Contractor dossier
51 projects on file, including joint ventures this contractor is part of.
Total projects
51
Total budget
₱671.7M
Average progress
98.5%
Completion rate
94.1%
Average risk score
27.0
Low risk on average, out of 100
Flagged as unusual
3
5.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 49 | ₱622.7M | 26.1 | 3 | 98.4% |
| Region XI | 2 | ₱49M | 46.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 27 | ₱186M | 18.9 | 0 | 100.0% |
| Roads | 13 | ₱236.6M | 27.8 | 0 | 100.0% |
| Flood Control and Drainage | 5 | ₱190.4M | 25.1 | 0 | 100.0% |
| GAA 2025 SSP | 3 | ₱39.5M | 89.7 | 2 | 74.1% |
| Water Provision and Storage | 2 | ₱4.6M | 10.6 | 0 | 100.0% |
| OTHER | 1 | ₱14.7M | 87.4 | 1 | 99.5% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ME0091CONSTRUCTION OF BIG MARGUS ELEMENTARY SCHOOL MULTI-PURPOSE BUILDING, BIG MARGUS, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.8M | 50% | High risk94 | Flagged0.035 |
| 25MG0102CONSTRUCTION OF AIRPORT ROAD FROM BARANGAY LIBERTAD TO BARANGAY CENTRALA, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱28.8M | 73% | High risk92 | Flagged0.024 |
| 25MG0108CONCRETING OF PUROK BALITE TO CROSSING BUNGOT, BRGY. SAN JOSE FMR (PHASE II), BRGY. SAN JOSE, NORALA, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱14.7M | 99% | High risk87 | Flagged0.039 |
| 25MG0085CONSTRUCTION OF MULTI PURPOSE BUILDING (TWO STOREY BUILDING FOR BPATS AND BDRRM) BARANGAY AVANCEÑA, KORONADAL CITY | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | High risk83 | —-0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MG0108CONCRETING OF PUROK BALITE TO CROSSING BUNGOT, BRGY. SAN JOSE FMR (PHASE II), BRGY. SAN JOSE, NORALA, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱14.7M | 99% | High risk87 | Flagged0.039 |
| 25ME0091CONSTRUCTION OF BIG MARGUS ELEMENTARY SCHOOL MULTI-PURPOSE BUILDING, BIG MARGUS, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.8M | 50% | High risk94 | Flagged0.035 |
| 25MG0102CONSTRUCTION OF AIRPORT ROAD FROM BARANGAY LIBERTAD TO BARANGAY CENTRALA, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱28.8M | 73% | High risk92 | Flagged0.024 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 24MB0071COMPLETION OF MULTI-PURPOSE BUILDING IN BRGY. POBLACION, POLOMOLOK, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱3.9M | 100% | Low risk6 | —-0.082 |