Contractor dossier
9 projects on file, including joint ventures this contractor is part of.
Total projects
9
Total budget
₱61.3M
Average progress
87.8%
Completion rate
44.4%
Below 70%
Average risk score
52.1
Medium risk on average, out of 100
Flagged as unusual
1
11.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 9 | ₱61.3M | 52.1 | 1 | 87.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 4 | ₱30.8M | 42.0 | 0 | 97.9% |
| Roads | 3 | ₱17.7M | 39.3 | 0 | 75.2% |
| GAA 2025 SSP | 1 | ₱4.9M | 94.8 | 1 | 74.9% |
| GAA 2025 OO-2 | 1 | ₱7.8M | 87.8 | 0 | 97.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PK0039BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BARANGAY BASAO, TINGLAYAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.9M | 75% | High risk95 | Flagged0.016 |
| 25PK0014ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱7.8M | 98% | High risk88 | —-0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PK0039BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BARANGAY BASAO, TINGLAYAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.9M | 75% | High risk95 | Flagged0.016 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PK0039BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BARANGAY BASAO, TINGLAYAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.9M | 75% | High risk95 | Flagged0.016 |
| 2 | 25PK0014ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱7.8M | 98% | High risk88 | —-0.005 |
| 3 | 24PK0029ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CHALIYONG - KUB-AO FLOOD CONT | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱5.9M | 93% | Medium risk46 | —-0.026 |
| 4 | 24PK0014ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF TABIONG FLOOD CONTROL ALONG CHICO RIVER, STA. 188+950 | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱8.8M | 100% | Medium risk46 | —-0.068 |
| 5 | 24PK0033ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF NGILIN FLOOD CONTROL ALONG C | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱11.7M | 100% | Medium risk46 | —-0.066 |
| 6 | 24PK0040BASIC INFRASTRUCTURE PROGRAM (BIP) BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES CONSTRUCTION OF ACCESS ROAD IN BARANGAY BASAO, TINGLAYAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.9M | 25% | Medium risk46 | —-0.024 |
| 7 | 23PK0046BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF LOCAL ROAD, TINGLAYAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.082 |
| 8 | 24PK0012ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: REHABILITATION OF LUPLUPA FLOOD CONTROL ALON | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱4.4M | 98% | Medium risk30 | —-0.026 |
| 9 | 23PK0062ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY MT. PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT ROAD K0423+645, TINGLAYAN, KALI | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱2.9M | 100% | Low risk27 | —-0.081 |