Opening the dossier…
Opening the dossier…
Contractor dossier
102 projects on file, including joint ventures this contractor is part of.
Total projects
102
Total budget
₱614.7M
Average progress
98.9%
Completion rate
94.1%
Average risk score
25.9
Low risk on average, out of 100
Flagged as unusual
2
2.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 102 | ₱614.7M | 25.9 | 2 | 98.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 71 | ₱362.6M | 22.1 | 0 | 100.0% |
| Roads | 21 | ₱229.5M | 36.9 | 0 | 95.5% |
| Water Provision and Storage | 7 | ₱12.1M | 19.8 | 0 | 100.0% |
| OTHER | 2 | ₱5.5M | 55.4 | 2 | 92.9% |
| Bridges | 1 | ₱4.9M | 50.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18EE0370COMPLETION OF TWO-STOREY 8 CLASSROOMS (4 REG. WORKSHOP) BORAC NATIONALHIGH SCHOOL CORON, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱3.1M | 100% | Medium risk53 | Flagged0.021 |
| 25EE0016CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DUMARAN BEACH, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱2.4M | 86% | Medium risk58 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 18EE0188CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) CONCEPCION NATIONAL HIGH SCHOOL, AGUTAYA, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱10.8M | 100% | Medium risk35 | —-0.039 |
| 27 | 22EE0016CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDINGBARANGAY PULARAQUEN, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk35 | —-0.070 |
| 28 | 18EE0146CONSTRUCTION OF TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING PAWA NHS, CUYO, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱14M | 100% | Medium risk34 | —-0.041 |
| 29 | 24EE0016CONSTRUCTION OF MULTI-PURPOSE BUILDING, BOHOL, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.076 |
| 30 | 24EE0028CONSTRUCTION OF MULTI-PURPOSE BUILDING, BGY. POBLACION, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.073 |
| 31 | 22EE0004CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDINGBARANGAY POBLACION, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.073 |
| 32 | 24EE0014CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BACAO, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.074 |
| 33 | 22EE0032CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY ITANGIL, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.070 |
| 34 | 23EE0113CONSTRUCTION OF 1-STY 4CL MAGSAYSAY CENTRAL SCHOOL MAGSAYSAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱12.7M | 100% | Medium risk34 | —-0.044 |
| 35 | 22EE0094CONSTRUCTION OF 1-STY 2CL VILLA SOL ELEMENTARY SCHOOL AGUTAYA, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱6.7M | 100% | Medium risk34 | —-0.044 |
| 36 | 18EE0260CONSTRUCTION OF TWO-STOREY (10 CLASSROOMS) (5 REGULAR WORKSHOPS) CULIONSANITARIUM SPECIAL NATIONAL HIGH SCHOOL CULION, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱22M | 100% | Medium risk34 | —-0.036 |
| 37 | 24EE0030CONSTRUCTION OF MULTI-PURPOSE BUILDING, BGY. TANATANAON, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.069 |
| 38 | 23EE0108CONSTRUCTION OF 1-STY 2CL RIZAL ELEMENTARY SCHOOL MAGSAYSAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱6.6M | 100% | Medium risk34 | —-0.042 |
| 39 | 22EE0091CONSTRUCTION OF 1-STY 2CL BALAGUEN ELEMENTARY SCHOOL MAGSAYSAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱6.7M | 100% | Medium risk34 | —-0.044 |
| 40 | 23EE0107CONSTRUCTION OF 1-STY 2CL LACAREN ELEMENTARY SCHOOL MAGSAYSAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱6.6M | 100% | Medium risk34 | —-0.044 |
| 41 | 18EE0184CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) CULION SANITARIUM SPECIAL NATIONAL HIGH SCHOOL, CULION, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱10.7M | 100% | Medium risk34 | —-0.036 |
| 42 | 23EE0114CONSTRUCTION OF 1-STY 2CL GAUDENCIO E. ABORDO MEM. NATIONAL HIGH SCHOOL AGUTAYA, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.7M | 100% | Medium risk33 | —-0.043 |
| 43 | 22EG0032CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PUERTO PRINCESA CITY NATIONAL SCIENCE HIGH SCHOOL, BARANGAY STA. MONICA, CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.067 |
| 44 | 22EG0013CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY NAPSAN, CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.066 |
| 45 | 22EE0095CONSTRUCTION OF 1-STY 2CL TALAGA ELEMENTARY SCHOOL CAGAYANCILLO, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱6.6M | 100% | Medium risk32 | —-0.043 |
| 46 | 18EE0256CONSTRUCTION OF 3 STY 12 CL (2 UNITS REGULAR WORKSHOP, 2 UNITS ICTLABORATORY, AND 2 UNITS SCIENCE LABORATORY BUILDING) TUMARBONG NATIONAL HIGH SCHOOL, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱26.3M | 100% | Medium risk31 | —-0.021 |
| 47 | 23EE0088CONCRETING OF PUROK BULIGAY, BRGY. DANLEG FMR BRGY. DANLEG, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱11.9M | 100% | Medium risk31 | —-0.024 |
| 48 | 18EE0254CONSTRUCTION OF TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING CULION ES CULION, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱22.4M | 100% | Medium risk31 | —-0.024 |
| 49 | 21EE0122CONCRETING OF BRGY. STO. TOMAS PROPER FMRBRGY. STO. TOMAS, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱11.9M | 100% | Medium risk31 | —-0.028 |
| 50 | 18EE0195CONSTRUCTION OF 2-STOREY 4 CLASSROOMS (2 UNITS ICT LABORATORY BUILDING) STA. TERESITA NATIONAL HIGH SCHOOL, DUMARAN, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9.1M | 100% | Medium risk30 | —-0.032 |