On-Going | ₱118.5M | 98% | High risk63 | —-0.021 |
| 21G00156BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SECTION 1, SEGMENT 3, NEGROS OCCIDENTAL | Region VI | Region VI | Completed | ₱183.9M | 100% | High risk63 | —-0.043 |
| 24GM0016CONSTRUCTION OF FLOOD MITIGATION STUCTURE-CONSTRUCTION OF FLOOD MITIGATION STUCTURE ALONG ILOG-BUNGOL RIVER (DOWNSTREAM OF APPROACH A OF MALABONG BR.), ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱110.1M | 100% | High risk62 | —-0.054 |
| 22GM0021CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG ILOG - HILABANGAN RIVER, KABANKALAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.051 |
| 23GO0013CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF LUPIT RIVER FLOOD CONTROL STRUCTURE, PHASE 7, BACOLOD CITY, NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.055 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GO0089CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANSILINGAN, PHASE 2, BACOLOD CITY | Negros Island Region | Bacolod City DEO | On-Going | ₱39.6M | 79% | High risk74 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 18RD0004CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) PINAGUINPINAN NHS, KABANKALAN CITY, NEGROS O | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.087 |
| 52 | 18GM0005CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) ORONG ELEMENTARY SCHOOL, BRGY. ORONG, KABANKA | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.087 |
| 53 | 18GM0031CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. ELIHAN, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.084 |
| 54 | 18GM0012(RE-BIDDING) CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. BACLAO, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.084 |
| 55 | 18GM0001CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY YAOYAO, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.084 |
| 56 | 18GM0017(RE-BIDDING) CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. TALACDAN, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.084 |
| 57 | 18GM0003CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. MOLOBOLO, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.084 |
| 58 | 18GM0018CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. TOMINA, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.085 |
| 59 | 18GM0019(RE-BIDDING)-CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. TAMBAD, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.085 |
| 60 | 18RD0020CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. PINGGOT, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.086 |
| 61 | 18RD0010CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. DELICIOSO, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.087 |
| 62 | 18GM0009CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. VISTA ALEGRE, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.087 |
| 63 | 18RD0014CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. 2 ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.8M | 100% | Low risk13 | —-0.087 |
| 64 | 18RD0008CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) CAMANSI ELEMENTARY SCHOOL, CAMANSI, KABANKALA | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.8M | 100% | Low risk13 | —-0.085 |
| 65 | 18GM0006CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) DAAN BANWA ELEMENTARY SCHOOL, BRGY. DAAN BANW | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.086 |
| 66 | 18GM0016CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) TALUBANGI NHS, BRGY. TALUBANGI, KABANKALAN CI | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.087 |