Contractor dossier
80 projects on file, including joint ventures this contractor is part of.
Total projects
80
Total budget
₱1.3B
Average progress
93.7%
Completion rate
85.0%
Average risk score
47.5
Medium risk on average, out of 100
Flagged as unusual
1
1.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 80 | ₱1.3B | 47.5 | 1 | 93.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 34 | ₱585.1M | 44.4 | 0 | 96.5% |
| Buildings and Facilities | 26 | ₱263.5M | 44.2 | 0 | 92.7% |
| Flood Control and Drainage | 12 | ₱275.1M | 46.7 | 0 | 93.4% |
| OTHER | 5 | ₱92.6M | 69.3 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱33.6M | 94.9 | 1 | 0.0% |
| GAA 2025 OO-1 | 1 | ₱38M | 90.8 | 0 | 83.8% |
| Bridges | 1 | ₱14.8M | 47.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DH0075CONSTRUCTION OF ROAD AT BRGY. AMONOY AND BALAYONG, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱33.6M | 0% | High risk95 | Flagged0.022 |
| 25DH0026ROAD WIDENING-SECONDARY ROADS CALAMBA-STA. CRUZ-FAMY JCT. RD-K0105+180-K0105+561, K0105+620-K0105+640, K0105+687-K0105+740, PAKIL, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱38M | 84% | High risk91 | —-0.015 |
| 23DI0003CONSTRUCTION OF ROAD AND DRAINAGE, BARANGAY MALINTA, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱9.9M | 100% | High risk70 | —-0.042 |
| 18DP0004NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING OF TERTIARY ROADS ALONG SN PABLO - DOLORES RD - K0087+ (-1386) - K0087+(-386) | Region IV-A | Laguna 3rd DEO | Completed | ₱28.6M | 100% | High risk70 | —-0.043 |
| 24DI0029CONSTRUCTION OF ROAD AND DRAINAGE AT UNIVERSITY OF THE PHILIPPINES - LOS BANOS, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱26.2M | 100% | High risk69 | —-0.041 |
| 20DI0082CONSTRUCTION OF LAGUNA BOULEVARD ROAD EXTENSION CONNECTING STA. ROSA ULAT TAGAYTAY ROAD - SLEX - CABUYAO INTERCHANGE, STA. ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Terminated | ₱8.1M | 100% | High risk69 | —-0.008 |
| 19DI0089CONSTRUCTION OF ACCESS ROAD LEADING TO THE SHRINE JESUS IN THE HOLY SEPULCHRE (LOLO UWENG SHRINE), BRGY. LANDAYAN, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱19.8M | 100% | High risk69 | —-0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DH0075CONSTRUCTION OF ROAD AT BRGY. AMONOY AND BALAYONG, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱33.6M | 0% | High risk95 | Flagged0.022 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 23DP0032NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0079 + 650 - K0079 + 970, K0080 + 480 - K0080 + 815, K0081 + 250 - K0081 + 377 | Region IV-A | Laguna 3rd DEO | Completed | ₱26.3M | 100% | Medium risk46 | —-0.109 |
| 52 | 19DP0031LOCAL INFRASTRUCTURE PROGRAM REHABILITATION OF ROAD, BRGY. STA. ANA, SAN PABLO CITY | Region IV-A | Laguna 3rd DEO | Completed | ₱23.5M | 100% | Medium risk46 | —-0.109 |
| 53 | 23DH0009ROAD WIDENING-TERTIARY ROADS, MAJAYJAY-LUCBAN RD., K0121 + 494 - K0121 + 810, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.109 |
| 54 | 24DH0021ROAD WIDENING-SECONDARY ROADS-CALAMBA-STA. CRUZ-FAMY JCT. RD K0104+535-K0104+775, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱19.5M | 100% | Medium risk46 | —-0.108 |
| 55 | 23DH0017ROAD WIDENING-TERTIARY ROADS, CAVINTI-CALIRAYA RD, K0108 + 000 - K108 + 395, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱14.3M | 100% | Medium risk46 | —-0.107 |
| 56 | 20DI0025OFF- CARRIAGEWAY IMPROVEMENT- SECONDARY ROADS- STA. ROSA - ULAT -TAGAYTAY RD. - K0040+200 -K0040+390, K0044+450 - K0044+750 | Region IV-A | Laguna 2nd DEO | Completed | ₱8.3M | 100% | Medium risk46 | —-0.109 |
| 57 | 24DP0009CSSP - BASIC INFRASTRUTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY KANLURANG KABUBUHAYAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱5.8M | 100% | Medium risk46 | —-0.104 |
| 58 | 22DI0002CONSTRUCTION OF ROAD, CAMP GENERAL MACARIO L. SAKAY, BRGY. LALAKAY, LOS BAÑOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱7.8M | 100% | Medium risk46 | —-0.109 |
| 59 | 18DH0038CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG STA. CRUZ POBLACION ROAD, K0087 + 740 K0088 + 301 | Region IV-A | Laguna 1st DEO | Completed | ₱7.3M | 100% | Medium risk46 | —-0.109 |
| 60 | 24DP0179CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD (BOX CUVERT) IN BARANGAY WAKAT, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.110 |
| 61 | 24DP0140CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY BAYATE, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.106 |
| 62 | 24DP0010CSSP - BASIC INFRASTRUTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY PALAYAN, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.104 |
| 63 | 24DP0128CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY BUBUKAL, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.109 |
| 64 | 22DH0087CONSTRUCTION OF THREE (3) STOREY, SIX (6) CLASSROOM, PAKIL ES, PAKIL, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱17.6M | 100% | Medium risk44 | —-0.058 |
| 65 | 23DP0104CONSTRUCTION OF 4STY12CL, STA. VERONICA ELEMENTARY SCHOOL (PHASE 1 - 1STY2CL) | Region IV-A | Laguna 3rd DEO | Completed | ₱10M | 100% | Medium risk44 | —-0.061 |
| 66 | 24DP0156CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN STO. NINO ELEMENTARY SCHOOL, BARANGAY STA. NINO, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱9.7M | 100% | Medium risk44 | —-0.061 |
| 67 | 24DP0154CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN STA. ANA ELEMENTARY SCHOOL, BARANGAY STA. ANA, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱9.7M | 100% | Medium risk44 | —-0.061 |
| 68 | 18DI0128CONCRETING OF BRGY. BUNGGO - HORNALAN FMR, BRGY. BUNGGO AND BRGY. HORNALAN, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱6.7M | 100% | Medium risk43 | —-0.056 |
| 69 | 23DH0101OPENING AND CONCRETING OF BRGY. MACATAD FMR, BRGY. MACATAD, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.9M | 100% | Medium risk42 | —-0.055 |
| 70 | 18DH0070CONCRETING OF BRGY. MATALATALA FMR, BRGY. MATALATALA, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk42 | —-0.053 |
| 71 | 18DH0071CONCRETING OF SITIO SABANG, BRGY. GEN. LUNA FMR, BRGY. GEN. LUNA, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.055 |
| 72 | 19DI0034WIDENING OF ROADS, BRGY. SIRANGLUPA, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.7M | 100% | Medium risk42 | —-0.107 |
| 73 | 24DH0068CONCRETING OF BRGY. LABAYO FMR, BRGY. LABAYO, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱12.7M | 100% | Medium risk42 | —-0.056 |
| 74 | 20DI0146CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PACITA I, SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱3.4M | 100% | Low risk25 | —-0.105 |
| 75 | 20DI0022PREVENTIVE MAINTENANCE - PRIMARY ROADS -CALAMBA - STA. CRUZ - FAMY JCT. RD. - K0052+395 -K0052+476 | Region IV-A | Laguna 2nd DEO | Completed | ₱3.8M | 100% | Low risk25 | —-0.102 |