Contractor dossier
147 projects on file, including joint ventures this contractor is part of.
Total projects
147
Total budget
₱5.2B
Average progress
89.3%
Completion rate
68.0%
Below 70%
Average risk score
48.1
Medium risk on average, out of 100
Flagged as unusual
4
2.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 132 | ₱5.1B | 50.5 | 4 | 88.5% |
| National Capital Region | 11 | ₱14.8M | 21.3 | 0 | 100.0% |
| Region III | 4 | ₱98M | 41.7 | 0 | 87.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 49 | ₱1.5B | 42.7 | 2 | 79.5% |
| Buildings and Facilities | 48 | ₱807.3M | 44.0 | 0 | 92.9% |
| Flood Control and Drainage | 35 | ₱2.3B | 54.3 | 0 | 97.8% |
| OTHER | 4 | ₱158.4M | 72.8 | 1 | 100.0% |
| Water Provision and Storage | 4 | ₱33.6M | 48.1 | 0 | 99.8% |
| Bridges | 3 | ₱75.1M | 47.8 | 0 | 82.3% |
| GAA 2025 SSP | 2 | ₱53.5M | 93.6 | 1 | 52.5% |
| GAA 2025 OO-2 | 1 | ₱47.8M | 86.3 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱168.5M | 67.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DI0084CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱46.2M | 6% | High risk95 | Flagged0.022 |
| 25DI0144CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY FATIMA, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱7.3M | 99% | High risk93 | —-0.010 |
| 25DI0021CONSTRUCTION OF RIVER PROTECTION STRUCTURE NEAR F.T. SAN LUIS ROAD, BRGY. TRANCA, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱47.8M | 100% | High risk86 | —-0.062 |
| 20DI0178CAPITAL OUTLAY - CONTINGENT FUND - FUND SUBSIDIES FOR CONTINGENCIES - REPAIR / REHABILITATION OF PRIMARY ROAD W/ DRAINAGE INSIDE FORT STO. DOMINGO, STA. ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱57.9M | 100% | High risk83 | Flagged0.012 |
| 25CC0264CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PANDUCOT, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.5M | 50% | High risk74 | —-0.024 |
| 17DP0006NETWORK DEVELOPMENT - IMPROVEMENT / WIDENING OF NATIONAL ROADS ALONG SAN PABLO-RIZAL - NAGCARLAN - LILIW RD. (S05817LZ) K0095 + 465 - K0096 + 912 | Region IV-A | Laguna 3rd DEO | Completed | ₱48.3M | 100% | High risk72 | —-0.042 |
| 22DI0141CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAYS BAMBANG AND LALAKAY, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱29.7M | 100% | High risk68 | —-0.043 |
| 24DC0178REHABILITATION/RECONSTRUCTION OF SLOPE PROTECTION ALONG LAKE TAAL-TAGAYTAY ROAD K0067+507 - K0067+592 | Region IV-A | Batangas 3rd DEO | Completed | ₱22.4M | 100% | High risk67 | —-0.042 |
| 18D00039FY 2018 DPWH INFRASTRUCTURE PROGRAM, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS & DIVERSION ROADS, BIÑAN-CARMONA BYPASS ROAD, INCL.. BRIDGE & ROW, LAGUNA | Region IV-A | Region IV-A | Completed | ₱168.5M | 100% | High risk67 | —-0.049 |
| 25D00095CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CARMONA-BIÑAN DIVERSION ROAD, BIÑAN SECTION, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱141.1M | 20% | High risk66 | —-0.030 |
| 25DI0043REHABILITATION OF BANK STRUCTURE ALONG SANTA ROSA RIVER, PHASE 1, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱95.5M | 97% | High risk65 | —-0.045 |
| 23DI0061CONSTRUCTION OF STRUCTURE FOR RIVERBANK PROTECTION ALONG STA. ROSA RIVER, (NEAR NUVALI ROAD), STA. ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱93.8M | 100% | High risk65 | —-0.075 |
| 23DI0065CONSTRUCTION OF STRUCTURE FOR RIVERBANK PROTECTION ALONG STA. ROSA RIVER, (NEAR SAF), BRGY. STO. DOMINGO, STA. ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱93.9M | 100% | High risk65 | —-0.075 |
| 23D00080CONSTRUCTION OF SLOPE PROTECTION AT BARANGAY LARAM, SAN PEDRO, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱108.1M | 100% | High risk65 | —-0.030 |
| 23D00098CONSTRUCTION OF SLOPE PROTECTION AT BARANGAY LANGGAM, SAN PEDRO, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱103M | 99% | High risk64 | —-0.029 |
| 20D00054PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF RIVER CONTROL ALONG SAN PEDRO RIVER (PHASE II), SAN PEDRO CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱106.1M | 100% | High risk64 | —-0.071 |
| 23DC0095CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG SAN JUAN RIVER-PHASE 5, TANAUAN-STO. TOMAS, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱99M | 100% | High risk64 | —-0.077 |
| 24DI0185CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. ROSA RIVER (NEAR CALAX BRIDGE), STO. DOMINGO SIDE, SANTA ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.079 |
| 23DI0109CONSTRUCTION OF STRUCTURE FOR RIVERBANK PROTECTION ALONG MAULAWIN WATERWAYS, BRGY. SAN ANTONIO, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱99M | 100% | High risk64 | —-0.075 |
| 24DI0112CONSTRUCTION OF WATERWAYS PROTECTION STRUCTURE, BARANGAYS BAMBANG AND LALAKAY, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱96.4M | 96% | High risk64 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DI0084CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱46.2M | 6% | High risk95 | Flagged0.022 |
| 25DC0198CONCRETING OF BRGY. J. LEVISTE FMR, BRGY. J. LEVISTE, LAUREL, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱14.5M | 0% | Medium risk48 | Flagged0.013 |
| 20DI0178CAPITAL OUTLAY - CONTINGENT FUND - FUND SUBSIDIES FOR CONTINGENCIES - REPAIR / REHABILITATION OF PRIMARY ROAD W/ DRAINAGE INSIDE FORT STO. DOMINGO, STA. ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱57.9M | 100% | High risk83 | Flagged0.012 |
| 25DH0064CONCRETING OF BRGY. SISILMIN TO BRGY. TIBATIB FMR, BRGY. SISILMIN TO BRGY. TIBATIB, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱14.5M | 8% | Medium risk48 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24D00092CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CARMONA - BIÑAN DIVERSION ROAD, BIÑAN SECTION, LAGUNA | Region IV-A | Region IV-A | On-Going | ₱136.4M | 41% | High risk64 | —-0.037 |
| 27 | 25DI0124REHABILITATION OF ROAD AND DRAINAGE SYSTEM ALONG CUYAB-SAN ROQUE- LANDAYAN ROAD, SAN PEDRO CITY, LAGUNA, PHASE III | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.9M | 0% | High risk61 | —-0.038 |
| 28 | 22DH0007ROAD WIDENING - SECONDARY ROADS, RIZAL BDRY.-FAMY-QUEZON RD., K0072 + 709-K0073 + 500, K0083 + 650-K0085 + 204, MABITAC, LAGUNA, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱93.3M | 100% | High risk61 | —-0.087 |
| 29 | 20D00032ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CARMONA - BIÑAN BYPASS ROAD, (BIÑAN SECTION), LAGUNA | Region IV-A | Region IV-A | Completed | ₱96.5M | 100% | High risk60 | —-0.087 |
| 30 | 21DH0074CONSTRUCTION OF THE 2ND FLOOR (LEFT/RIGHT WING) AND REHABILITATION OF THE EXISTING CAPITOL BUILDING, PROVINCIAL CAPITOL COMPOUND, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱67.2M | 100% | Medium risk58 | —-0.091 |
| 31 | 23DH0073CONSTRUCTION OF MULTI-PURPOSE BUILDING (ADMINISTRATION BUILDING), LAGUNA UNIVERSITY BRGY. BUBUKAL, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱49.5M | 100% | Medium risk56 | —-0.096 |
| 32 | 22DH0073CONSTRUCTION OF MULTI PURPOSE BUILDING, PROVINCIAL CAPITOL COMPOUND, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱49.5M | 100% | Medium risk55 | —-0.097 |
| 33 | 23D00016CONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARMONA-BIÑAN DIVERSION ROAD, BIÑAN SECTION, LAGUNA | Region IV-A | Region IV-A | Completed | ₱86.8M | 100% | Medium risk54 | —-0.094 |
| 34 | 21D00032ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CARMONA - BIÑAN BYPASS ROAD, BIÑAN SECTION, LAGUNA | Region IV-A | Region IV-A | Completed | ₱55.8M | 100% | Medium risk54 | —-0.105 |
| 35 | 25DI0090CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, BARANGAY SAN ANTONIO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱38.8M | 9% | Medium risk53 | —-0.033 |
| 36 | 24D00228CONSTRUCTION OF CARMONA SLOPE PROTECTION WORKS ALONG CARMONA-BIÑAN RIVER, CARMONA, CAVITE | Region IV-A | Region IV-A | On-Going | ₱70.6M | 95% | Medium risk53 | —-0.045 |
| 37 | 24DI0095CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG STA. ROSA RIVER (NEAR LIMA LOGISTICS), BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱86.8M | 100% | Medium risk53 | —-0.077 |
| 38 | 23D00011CONSTRUCTION OF RIVER CONTROL ALONG SAN PEDRO RIVER (PHASE 1), SAN PEDRO, LAGUNA | Region IV-A | Region IV-A | Completed | ₱77.2M | 100% | Medium risk53 | —-0.080 |
| 39 | 22DI0036CONSTRUCTION OF REVETMENT/RIVERWALL ALONG SAN ISIDRO RIVER, BRGY. SAMPAGUITA, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.083 |
| 40 | 21DI0064CONSTRUCTION OF WOMEN AND CHILDREN CRISIS CENTER, BRGY. SAN ANTONIO, BIÑAN, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱29.7M | 100% | Medium risk53 | —-0.102 |
| 41 | 22DI0153CONSTRUCTION OF THREE (3) STOREY BUILDING, APEX BUILDING, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱29.4M | 100% | Medium risk52 | —-0.102 |
| 42 | 25DI0092REHABILITATION OF CLASSROOMS, JACOBO Z. GONZALES MEMORIAL NATIONAL HIGH SCHOOL, BARANGAY SAN ANTONIO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk52 | —-0.073 |
| 43 | 22DI0132CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY DE LA PAZ, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.8M | 100% | Medium risk52 | —-0.105 |
| 44 | 24DI0080CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0061 + 085 - K0062 + 285 | Region IV-A | Laguna 2nd DEO | On-Going | ₱52.7M | 44% | Medium risk52 | —-0.048 |
| 45 | 25DI0123REHABILITATION OF ROAD AND DRAINAGE SYSTEM ALONG CUYAB-SAN ROQUE- LANDAYAN ROAD, SAN PEDRO CITY, LAGUNA, PHASE II | Region IV-A | Laguna 2nd DEO | On-Going | ₱48.2M | 2% | Medium risk51 | —-0.044 |
| 46 | 21DI0116CONSTRUCTION OF MULTI-PURPOSE BUILDING (FIRE DEPARTMENT), SAN ANTOÑIO, BIÑAN, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱19.4M | 100% | Medium risk51 | —-0.096 |
| 47 | 19D00033FY2019 DPWH INFRA PROGRAM, ORG. OUTCOME 1: ENSURE SAFE & RELIABLE NAT'L. ROAD SYSTEM, NETWORK DEV'T. PROGRAM, CONST. OF BY-PASS & DIVERSION ROADS, CARMONA-BIÑAN BYPASS ROAD, (BIÑAN SECTION), LAGUNA | Region IV-A | Region IV-A | Completed | ₱50.4M | 100% | Medium risk51 | —-0.091 |
| 48 | 20DH0007ROAD WIDENING ON SPECIFIC LOCATIONS ALONG RIZAL BDRY.-FAMY-QUEZON ROAD (S01667LZ), K0077 + 958 TO K0078 + 920, MABITAC, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱50.4M | 100% | Medium risk51 | —-0.103 |
| 49 | 24DC0162CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROPGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (ADMIN BLDG.), TANAUAN CITY COLLEGE, BRGY. TARAPICHI I, TANAUAN CI | Region IV-A | Batangas 3rd DEO | Completed | ₱19.8M | 100% | Medium risk51 | —-0.105 |
| 50 | 25DI0097REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY MALABAN, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱16.5M | 49% | Medium risk50 | —-0.050 |