Opening the dossier…
Opening the dossier…
Contractor dossier
145 projects on file, including joint ventures this contractor is part of.
Total projects
145
Total budget
₱828.9M
Average progress
100.0%
Completion rate
97.2%
Average risk score
31.0
Medium risk on average, out of 100
Flagged as unusual
2
1.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 81 | ₱419.9M | 27.5 | 0 | 100.0% |
| Negros Island Region | 64 | ₱408.9M | 35.4 | 2 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 81 | ₱431.7M | 29.4 | 0 | 100.0% |
| Roads | 24 | ₱175.5M | 30.2 | 0 | 100.0% |
| Flood Control and Drainage | 16 | ₱102.2M | 33.1 | 0 | 100.0% |
| Water Provision and Storage | 13 | ₱47.8M | 27.5 | 0 | 100.0% |
| Bridges | 8 | ₱47.4M | 29.2 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱16.6M | 89.1 | 2 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱7.7M | 90.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HJ0138CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF JCT. DUMAGUETE NORTH ROAD | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱14.7M | 100% | High risk94 | Flagged0.004 |
| 25HJ0011ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATINAL ROAD SYSTEM ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - MABINAY AYUNGON RD - K0132+922-K0133+075, K0136+549 - K0136+857, AYUNGON, NEGROS O | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱7.7M | 100% | High risk91 | —-0.011 |
| 25HJ0034BASIC- INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, (COVERED COURT), BARANGAY ATOTES, BINDOY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱2M | 100% | High risk84 | Flagged0.004 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HJ0034BASIC- INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, (COVERED COURT), BARANGAY ATOTES, BINDOY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱2M | 100% | High risk84 | Flagged0.004 |
| 25HJ0138CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF JCT. DUMAGUETE NORTH ROAD | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱14.7M | 100% | High risk94 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24HJ0002BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/ EVACUATION CENTER), LAMOGONG ELEMENTARY SCHOOL, BARANGAY LAMOGONG, MANJUYOD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.087 |
| 27 | 19HC0036CY 2019- LIP- REHABILITATION OF MULTI-PURPOSE BUILDING AT: CLUSTER 1 A. BUENAVISTA, BOHOL 1.)BRGY. CAMBUHAT 2.)BRGY. CANTORES 3.)BRGY. CANTUBA 4.)BRGY. CRUZ 5.)BRGY. MAGKAYA 6.)BRGY. OVERLAND 7.)BRGY. PANGHAGBAN 8.)BRGY. POBLACION AND 9.)BRGY. DAIT | Region VII | Bohol 2nd DEO | Completed | ₱6.5M | 100% | Medium risk43 | —-0.095 |
| 28 | 24HC0050ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- IMPROVEMENT OF BAYONGAN IS DRAINAGE CANAL, TRINIDAD, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱12.2M | 100% | Medium risk43 | —-0.066 |
| 29 | 19HC0044CY 2019- LIP- REPAIR/REHABILITATION OF MULTI-PURPOSE BUILDING AT: CLUSTER 7 A. INABANGA 1.)BRGY. BADIANG 2.)BRGY. DAGNAWAN 3.)BRGY. ILAUD (POB.) 4.)BRGY. POBLACION 5.)BRGY. TAMBOOK 6.)BRGY. UBOJAN 7.)BRGY. U-OG 8.)BRGY. SAA | Region VII | Bohol 2nd DEO | Completed | ₱5.7M | 100% | Medium risk43 | —-0.095 |
| 30 | 23HJ0010BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTERS / COVERED COURT, BUSILAK, LA LIBERTAD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.087 |
| 31 | 21HJ0036CONSTRUCTION OF MULTI-PURPOSE BUILDING (FIRE STATION) IN TAYASAN, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.087 |
| 32 | 21HJ0075CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO NABILOG, BARANGAY TAMBULAN, TAYASAN, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.088 |
| 33 | 23HJ0005BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTERS / COVERED COURT, PLANAS, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.086 |
| 34 | 23HJ0004BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTERS / COVERED COURT, HINAKPAN, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.087 |
| 35 | 18HC0064CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM AT WAHIG RIVER CONTROL (LIR)-WAHIG BRIDGE, REVETMENT, DAGOHOY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱9.3M | 100% | Medium risk43 | —-0.074 |
| 36 | 18HC0065CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM AT WAHIG RIVER CONTROL (SDR)-CANTIWAS BRIDGE, POBLACION, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱9.3M | 100% | Medium risk43 | —-0.077 |
| 37 | 23HC0116COMPLETION OF MULTI-PURPOSE BUILDING, MUNICIPAL HALL GROUND, BARANGAY ILAUD, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.089 |
| 38 | 22HC0084CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, PUROK 4, LOMANGOG, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱5.8M | 100% | Medium risk43 | —-0.094 |
| 39 | 24HC0161CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 2) | Region VII | Bohol 2nd DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.091 |
| 40 | 17HC0036CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, TAONGON BRIDGE (BO0184BH) ALONG TAGBILARAN NORTH ROAD (TAGBILARAN-GETAFE SECTION), TALIBON, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱5.4M | 100% | Medium risk43 | —-0.029 |
| 41 | 23HC0030REHABILITATION OF DPWH MAIN BUILDING, DPWH BUILDING 2ND DEO, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱9.7M | 100% | Medium risk42 | —-0.091 |
| 42 | 23HC0159REHABILITATION (COMPLETION) OF DPWH BOHOL 2ND DEO INCLUDING OTHER FACILITIES, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱12.7M | 100% | Medium risk42 | —-0.091 |
| 43 | 22HC0063REHABILITATION OF MULTI-PURPOSE BUILDINGS, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱11.7M | 100% | Medium risk42 | —-0.090 |
| 44 | 23HC0016REHABILITATION OF DPWH 2ND DISTRICT ENGINEERING OFFICE BUILDING (ROOF DECK), BARANGAY BOOD, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.093 |
| 45 | 23HC0128BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 1: CONSTRUCTION OF 1STY2CL SCHOOL BUILDING, MASONOY PRIMARY SCHOOL, SAN ISIDRO BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱5.7M | 100% | Medium risk42 | —-0.052 |
| 46 | 22HC0120BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 2: CONSTRUCTION OF 1STY2CL, CANDUNGAO HIGH SCHOOL, SAN ISIDRO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.053 |
| 47 | 23HC0138CONSTRUCTION/IMPROVEMENT OF DPWH STAFF HOUSE INCLUDING OTHER FACILITIES, BOHOL 2ND DEO, BARANGAY BOOD, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.092 |
| 48 | 25HC0035COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) FOR DPWH BOHOL 2ND DEO, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.093 |
| 49 | 22HC0039CONSTRUCTION (COMPLETION) OF DPWH STAFF HOUSE INCLUDING OTHER FACILITIES, BOHOL 2ND DEO, BARANGAY BOOD, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.075 |
| 50 | 20HC0164CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), SAN PASCUAL, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.8M | 100% | Medium risk42 | —-0.094 |