Contractor dossier
47 projects on file, including joint ventures this contractor is part of.
Total projects
47
Total budget
₱2.2B
Average progress
93.2%
Completion rate
80.9%
Average risk score
47.3
Medium risk on average, out of 100
Flagged as unusual
4
8.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 25 | ₱827.4M | 41.8 | 2 | 100.0% |
| Region IV-B | 6 | ₱520.4M | 50.4 | 0 | 69.1% |
| National Capital Region | 6 | ₱173.6M | 49.7 | 0 | 100.0% |
| Central Office | 4 | ₱372.6M | 70.5 | 1 | 72.9% |
| Region VI | 2 | ₱137.6M | 54.5 | 1 | 87.2% |
| Region V | 2 | ₱88.5M | 46.1 | 0 | 100.0% |
| Region IV-A | 1 | ₱48.7M | 49.2 | 0 | 100.0% |
| Cordillera Administrative Region | 1 | ₱36.6M | 46.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 17 | ₱1.1B | 51.1 | 1 | 91.9% |
| Buildings and Facilities | 15 | ₱382.4M | 46.0 | 1 | 100.0% |
| Roads | 10 | ₱559.6M | 46.4 | 1 | 84.5% |
| Bridges | 4 | ₱87.7M | 33.3 | 1 | 93.6% |
| Water Provision and Storage | 1 | ₱28.7M | 67.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19O00056PROVISION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE WITH BOX CULVERT (PHASE 2), NAVOTAS CITY, | Central Office | Flood Control Management Cluster | On-Going | ₱139.6M | 92% | High risk75 | —-0.000 |
| 21O00127CONSTRUCTION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE WITH BOX CULVERT (PHASE 3), NAVOTAS CITY | Central Office | Flood Control Management Cluster | On-Going | ₱69M | 0% | High risk73 | Flagged0.007 |
| 24CL0035CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAMPAY ES, BARANGAY DAMPAY, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.7M | 100% | High risk72 | —-0.066 |
| 22Z00013UPGRADING OF BANGKULASI PUMPING STATION, NAVOTAS | Central Office | Flood Control Management Cluster | Completed | ₱48.2M | 100% | High risk70 | —-0.078 |
| 24CL0107CONSTRUCTION OF MULTI-PURPOSE BUILDING, CENTRAL ES, BRGY. WEST POBLACION, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱19.5M | 100% | High risk68 | —-0.062 |
| 24CL0075CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY STO. TOMAS, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.7M | 100% | High risk68 | —-0.063 |
| 24CL0058CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION WORKS ALONG STO. NIÑO CREEK, CAPAYAWAN, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱29.3M | 100% | High risk68 | —-0.058 |
| 17CL0165IMPROVEMENT/ REHABILITATION OF WATER SYSTEM, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱28.7M | 100% | High risk68 | —-0.034 |
| 23CL0158CONCRETING OF BARANGAY ROAD, PUROK 2, BRGY. LIPAY, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱18.9M | 100% | High risk68 | Flagged0.030 |
| 25E00003CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BOAC RIVER (UPSTREAM-RIGHTSIDE), BOAC, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱184.7M | 70% | High risk66 | —-0.007 |
| 23Z00003CONSTRUCTION OF OPEN CANAL ALONG NAVOTAS COASTAL DIKE, NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱115.8M | 100% | High risk64 | —-0.095 |
| 23CL0151CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED S CY 2023 BASIC EDUCATION FACILITIES FUND | Region III | Zambales 1st DEO | On-Going | ₱87.5M | 100% | High risk64 | Flagged0.026 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23CL0158CONCRETING OF BARANGAY ROAD, PUROK 2, BRGY. LIPAY, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱18.9M | 100% | High risk68 | Flagged0.030 |
| 23CL0151CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED S CY 2023 BASIC EDUCATION FACILITIES FUND | Region III | Zambales 1st DEO | On-Going | ₱87.5M | 100% | High risk64 | Flagged0.026 |
| 21O00127CONSTRUCTION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE WITH BOX CULVERT (PHASE 3), NAVOTAS CITY | Central Office | Flood Control Management Cluster | On-Going | ₱69M | 0% | High risk73 | Flagged0.007 |
| 23GD0038WIDENING OF BRIDGE - MAAYON BY-PASS ROAD, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱63.1M | 74% | Medium risk56 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 19O00056PROVISION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE WITH BOX CULVERT (PHASE 2), NAVOTAS CITY, | Central Office | Flood Control Management Cluster | On-Going | ₱139.6M | 92% | High risk75 | —-0.000 |
| 2 | 21O00127CONSTRUCTION OF TWO (2) PUMPING STATIONS ALONG NAVOTAS COASTAL DIKE WITH BOX CULVERT (PHASE 3), NAVOTAS CITY | Central Office | Flood Control Management Cluster | On-Going | ₱69M | 0% | High risk73 | Flagged0.007 |
| 3 | 24CL0035CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAMPAY ES, BARANGAY DAMPAY, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.7M | 100% | High risk72 | —-0.066 |
| 4 | 22Z00013UPGRADING OF BANGKULASI PUMPING STATION, NAVOTAS | Central Office | Flood Control Management Cluster | Completed | ₱48.2M | 100% | High risk70 | —-0.078 |
| 5 | 24CL0107CONSTRUCTION OF MULTI-PURPOSE BUILDING, CENTRAL ES, BRGY. WEST POBLACION, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱19.5M | 100% | High risk68 | —-0.062 |
| 6 | 24CL0075CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY STO. TOMAS, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.7M | 100% | High risk68 | —-0.063 |
| 7 | 24CL0058CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION WORKS ALONG STO. NIÑO CREEK, CAPAYAWAN, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱29.3M | 100% | High risk68 | —-0.058 |
| 8 | 17CL0165IMPROVEMENT/ REHABILITATION OF WATER SYSTEM, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱28.7M | 100% | High risk68 | —-0.034 |
| 9 | 23CL0158CONCRETING OF BARANGAY ROAD, PUROK 2, BRGY. LIPAY, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱18.9M | 100% | High risk68 | Flagged0.030 |
| 10 | 25E00003CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, BOAC RIVER (UPSTREAM-RIGHTSIDE), BOAC, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱184.7M | 70% | High risk66 | —-0.007 |
| 11 | 23Z00003CONSTRUCTION OF OPEN CANAL ALONG NAVOTAS COASTAL DIKE, NAVOTAS CITY | Central Office | Flood Control Management Cluster | Completed | ₱115.8M | 100% | High risk64 | —-0.095 |
| 12 | 23CL0151CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED S CY 2023 BASIC EDUCATION FACILITIES FUND | Region III | Zambales 1st DEO | On-Going | ₱87.5M | 100% | High risk64 | Flagged0.026 |
| 13 | 23GD0038WIDENING OF BRIDGE - MAAYON BY-PASS ROAD, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱63.1M | 74% | Medium risk56 | Flagged0.003 |
| 14 | 24EA0081CONSTRUCTION OF BALANACAN COASTAL ROAD, MOGPOG, MARINDUQUE (PACKAGE 2) | Region IV-B | Marinduque DEO | Completed | ₱99M | 100% | Medium risk53 | —-0.078 |
| 15 | 24EA0080CONSTRUCTION OF BALANACAN COASTAL ROAD, MOGPOG, MARINDUQUE (PACKAGE 1) | Region IV-B | Marinduque DEO | Completed | ₱99M | 100% | Medium risk53 | —-0.079 |
| 16 | 23GD0045CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF RIVER BANK SLOPE PROTECTION (UPSTREAM OF MAAYON BRIDGE) (RIGHT BANK) STA. 000+000 - STA. 000+322.40, BRGY. POBLACION ILAYA, MAAYON, CAPIZ | Region VI | Capiz 1st DEO | Completed | ₱74.6M | 100% | Medium risk53 | —-0.064 |
| 17 | 20OA0042CONSTRUCTION OF MPB KAPITBAHAYAN BRGY. NBBS, DAGAT-DAGATAN NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱44.5M | 100% | Medium risk52 | —-0.088 |
| 18 | 25E00004COASTAL ROADS/CAUSEWAY FOR ENVIRONMENT PROTECTION/CONSERVATION- CONST. OF ROAD, BALANACAN-INO COASTAL ROAD, MOGPOG, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱92M | 45% | Medium risk52 | —-0.046 |
| 19 | 20OA0015CONSTRUCTION OF MULTI-PURPOSE BLDG. PHASE 1-A BRGY. NBBS KAUNLARAN, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱33.3M | 100% | Medium risk51 | —-0.093 |
| 20 | 20OA0017CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1-C BRGY. NBBS KAUNLARAN, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱32.3M | 100% | Medium risk51 | —-0.094 |
| 21 | 21OA0057CONST(COMPL) OF MPB PHASE 1-C BRGY. NBBS KAUNLARAN NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱24.4M | 100% | Medium risk49 | —-0.100 |
| 22 | 18DQ0066ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS : CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG METIZO RIVER, P | Region IV-A | Region IV-A | Completed | ₱48.7M | 100% | Medium risk49 | —-0.082 |
| 23 | 21OA0062CONSTRUCTION (COMPL.) OF MPB PHASE 1-A, BRGY. NBBS KAUNLARAN NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱19.2M | 100% | Medium risk49 | —-0.100 |
| 24 | 18CJ0175ASSET PRESERVATION PROGRAM CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS MANILA NORTH RD - K0153 + 260 - K0153 + 963, K0155 + 507 - K0158 + 487.20 | Region III | Tarlac DEO | Completed | ₱92.6M | 100% | Medium risk48 | —-0.088 |
| 25 | 20FE0044LP: FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/ FACILITIES - CONST/ REPAIR/ REHAB/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONST OF DIKE (SEAWALL) ALONG THE SHORELINE, BRGY. SAN CIRILO, PASACAO, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱44.2M | 100% | Medium risk46 | —-0.087 |