Opening the dossier…
Opening the dossier…
Contractor dossier
121 projects on file, including joint ventures this contractor is part of.
Total projects
121
Total budget
₱7.5B
Average progress
97.0%
Completion rate
86.8%
Average risk score
49.6
Medium risk on average, out of 100
Flagged as unusual
7
5.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 73 | ₱3.9B | 49.2 | 2 | 98.5% |
| Region XIII | 31 | ₱1.7B | 45.0 | 1 | 100.0% |
| Region IV-B | 11 | ₱1.2B | 57.4 | 4 | 79.8% |
| Region VIII | 3 | ₱340.8M | 61.0 | 0 | 91.5% |
| Negros Island Region | 1 | ₱96.5M | 79.2 | 0 | 100.0% |
| Region VI | 1 | ₱136.6M | 63.6 | 0 | 100.0% |
| Region XI | 1 | ₱78.7M | 56.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 47 | ₱2.5B | 46.5 | 0 | 99.8% |
| Bridges | 36 | ₱2.1B | 48.7 | 3 | 97.6% |
| Flood Control and Drainage | 30 | ₱2.1B | 51.4 | 3 | 97.5% |
| OTHER | 3 | ₱344M | 78.4 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱39.4M | 42.2 | 0 | 38.2% |
| GAA 2025 OO-1 | 1 | ₱67.2M | 93.7 | 1 | 39.0% |
| Water Provision and Storage | 1 | ₱27.5M | 60.5 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱193M | 53.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EG0017REPLACEMENT OF PERMANENT WEAK BRIDGES - MAYLIGAN BR. (B00020PW) ALONG PUERTO PRINCESA SOUTH ROAD, K0062+147, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | On-Going | ₱67.2M | 39% | High risk94 | Flagged0.027 |
| 17N00015ROAD UPGRADING (UNPAVED TO PAVED), DINAGAT-LORETO ROAD, K0009+466-K0010+000, K0010+000-K0010+757, K0048+000-K0048+700, K0053+020-K0053+320, K0053+348-K0054+000-K0055+000, K0058+566-K0058+810, DINAGAT ISLANDS | Region XIII | Region XIII | Completed | ₱161M | 100% | High risk80 | —-0.013 |
| 20GL0058REPLACEMENT OF PERMANENT WEAK BRIDGE TANOLO BR. 3 (B00354NR) ALONG BACOLOD SOUTH RD, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.022 |
| 19KF0050CONSTRUCTION OF NEW PERMANENT BRIDGES AT LARAPAN BRIDGE ALONG LINAMON-ZAMBOANGA ROAD (PHASE II) | Region X | Lanao del Norte 1st DEO | Completed | ₱86.5M | 100% | High risk76 | —-0.029 |
| 24I00013CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF EMBARKADERO FLOOD CONTROL STRUCTURE ALONG BAHAY RIVER, (DOWNSTREAM), PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱159.6M | 83% | High risk68 | —-0.012 |
| 23IM0086CONSTRUCTION OF TACLOBAN CITY MASTER DRAINAGE AND FLOOD CONTROL SYSTEM, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱150.8M | 91% | High risk68 | —-0.007 |
| 24E00177FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENAMNCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER (RS), STA. 000+000-STA. 000+623.17, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱241.2M | 96% | High risk67 | Flagged0.016 |
| 24E00176FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER, BRGY. MAOYON (LS), PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱241.2M | 94% | High risk67 | Flagged0.018 |
| 24E00132SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (DOWNSTREAM RIGHTSIDE), ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱154.4M | 95% | High risk66 | Flagged0.007 |
| 18G00041WIDENING OF BRIDGE - BAGO BR. (B00195NR) ALONG BACOLOD SOUTH BY-PASS RD INCL. ROW | Region VI | Region VI | Completed | ₱136.6M | 100% | High risk64 | —-0.027 |
| 24K00173REPLACEMENT OF PERMANENT WEAK BRIDGE-MAIGO BR. (B00949MN) ALONG LINAMON-ZAMBOANGA RD | Region X | Region X | On-Going | ₱146.4M | 100% | High risk63 | —-0.008 |
| 19K00217CONSTRUCTION OF NEW PERMANENT BRIDGES, PULANGI PARALLEL BR. ALONG BUKIDNON-DAVAO CITY RD | Region X | Region X | Completed | ₱137.4M | 100% | High risk63 | —-0.021 |
| 20K00060CONSTRUCTION OF MISSING LINKS/NEW ROADS, TUBOD - GANASSI ROAD, LANAO DEL NORTE | Region X | Region X | Completed | ₱139.2M | 100% | High risk62 | —-0.032 |
| 17NE0052IMPROVEMENT/REHABILITATION OF WATER SUPPLY SYSTEM, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱27.5M | 100% | High risk61 | —-0.023 |
| 23KD0038CONSTRUCTION OF BRIDGE: PUERTO BRIDGE ALONG BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY ROAD | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱94.5M | 100% | High risk60 | —-0.043 |
| 18KF0082CONSTRUCTION OF MANDULOG BRIDGE-4 INCLUDING APPROACHES AND RROW (PHASE II) AT BAYUG ISLAND, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱93M | 100% | High risk60 | —-0.049 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EG0017REPLACEMENT OF PERMANENT WEAK BRIDGES - MAYLIGAN BR. (B00020PW) ALONG PUERTO PRINCESA SOUTH ROAD, K0062+147, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | On-Going | ₱67.2M | 39% | High risk94 | Flagged0.027 |
| 24E00176FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER, BRGY. MAOYON (LS), PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱241.2M | 94% | High risk67 | Flagged0.018 |
| 24E00177FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENAMNCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER (RS), STA. 000+000-STA. 000+623.17, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱241.2M | 96% | High risk67 | Flagged0.016 |
| 17N00016DAPA PORT-CONSUELO-CORAZON-STA. CRUZ - STA. FE - CABITOONAN-CATANGNAN-GENERAL LUNA ROAD (CABITOONAN-CATANGNAN BRIDGE PHASE II), SURIGAO DEL NORTE 1ST LD., GENERAL LUNA, SURIGAO DEL NORTE, SIARGAO ISLANDS | Region XIII | Region XIII | Completed | ₱193M | 100% | Medium risk52 | Flagged0.015 |
| 18KG0047CONSTRUCTION OF CADAYUNAN BRIDGE, MUNAI, LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱30.6M | 100% | Medium risk40 | Flagged0.012 |
| 24E00132SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (DOWNSTREAM RIGHTSIDE), ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱154.4M | 95% | High risk66 | Flagged0.007 |
| 18KG0045CONSTRUCTION OF TANGKAL BRIDGE, PANTAO RAGAT, LANAO DEL NORTE | Region X | Lanao del Norte 2nd DEO | Completed | ₱16.2M | 100% | Medium risk39 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EG0017REPLACEMENT OF PERMANENT WEAK BRIDGES - MAYLIGAN BR. (B00020PW) ALONG PUERTO PRINCESA SOUTH ROAD, K0062+147, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | On-Going | ₱67.2M | 39% | High risk94 | Flagged0.027 |
| 2 | 17N00015ROAD UPGRADING (UNPAVED TO PAVED), DINAGAT-LORETO ROAD, K0009+466-K0010+000, K0010+000-K0010+757, K0048+000-K0048+700, K0053+020-K0053+320, K0053+348-K0054+000-K0055+000, K0058+566-K0058+810, DINAGAT ISLANDS | Region XIII | Region XIII | Completed | ₱161M | 100% | High risk80 | —-0.013 |
| 3 | 20GL0058REPLACEMENT OF PERMANENT WEAK BRIDGE TANOLO BR. 3 (B00354NR) ALONG BACOLOD SOUTH RD, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.022 |
| 4 | 19KF0050CONSTRUCTION OF NEW PERMANENT BRIDGES AT LARAPAN BRIDGE ALONG LINAMON-ZAMBOANGA ROAD (PHASE II) | Region X | Lanao del Norte 1st DEO | Completed | ₱86.5M | 100% | High risk76 | —-0.029 |
| 5 | 24I00013CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF EMBARKADERO FLOOD CONTROL STRUCTURE ALONG BAHAY RIVER, (DOWNSTREAM), PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱159.6M | 83% | High risk68 | —-0.012 |
| 6 | 23IM0086CONSTRUCTION OF TACLOBAN CITY MASTER DRAINAGE AND FLOOD CONTROL SYSTEM, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱150.8M | 91% | High risk68 | —-0.007 |
| 7 | 24E00177FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENAMNCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER (RS), STA. 000+000-STA. 000+623.17, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱241.2M | 96% | High risk67 | Flagged0.016 |
| 8 | 24E00176FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER, BRGY. MAOYON (LS), PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱241.2M | 94% | High risk67 | Flagged0.018 |
| 9 | 24E00132SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (DOWNSTREAM RIGHTSIDE), ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱154.4M | 95% | High risk66 | Flagged0.007 |
| 10 | 18G00041WIDENING OF BRIDGE - BAGO BR. (B00195NR) ALONG BACOLOD SOUTH BY-PASS RD INCL. ROW | Region VI | Region VI | Completed | ₱136.6M | 100% | High risk64 | —-0.027 |
| 11 | 24K00173REPLACEMENT OF PERMANENT WEAK BRIDGE-MAIGO BR. (B00949MN) ALONG LINAMON-ZAMBOANGA RD | Region X | Region X | On-Going | ₱146.4M | 100% | High risk63 | —-0.008 |
| 12 | 19K00217CONSTRUCTION OF NEW PERMANENT BRIDGES, PULANGI PARALLEL BR. ALONG BUKIDNON-DAVAO CITY RD | Region X | Region X | Completed | ₱137.4M | 100% | High risk63 | —-0.021 |
| 13 | 20K00060CONSTRUCTION OF MISSING LINKS/NEW ROADS, TUBOD - GANASSI ROAD, LANAO DEL NORTE | Region X | Region X | Completed | ₱139.2M | 100% | High risk62 | —-0.032 |
| 14 | 17NE0052IMPROVEMENT/REHABILITATION OF WATER SUPPLY SYSTEM, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱27.5M | 100% | High risk61 | —-0.023 |
| 15 | 23KD0038CONSTRUCTION OF BRIDGE: PUERTO BRIDGE ALONG BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY ROAD | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱94.5M | 100% | High risk60 | —-0.043 |
| 16 | 18KF0082CONSTRUCTION OF MANDULOG BRIDGE-4 INCLUDING APPROACHES AND RROW (PHASE II) AT BAYUG ISLAND, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱93M | 100% | High risk60 | —-0.049 |
| 17 | 24K00194CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUERTO CREEK, PACKAGE 1, CAGAYAN DE ORO CITY | Region X | Region X | Completed | ₱110.6M | 100% | Medium risk60 | —-0.065 |
| 18 | 25KG0033REPLACEMENT OF PERMANENT WEAK BRIDGES AT LINAMON BR. (B00940MN) ALONG LINAMON-ZAMBOANGA RD. | Region X | Lanao del Norte 1st DEO | On-Going | ₱111.4M | 57% | Medium risk60 | —-0.009 |
| 19 | 23EG0056REPLACEMENT OF PERMANENT WEAK BRIDGE - CONCEPCION BR. (B00101PW) ALONG PUERTO PRINCESA NORTH ROAD, K0066+678.10, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱115.8M | 100% | Medium risk59 | —-0.016 |
| 20 | 22KI0061ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - OROQUIETA CITY - PLARIDEL - CALAMBA - SAPANG DALAGA RD - K1790+950 - K1791+200 | Region X | Misamis Occidental 1st DEO | Completed | ₱95.5M | 100% | Medium risk57 | —-0.083 |
| 21 | 23KD0035CONSTRUCTION OF ROAD, JCT BCIR: LAPASAN-CAMAMAN-AN-INDAHAG-BUKIDNON ROAD | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱93.6M | 100% | Medium risk57 | —-0.082 |
| 22 | 20K00064CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, OROQUIETA CITY BYPASS ROAD, MISAMIS OCCIDENTAL | Region X | Region X | Completed | ₱102.9M | 100% | Medium risk57 | —-0.070 |
| 23 | 17K00411CONST./ REHABILITATION OF FLOOD MITIGATION FACILITIES ALONG MARANDING RIVER BASIN, LANAO DEL NORTE | Region X | Region X | Completed | ₱16.4M | 100% | Medium risk56 | —-0.042 |
| 24 | 22L00152CONSTRUCTION OF CONCRETE ROAD - MATANAO - KIBLAWAN - PADADA ROAD, PACKAGE G, DAVAO DEL SUR | Region XI | Region XI | Completed | ₱78.7M | 100% | Medium risk56 | —-0.073 |
| 25 | 24KL0098CONSTRUCTION OF ROAD, MANTICAO - OPOL ROAD, MISAMIS ORIENTAL (PACKAGE 3) | Region X | Misamis Oriental 2nd DEO | Completed | ₱99M | 100% | Medium risk56 | —-0.082 |