Contractor dossier
224 projects on file, including joint ventures this contractor is part of.
Total projects
224
Total budget
₱35.6B
Average progress
91.6%
Completion rate
75.9%
Average risk score
59.4
Medium risk on average, out of 100
Flagged as unusual
48
21.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 88 | ₱7.1B | 57.3 | 9 | 97.9% |
| Region XI | 61 | ₱14.2B | 62.1 | 19 | 92.1% |
| Region XIII | 17 | ₱2B | 44.6 | 0 | 96.5% |
| Region VI | 13 | ₱2.4B | 67.9 | 6 | 81.1% |
| Region X | 12 | ₱2.9B | 58.7 | 0 | 100.0% |
| National Capital Region | 7 | ₱1.5B | 65.1 | 2 | 85.0% |
| Region I | 5 | ₱1.3B | 72.8 | 5 | 49.2% |
| Region IV-B | 5 | ₱878M | 65.7 | 4 | 80.0% |
| Region III | 5 | ₱1.1B | 62.1 | 1 | 8.6% |
| Central Office | 3 | ₱1.3B | 64.5 | 1 | 100.0% |
| Region IV-A | 3 | ₱414.5M | 61.6 | 1 | 100.0% |
| Region VII | 3 | ₱142M | 50.6 | 0 | 100.0% |
| Region V | 2 | ₱349.5M | 69.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 136 | ₱19B | 55.8 | 16 | 92.5% |
| Bridges | 22 | ₱3B | 59.1 | 7 | 87.6% |
| OTHER | 21 | ₱4.2B | 80.4 | 13 | 93.8% |
| Flood Control and Drainage | 20 | ₱2.2B | 58.5 | 4 | 91.5% |
| Bridges, Roads | 18 | ₱6.3B | 64.3 | 7 | 90.8% |
| Buildings and Facilities | 6 | ₱814.6M | 55.9 | 1 | 78.9% |
| Water Provision and Storage | 1 | ₱93.6M | 62.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18I00083REPLACEMENT OF MOTHER MARY BAILEY BRIDGE, NAVAL, BILIRAN | Region VIII | Region VIII | Completed | ₱144.7M | 100% | High risk90 | Flagged0.046 |
| 23G00095CONSTRUCTION OF MULTI-PURPOSE FACILITY (MEDICAL ARTS BUILDING PARKING), ILOILO CITY HOSPITAL, BRGY. SAN PEDRO MOLO, ILOILO CITY | Region VI | Region VI | On-Going | ₱193M | 59% | High risk85 | Flagged0.042 |
| 24GI0105PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO EAST COAST-CAPIZ RD - K0286 + 280 - K0288 + 124 | Region VI | Iloilo 4th DEO | On-Going | ₱130.1M | 81% | High risk84 | Flagged0.019 |
| 24GI0088PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO EAST COAST-CAPIZ RD - K0284 + 777 - K0286 + 280 | Region VI | Iloilo 4th DEO | On-Going | ₱120M | 77% | High risk84 | Flagged0.019 |
| 20I00034CLUSTER 4: 1. ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DDANG MAHARLIKA (LT) - K0986+500 - K0988+871, LEYTE 5TH LD; 2. NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K0986+000 - K0986+000 - K0987+000, KO98 | Region VIII | Region VIII | Completed | ₱207.4M | 100% | High risk84 | —-0.008 |
| 18I00060CONSTRUCTION OF CONCRETE ROAD - ORMOC CITY DIVERSION ROAD, (BRGY. SAN JUAN - LAO - NAUNGAN), PACKAGE C1, LEYTE, ORMOC CITY | Region VIII | Region VIII | Completed | ₱183.1M | 100% | High risk82 | Flagged0.002 |
| 18I00059CONSTRUCTION OF CONCRETE ROAD - ORMOC CITY DIVERSION ROAD, (BRGY. SAN JUAN - LAO - NAUNGAN), PACKAGE C, LEYTE, ORMOC CITY | Region VIII | Region VIII | Completed | ₱175.1M | 100% | High risk82 | Flagged0.002 |
| 20I00007NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD., K1000+733 - K1001+140; K1001+159 - K1001+455; K1001+466 - K1001+687; K1001+703 - K1002+560; K1002+640 - K1003+380; K1003+860 - K1004+435; K1004+460 - K1004+551, LEY | Region VIII | Region VIII | Completed | ₱120.6M | 100% | High risk82 | —-0.019 |
| 18IF0072CONSTRUCTION OF MISSING LINKS/NEW ROADS, BURAUEN-ALBUERA ROAD, LEYTE, INCLUDING SLOPE PROTECTION (CONSTRUCTION OF CONCRETE ROAD AND CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE) | Region VIII | Leyte 4th DEO | Completed | ₱245.8M | 100% | High risk82 | —-0.006 |
| 18IF0114CONSTRUCTION OF BYPASS/ DIVERSION ROADS, ORMOC CITY DIVERSION ROAD (BRGY. SAN JUAN - LAO - NAUNGAN) PACKAGE B, LEYTE: CONSTRUCTION OF GRAVEL/ CONSTRUCTION OF CONCRETE ROAD INCLUDING SLOPE PROTECTION | Region VIII | Leyte 4th DEO | Completed | ₱96.4M | 100% | High risk82 | —-0.010 |
| 20I00057NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ORMOC CITY DIVERSION ROAD, (BRGY. SAN JUAN - LAO - NAUNGAN SECTION), LEYTE 4TH LD | Region VIII | Region VIII | Completed | ₱137.4M | 100% | High risk82 | —-0.005 |
| 18IF0113CONSTRUCTION OF BYPASS/ DIVERSION ROADS, ORMOC CITY DIVERSION ROAD (BRGY. SAN JUAN - LAO - NAUNGAN) PACKAGE A, LEYTE: CONSTRUCTION OF GRAVEL/ CONSTRUCTION OF CONCRETE ROAD INCLUDING SLOPE PROTECTION | Region VIII | Leyte 4th DEO | Completed | ₱96.5M | 100% | High risk82 | —-0.011 |
| 21IF0056CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ORMOC CITY DIVERSION ROAD (BRGY. SAN JUAN-LAO-NAUNGAN SECTION) LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱91.7M | 100% | High risk80 | —-0.019 |
| 18Z00024PR-07, TAMPILISAN - SANDAYONG ROAD, ZAMBOANGA DEL NORTE, K1981+490.00 - K1999+065.86 | Central Office | Roads Management Cluster II (Multilateral) | Completed | ₱658.2M | 100% | High risk80 | Flagged0.010 |
| 20L00005CONSTRUCTION OF CONCRETE ROAD-MAWAB-MARAGUSAN-CARAGA ROAD, SECTION 1, PACKAGE G, COMPOSTELA VALLEY | Region XI | Region XI | On-Going | ₱139M | 92% | High risk80 | Flagged0.058 |
| 18D00085FY 2018 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS ATIMONAN-MAUBAN ROAD, MAUBAN SECTION, QUEZON PROVINCE | Region IV-A | Region IV-A | Completed | ₱280.8M | 100% | High risk79 | Flagged0.017 |
| 23K00121CONST. OF MISSING LINKS/NEW ROADS, BUKIDNON-DAVAO CONNECTOR ROAD (JCT. PANGANAN-KIULOM), PACKAGE 7, BUKIDNON | Region X | Region X | Completed | ₱99.9M | 100% | High risk78 | —-0.018 |
| 24IF0038CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ORMOC CITY DIVERSION ROAD, SAN JUAN-LAO-NAUNGAN ROAD, (CONSTRUCTION OF LAO BRIDGE), LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱39.1M | 65% | High risk78 | Flagged0.012 |
| 19Z00038PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS) | National Capital Region | National Capital Region | On-Going | ₱502.3M | 95% | High risk78 | Flagged0.078 |
| 24C00235CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONST. OF ROAD, BRGY. ALAS-ASIN IPAG (PHASE I | Region III | Region III | On-Going | ₱302.6M | 0% | High risk77 | Flagged0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19Z00038PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS) | National Capital Region | National Capital Region | On-Going | ₱502.3M | 95% | High risk78 | Flagged0.078 |
| 20L00005CONSTRUCTION OF CONCRETE ROAD-MAWAB-MARAGUSAN-CARAGA ROAD, SECTION 1, PACKAGE G, COMPOSTELA VALLEY | Region XI | Region XI | On-Going | ₱139M | 92% | High risk80 | Flagged0.058 |
| 23E00306SUSTANABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF POBLACION-TAGUMPAY DIVERSION ROAD LEADING TO CORON CRUISE PORT, PACKAGE 1 | Region IV-B | Region IV-B | On-Going | ₱280.2M | 20% | High risk64 | Flagged0.057 |
| 19L00195CONSTRUCTION OF CONCRETE ROAD - MONKAYO, COMPOSTELA VALLEY - VERUELA, AGUSAN DEL SUR ROAD, DAVAO DE ORO 1ST LD | Region XI | Region XI | On-Going | ₱90.6M | 95% | Medium risk59 | Flagged0.054 |
| 25A00288CONSTRUCTION OF NEW BRIDGES, PANCIAN VIADUCT ALONG MANILA NORTH RD (PHASE III) | Region I | Region I | On-Going | ₱374.4M | 5% | High risk73 | Flagged0.049 |
| 18I00083REPLACEMENT OF MOTHER MARY BAILEY BRIDGE, NAVAL, BILIRAN | Region VIII | Region VIII | Completed | ₱144.7M | 100% | High risk90 | Flagged0.046 |
| 23O00080RETROFITTING OF COA MAINBUILDING NOS. 1 AND 2 | National Capital Region | National Capital Region | On-Going | ₱143M | 0% | High risk63 | Flagged0.043 |
| 23G00095CONSTRUCTION OF MULTI-PURPOSE FACILITY (MEDICAL ARTS BUILDING PARKING), ILOILO CITY HOSPITAL, BRGY. SAN PEDRO MOLO, ILOILO CITY | Region VI | Region VI | On-Going | ₱193M | 59% | High risk85 | Flagged0.042 |
| 23A00075WIDENING OF PERMANENT BRIDGES - BOLO PARALLEL BR. (B00541LZ) ALONG MANILA NORTH RD | Region I | Region I | On-Going | ₱170.8M | 35% | High risk73 | Flagged0.039 |
| 24A00014CONSTRUCTION OF NEW BRIDGES, PANCIAN VIADUCT ALONG MANILA NORTH ROAD (PHASE II) | Region I | Region I | On-Going | ₱289.5M | 57% | High risk73 | Flagged0.036 |
| 24L00122DAVAO CITY COASTAL BYPASS ROAD (BAGO APLAYA - TIMES BEACH - ROXAS AVENUE - STA. ANA WHARF - R. CASTILLO), PACKAGE 6, DAVAO CITY | Region XI | Region XI | On-Going | ₱719.8M | 0% | High risk66 | Flagged0.036 |
| 18E00028CONST. OF MISSING LINKS/NEW ROADS, PALAWAN CIRCUMFERENTIAL ROAD (LATUD-CANIPAAN SECTION) PACKAGE B, KO286+480-KO294+850, PALAWAN | Region IV-B | Region IV-B | Completed | ₱141.8M | 100% | High risk65 | Flagged0.034 |
| 24A00013CONSTRUCTION OF NEW BRIDGES, PANCIAN VIADUCT ALONG MANILA NORTH ROAD (PHASE I) | Region I | Region I | On-Going | ₱285.3M | 65% | High risk73 | Flagged0.033 |
| 21L00159CONSTRUCTION OF DAVAO CITY COASTAL BYPASS ROAD (BAGO APLAYA - TIMES BEACH - ROXAS AVENUE), PACKAGE 30, DAVAO CITY | Region XI | Region XI | On-Going | ₱398.7M | 94% | High risk66 | Flagged0.026 |
| 23G00062CONSTRUCTION OF FLOOD CONTROL ALONG SIBALOM RIVER, SIBALOM. ANTIQUE | Region VI | Region VI | On-Going | ₱358M | 47% | High risk67 | Flagged0.024 |
| 18L00008CONSTRUCTION OF MAWAB-MARAGUSAN-CARAGA ROAD (SECTION 1), PACKAGE A, INCLUDING ROW, COMPOSTELA VALLEY | Region XI | Region XI | On-Going | ₱184.2M | 85% | High risk65 | Flagged0.023 |
| 22L00166CONSTRUCTION OF ASPHALT ROAD - DAVAO CITY COASTAL BYPASS ROAD (BAGO APLAYA - TIMES BEACH - ROXAS AVENUE - STA. ANA WHARF - R. CASTILLO), STA. ANA WHARF - R. CASTILLO SEGMENT, PACKAGE 4, DAVAO CITY | Region XI | Region XI | On-Going | ₱374.4M | 90% | High risk68 | Flagged0.022 |
| 20L00004CONSTRUCTION OF CONCRETE BRIDGE-MONKAYO-COMPOSTELA ROAD, PACKAGE F, COMPOSTELA VALLEY | Region XI | Region XI | On-Going | ₱179M | 99% | High risk68 | Flagged0.022 |
| 17IJ0211PREVENTIVE MAINTENANCE ALONG CALBAYOG DIVERSION ROAD (S0085SM) K0727+000 - K0735.57+000, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱163.2M | 100% | High risk62 | Flagged0.022 |
| 18L00156MAWAB-MARAGUSAN-CARAGA RD (SECT. 1),PACKAGE B & C,INCLUDING ROW,COMPOSTELA VALLEY, A)MAWAB-MARAGUSAN | Region XI | Region XI | On-Going | ₱377.9M | 100% | High risk66 | Flagged0.021 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 24IF0048PREVENTIVE MAINTENANCE - SECONDARY ROADS - VILLABA - PALOMPON RD - K1059+(-649) - K1059+515 | Region VIII | Leyte 4th DEO | On-Going | ₱57.8M | 100% | Medium risk55 | —-0.051 |
| 152 | 20L00071ROAD WIDENING ALONG BABAK-SAMAL-KAPUTIAN ROAD (S00095MN), DAVAO DEL NORTE, K1502+249-K1503+750 | Region XI | Region XI | Completed | ₱62.7M | 100% | Medium risk54 | —-0.069 |
| 153 | 18N00116ACCESS ROAD LEADING TO JUBANG PORT, CONSTRUCTION OF STA. FE - JUBANG PORT, DAPA, SIARGAO, SURIGAO DEL NORTE | Region XIII | Region XIII | Completed | ₱327.9M | 100% | Medium risk53 | —-0.033 |
| 154 | 22IG0029ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K0966+100 - K0967+188, K0967+217 - K0967+980 | Region VIII | Leyte 5th DEO | Completed | ₱54.3M | 100% | Medium risk53 | —-0.093 |
| 155 | 23IF0009PREVENTIVE MAINTENANCE - SECONDARY ROADS PALOMPON - ISABEL - MERIDA - ORMOC ROAD, K1109 + 421 - K1110+535 | Region VIII | Leyte 4th DEO | Completed | ₱51.5M | 100% | Medium risk52 | —-0.093 |
| 156 | 23IF0080CONSTRUCTION OF LAO BRIDGE ALONG SAN JUAN-LAO-NAUNGAN ROAD, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱48.8M | 100% | Medium risk52 | —-0.054 |
| 157 | 18I00019ASSET PRESERVATION OF NAT'L. ROADS - PREVENTIVE MAINT. BASED ON PAVEMENT MGT. SYSTEM/HIGHWAY DEV'T. & MGT.-4 (HDM-4) - PRIMARY ROADS, PALO-CARIGARA-ORMOC ROAD,K1007+100-K1007+600; K1007+600-K1008+000; K1008+341-K1010+000, LEYTE 4TH LD | Region VIII | Leyte 4th DEO | Completed | ₱49.8M | 100% | Medium risk52 | —-0.094 |
| 158 | 19O00059PROPOSED MANILA BAY REHABILITATION PROGRAM (CONTAINMENT DEVICES AND SILT CURTAINS ESTABLISHED), MANILA BAY | National Capital Region | National Capital Region | Completed | ₱49.9M | 100% | Medium risk52 | —-0.045 |
| 159 | 20LC0036TAGUM-PANABO CIRCUM. ROAD K1460+000-K1461+000, K1463+000-K1464+000, K1469+210-K1471+200, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱51.9M | 100% | Medium risk52 | —-0.070 |
| 160 | 24IF0049PREVENTIVE MAINTENANCE - SECONDARY ROADS - PALOMPON - ISABEL - MERIDA - ORMOC ROAD K1098+896 - K1099+946 | Region VIII | Leyte 4th DEO | Completed | ₱48.8M | 100% | Medium risk51 | —-0.095 |
| 161 | 20HH0120LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - NATIONAL ROADS AND BRIDGES - NATIONAL ROADS - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE AND LANDSLIDE, CEBU-BALAMBAN TRANSCENTRAL HIGHWAY KM 7+421 - KM 7+630, KM 7+650 - KM 7+684, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱48M | 100% | Medium risk51 | —-0.095 |
| 162 | 20L00120CONSTRUCTION OF CONCRETE ROAD - MAWAB - MARAGUSAN - CARAGA ROAD, SECTION 2, PACKAGE E, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱50.3M | 100% | Medium risk51 | —-0.080 |
| 163 | 20HH0117LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - NATIONAL ROADS AND BRIDGES-NATIONAL ROADS - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE AND LANDSLIDE, CEBU-BALAMBAN TRANSCENTRAL HIGHWAY KM 7+684 - KM 7+780, KM 7+900 - KM 8+012, CEBU C | Region VII | Cebu City DEO | Completed | ₱47M | 100% | Medium risk50 | —-0.095 |
| 164 | 20HH0116LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - NATIONAL ROADS AND BRIDGES - NATIONAL ROADS - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE AND LANDSLIDE, CEBU - BALAMBAN - TRANSCENTRAL HIGHWAY KM 7+059 - KM 7+249, KM 7+280 - KM 7+421, CEBU C | Region VII | Cebu City DEO | Completed | ₱47M | 100% | Medium risk50 | —-0.095 |
| 165 | 17L00021WIDENING (4 TO 6 LANES) OF DIGOS MAKAR RD INCL. CONST. OF OFF-CARRIAGEWAY & ROAD RIGHT-OF-WAY (RROW) | Region XI | Region XI | Completed | ₱107.2M | 100% | Medium risk50 | —-0.038 |
| 166 | 17L00175CONC. OF DAVAO DEL NORTE-COMPOSTELA VALLEY-AGUSAN DEL SUR RD LEADING TO VARIOUS TOURISM SITES, SAN I | Region XI | Region XI | Completed | ₱193M | 100% | Medium risk50 | —-0.017 |
| 167 | 20L00121CONSTRUCTION OF CONCRETE ROAD - MONTEVISTA - DNAS ROAD (DNAS- LAAK), SECTION 2, PACKAGE A, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱49.1M | 100% | Medium risk50 | —-0.085 |
| 168 | 18KA0110CONSTRUCTION OF A MULTI-PURPOSE FACILITY (GRANDSTAND-2), BRGY. LAGUITAS, MALAYBALAY, BUKIDNONMALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱53.5M | 100% | Medium risk49 | —-0.077 |
| 169 | 20IL0159LOCAL-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS/PREVENTIVE MAINTENANCE ALONG BDRY SO. LEYTE - MAASIN - MACROHON - SOGOD - JCT DAANG MAHARLIKA ROAD- K1199+20 | Region VIII | Southern Leyte 1st DEO | Completed | ₱44.1M | 100% | Medium risk49 | —-0.093 |
| 170 | 23IF0010PREVENTIVE MAINTENANCE - PRIMARY ROADS, PALO - CARIGARA - ORMOC ROAD - K0984+060 - K0984+875, K0990+000 - K0990+089 | Region VIII | Leyte 4th DEO | Completed | ₱43.9M | 100% | Medium risk49 | —-0.095 |
| 171 | 20IL0158LOCAL-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS/PREVENTIVE MAINTENANCE ALONG BDRY SO. LEYTE - MAASIN - MACROHON - SOGOD - JCT DAANG MAHARLIKA ROAD- K1189+00 | Region VIII | Southern Leyte 1st DEO | Completed | ₱39.2M | 100% | Medium risk49 | —-0.093 |
| 172 | 20IG0010ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA K0959+-205 - K0961+200 | Region VIII | Leyte 5th DEO | Completed | ₱29.2M | 100% | Medium risk49 | —-0.092 |
| 173 | 22IF0007PREVENTIVE MAINTENANCE - PRIMARY ROADS, PALO- CARIGARA-ORMOC RD - K0988+060 - K0988+826 | Region VIII | Leyte 4th DEO | Completed | ₱14.7M | 100% | Medium risk48 | —-0.094 |
| 174 | 23IF0063PREVENTIVE MAINTENANCE - TERTIARY ROADS LIBUNGAO - MATAG-OB - PALOMPON RD - K0991+(-079) - K0991+111 | Region VIII | Leyte 4th DEO | On-Going | ₱19.3M | 92% | Medium risk48 | —-0.044 |
| 175 | 24IF0020PREVENTIVE MAINTENANCE - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD - K0991+111 - K0991+460 | Region VIII | Leyte 4th DEO | Completed | ₱17.4M | 100% | Medium risk48 | —-0.096 |