Contractor dossier
118 projects on file, including joint ventures this contractor is part of.
Total projects
118
Total budget
₱4.6B
Average progress
93.5%
Completion rate
81.4%
Average risk score
43.8
Medium risk on average, out of 100
Flagged as unusual
5
4.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 96 | ₱3.7B | 42.6 | 4 | 93.3% |
| National Capital Region | 14 | ₱378.2M | 43.1 | 0 | 100.0% |
| Region IV-A | 6 | ₱426.8M | 54.8 | 0 | 83.0% |
| Region VI | 2 | ₱158.7M | 73.9 | 1 | 90.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 44 | ₱2.5B | 49.1 | 3 | 92.5% |
| Buildings and Facilities | 37 | ₱1B | 38.4 | 1 | 93.2% |
| Roads | 30 | ₱919.1M | 38.0 | 0 | 94.5% |
| OTHER | 6 | ₱110.3M | 59.7 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱96M | 96.2 | 1 | 81.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GI0069CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE, BARANGAY MANASA, ALIMODIAN, ILOILO (SITE 3) | Region VI | Iloilo 4th DEO | On-Going | ₱96M | 82% | High risk96 | Flagged0.027 |
| 24CC0548CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk81 | Flagged0.008 |
| 24CC0547CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY CALERO CREEK, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 51% | High risk81 | —-0.006 |
| 25CC0330CONSTRUCTION OF PUMPING STATION AND FLOOD GATE AT CALERO CREEK, PHASE II, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.5M | 0% | High risk80 | Flagged0.005 |
| 24CC0560CONSTRUCTION OF NEW PANDI MUNICIPAL HALL, BARANGAY POBLACION, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱95M | 13% | High risk80 | Flagged0.003 |
| 24CC0549CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH WATER PUMPING AT BARANGAY BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 94% | High risk79 | —-0.022 |
| 24CC0037CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG GUIGUINTO RIVER, BARANGAY DAUNGAN, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.051 |
| 24CC0050CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY BAGBAGUIN, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.051 |
| 23CC0483REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BRGYS. PANGINAY TO WAWA (PHASE III), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk77 | —-0.004 |
| 25CP0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD,PHASE III, SITIO TALAMSI I-SITIO KA | Region III | Bulacan 3rd DEO | On-Going | ₱142.5M | 24% | High risk77 | —-0.003 |
| 25CC0191CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY MALIS (PUROK 3), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 64% | High risk76 | —-0.017 |
| 25CC0181CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE B) AT BARANGAY MALIS (PUROK 3), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱77.2M | 81% | High risk76 | —-0.025 |
| 24C00592CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRA PROG.-MULTI-PURPOSE BLDGS./FACILITIES TO SUPP. SOCIAL SERVICES: 1.CONST. OF MPB BRGY. IBAYO, 2. CONST. OF MPB BRGY. PRENZA 1, 3. CONST. OF MPB, BRGY. LIAS, MARILAO, BULACAN, PROV. OF BULACAN | Region III | Region III | On-Going | ₱54.4M | 71% | High risk76 | —-0.027 |
| 24C00318CONVERGENCE & SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-REHABILITATION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. SAN PASCUAL, OBANDO, BULACAN | Region III | Region III | On-Going | ₱14.8M | 100% | High risk73 | —-0.042 |
| 24C00304CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEAD. TO MAJ./STRATEGIC PULIC BLDGS./FACILITIES, CONST. OF ROAD, FLAMENCO ST., BRGY. PANGHULO, OBANDO | Region III | Region III | On-Going | ₱47.5M | 92% | High risk73 | —-0.037 |
| 25C00495CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRASTRUCTURE PROG.-MULTI-PURPOSE BLDGS./FACILITIES TO SUPPORT SOCIAL SERVICES-CONST. OF MULTI-PURPOSE BLDG. 1.)BRGY. HEALTH CENTER, MARILAO 2.)BRGY. NAGBALON, MARILAO 3.) BRGY. PATUBIG, MARILAO, BULACAN, PROV. OF B | Region III | Region III | On-Going | ₱43.9M | 82% | High risk72 | —-0.037 |
| 24C00538CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING BULIRAN ELEMENTARY SCHOOL,BARANGAY BULIRAN,SAN MIGUEL,BULACAN | Region III | Region III | On-Going | ₱29.3M | 100% | High risk72 | —-0.042 |
| 24CC0638CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOCAUE RIVER, BARANGAY BAMBANG (SITIO ATUBANG), BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱46.3M | 98% | High risk70 | Flagged0.019 |
| 17CD0146IMPROVEMENT/REPAIR/REHABILITATION OF EXISTING FLOOD CONTROL OF ZAMORA PUMPING STATION AND ITS TRIBUTARIES, BARANGAY ZAMORA, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.4M | 100% | High risk69 | —-0.064 |
| 17CD0025IMPROVEMENT/REHABILITATION OF CITYLAND, PULONG BUHANGIN, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.4M | 100% | High risk69 | —-0.068 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GI0069CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE, BARANGAY MANASA, ALIMODIAN, ILOILO (SITE 3) | Region VI | Iloilo 4th DEO | On-Going | ₱96M | 82% | High risk96 | Flagged0.027 |
| 24CC0638CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOCAUE RIVER, BARANGAY BAMBANG (SITIO ATUBANG), BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱46.3M | 98% | High risk70 | Flagged0.019 |
| 24CC0548CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk81 | Flagged0.008 |
| 25CC0330CONSTRUCTION OF PUMPING STATION AND FLOOD GATE AT CALERO CREEK, PHASE II, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.5M | 0% | High risk80 | Flagged0.005 |
| 24CC0560CONSTRUCTION OF NEW PANDI MUNICIPAL HALL, BARANGAY POBLACION, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱95M | 13% | High risk80 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 23CC0488CONSTRUCTION OF BALAGTAS RIVER FLOOD MITIGATION STRUCTURE (STA. 03+533 TO STA. 03+683) AT BRGY. SANTOL, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk46 | —-0.026 |
| 52 | 20OA0004CONST. OF RIVERWALL AND ROAD DIKE (PHASE 7) BRGY. DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱35.9M | 100% | Medium risk46 | —-0.085 |
| 53 | 23C00212CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRA. PROG.-MULTI-PURPOSE BLDGS./FACILITIES TO SUPPORT SOCIAL SERVICES: 1. CONST. OF MULTI-PURPOSE FACILITY (STA. MARIA STADIUM), BRGY. POBLACION 2. CONST. OF MULTI-PURPOSE BLDG. AT MUN. HALL GROUNDS, BRGY. POBLACIO | Region III | Region III | On-Going | ₱77.6M | 73% | Medium risk45 | —-0.043 |
| 54 | 23C00141CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILINDGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONST. OF MULTI-PURPOSE FACILITY (OBANDO STADIUM), BRGY. TAWIRAN, OBANDO, BULACAN, PROV. OF BULACAN | Region III | Region III | Completed | ₱49.5M | 100% | Medium risk43 | —-0.097 |
| 55 | 19CD0092UPGRADING OF ROAD INCLUDING DRAINAGE, T. MENDOZA ST., SAOG, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.7M | 100% | Medium risk42 | —-0.042 |
| 56 | 23CC0312CONSTRUCTION OF MULTI-PURPOSE BUILDING AT ENGR. VIRGILIO DIONISIO NATIONAL HIGH SCHOOL, POBLACION, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱29.7M | 100% | Medium risk41 | —-0.102 |
| 57 | 23C00208CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRA. PROG. MULIT-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONST. OF MPB 1.NOR HOMES, BRGY. BITUNGOL NORZAGARAY 2. BRGY. MATICTIC, NORZAGARAY 3. SITIO KAYPAYA, BRGY. BIGTE NORZAGARAY 4. EVAC. CENTERS | Region III | Region III | On-Going | ₱38.8M | 53% | Medium risk40 | —-0.039 |
| 58 | 23CC0316CONSTRUCTION O FLOOD CONTROL PROJECT AND REHABILITATION OF WATERWAYS ALONG BOCAUE RIVER BRGY. BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱74.2M | 100% | Medium risk40 | —-0.089 |
| 59 | 22CD0123CONSTRUCTION OF MULTI-PURPOSE BUILDING, ST. ROSE, LOMA DE GATO, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱19.6M | 100% | Medium risk39 | —-0.104 |
| 60 | 23C00213CONVERGENCE & SPL. SUPPORT PROG.-BIP-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RD./S LEAD. TO MAJ./STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF RD. BRGY. PULONG AT BRGR. YANTOC, ANGAT, CONST. OF RD. W/DRAINAGE CANAL BRGY. STA. CRUZ II, SJDM, CONST. OF RDS. BRGY. | Region III | Region III | Completed | ₱54.4M | 100% | Medium risk39 | —-0.101 |
| 61 | 19CD0219CONSTRUCTION/IMPROVEMENT OF PUMPING STATION BISITA - SALUYSOY, MEYCAUAYAN RIVER | Region III | Bulacan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.090 |
| 62 | 25C00494CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BLDGS./FACILITIES TO SUPPORT SOCIAL SERVICES-CONST. OF MULTI-PURPOSE BLDG.: 1.)BRGY. BULAC, STA. MARIA 2.)BRGY. STA. CRUZ, STA. MARIA 3.)BRGY. MAG-ASAWANG SAPA, STA. MARIA, BULACA | Region III | Region III | On-Going | ₱39M | 58% | Medium risk38 | —-0.051 |
| 63 | 24CD0256CONSTRUCTION OF MULTI - PURPOSE FACILITY (SANTA MARIA STADIUM), BARANGAY POBLACION, STA. MARIA, BULACAN (PHASE 2) | Region III | Bulacan 2nd DEO | Completed | ₱29.4M | 100% | Medium risk37 | —-0.102 |
| 64 | 19CD0314CONSTRUCTION / REHABILITATION OF MULTI PURPOSE BUILDING BRGY. STO. TOMAS, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.2M | 100% | Medium risk37 | —-0.106 |
| 65 | 23C00211CONVERGENCE & SPL. SUPPORT PROG.-BASIC INFRA PROG.-MULTI-PURPOSE BLDGS./FACILITIES TO SUPPORT SOCIAL SERVICES: 1.CONST. OF MPB AT BRGY. CAYPOMBO, 2. CONST. OF MPB BAGBAGUIN, 3. CONST. OF MPB BRGY. GUYONG, STA. MARIA, BULACAN | Region III | Region III | Completed | ₱34.6M | 100% | Medium risk37 | —-0.101 |
| 66 | 23CC0224CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PANGINAY (LS), BALAGTAS, BULACAN (K014+770 TO K014+920), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk37 | —-0.088 |
| 67 | 24C00317CONVERGENCE & SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY MAG-ASAWANG SAPA, STA. MARIA, BULACAN | Region III | Region III | Completed | ₱19.8M | 100% | Medium risk36 | —-0.105 |
| 68 | 21CC0192CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOCAUE RIVER, BAMBANG SECTION, STA. 03+278 - STA. 03+589, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | Medium risk36 | —-0.090 |
| 69 | 19CC0246CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING AT ILUMINIDA ROXAS MENDOZA MEMORIAL HIGH SCHOOL BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.8M | 100% | Medium risk36 | —-0.108 |
| 70 | 24CC0320CONSTRUCTION OF MULTI-PURPOSE BUILDING (STA. BARBARA HIGH SCHOOL), STA. BARBARA, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱34.6M | 100% | Medium risk36 | —-0.101 |
| 71 | 23CC0216CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGBAG CREEK, BARANGAY PRITIL, GUIGUINTO, BULACAN (K003+220 TO K003+420) GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk35 | —-0.088 |
| 72 | 23CC0226CONSTRUCTION OF REVETMENT ALONG HAGONOY RIVER AT BARANGAY SANTA CRUZ, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk35 | —-0.089 |
| 73 | 19CD0100IMPROVEMENT OF MARILAO RIVER SYSTEM, IBAYO CREEK, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱37.2M | 100% | Medium risk35 | —-0.092 |
| 74 | 20CD0154CONCRETING OF ROAD, STO. TOMAS, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.4M | 100% | Medium risk35 | —-0.105 |
| 75 | 23CC0394CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY PAGALA, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱19.8M | 100% | Medium risk35 | —-0.103 |