Contractor dossier
23 projects on file, including joint ventures this contractor is part of.
Total projects
23
Total budget
₱260.6M
Average progress
95.8%
Completion rate
87.0%
Average risk score
41.5
Medium risk on average, out of 100
Flagged as unusual
3
13.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 23 | ₱260.6M | 41.5 | 3 | 95.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 13 | ₱128.6M | 37.0 | 0 | 99.9% |
| Roads | 7 | ₱63.9M | 38.0 | 1 | 99.1% |
| OTHER | 2 | ₱58.3M | 76.5 | 1 | 100.0% |
| Flood Control and Drainage | 1 | ₱9.8M | 53.3 | 1 | 10.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19LD0134DEVELOPMENT OF BAT CAVE AT BRGY. ASBANG, MATANAO, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱29M | 100% | High risk81 | Flagged0.019 |
| 18LB0062CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS JCT. FATIMA-MALABOG ROAD LEADING TO MEGKAWAYAN PEAK RESORT, INCLUDING BRIDGE, MALABOG, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱29.4M | 100% | High risk72 | —-0.027 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19LD0134DEVELOPMENT OF BAT CAVE AT BRGY. ASBANG, MATANAO, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱29M | 100% | High risk81 | Flagged0.019 |
| 25LD0185CONSTRUCTION OF SEA WALL AT THE PASSIG ISLET AQUA ECO-PARK RESORT, BRGY. BATO, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱9.8M | 11% | Medium risk53 | Flagged0.014 |
| 24LD0192CONCRETING OF BRGY. LINAWAN FMR, BRGY. LINAWAN, BANSALAN, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱10M | 94% | Medium risk42 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 19LD0134DEVELOPMENT OF BAT CAVE AT BRGY. ASBANG, MATANAO, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱29M | 100% | High risk81 | Flagged0.019 |
| 2 | 18LB0062CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS JCT. FATIMA-MALABOG ROAD LEADING TO MEGKAWAYAN PEAK RESORT, INCLUDING BRIDGE, MALABOG, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱29.4M | 100% | High risk72 | —-0.027 |
| 3 | 25LD0185CONSTRUCTION OF SEA WALL AT THE PASSIG ISLET AQUA ECO-PARK RESORT, BRGY. BATO, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱9.8M | 11% | Medium risk53 | Flagged0.014 |
| 4 | 24LD0120CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW ADMINISTRATIVE BUILDING OF THE PROVINCIAL HEALTH OFFICE), LAPU-LAPU ST., BRGY. ZONE 3, DIGOS CITY, DAVAO | Region XI | Davao del Sur DEO | Completed | ₱24.8M | 100% | Medium risk50 | —-0.087 |
| 5 | 23LD0044CONSTRUCTION OF NEW ATOME STATION AT BRGY. TAGABULI, SANTA CRUZ, DAVAO DEL SUR ALONG DAVAO-COTABATO RD(DAVAO CITY-JCT DIGOS SECT), BOTH DIRECTIONS, SANTA CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱22.1M | 100% | Medium risk49 | —-0.087 |
| 6 | 24LD0162CONSTRUCTION (COMPLETION) OF MUTLI-PURPOSE BUILDING (MOTORPOOL BUILDING), DIGOS CITY , DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.091 |
| 7 | 23LD0072CONSTRUCTION OF MULTI- PURPOSE BUILDING(PROVINCIAL ENGINEER'S OFFICER BUILDING), AT BRGY. SAN AGUSTIN, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.091 |
| 8 | 24LD0168REHABILITATION OF MULTI-PURPOSE BUILDING (PROVINCIAL ENGINEERING OFFICE), BRGY. SAN AGUSTIN, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.091 |
| 9 | 24LD0153CONSTRCUTION MULTI-PURPOSE BUILDING (PROVINCIAL NURSERY, PROVINCIAL AGRICULTURE OFFICE), BRGY. POBLACION DOS, BANSALAN, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱14.9M | 100% | Medium risk48 | —-0.090 |
| 10 | 21LD0042OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION-ALONG DIGOS-MAKAR RD-K1569+040-K1570+033, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱22.9M | 100% | Medium risk47 | —-0.090 |
| 11 | 25LD0022CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL AGRI-ECO TOURISM PARK), BARANGAY KAPATAGAN, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱14.6M | 98% | Medium risk47 | —-0.058 |
| 12 | 23LD0063CONSTRUCTION OF MULTI-PURPOSE BUILDING(CONVENTION CENTER), MT. APO AGRI- ECO TOURISM PARK, BARANGAY, KAPATAGAN, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱9.9M | 100% | Medium risk47 | —-0.092 |
| 13 | 19LB0059OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION ALONG DAVAO CITY DIV. RD. (S00013MN) CW1: 1498+(-)252-K1498+000 LS,K1499+805-K1500+000 LS, K1503+ 811-K1504+300 RS; K1504+100-K1504 +300 LS, CW2: K1505+629-K1505+694 RS; K1505+310-K1505+500 | Region XI | Davao City DEO | Completed | ₱5.8M | 100% | Medium risk46 | —-0.090 |
| 14 | 20LB0282OFF-CARRIAGEWAY IMPROVEMENT - DAVAO-COTABATO RD (DAVAO CITY-JCT DIGOS SECT) - K1519+920 - K1519+1100, K1520+048 - K1520+183, K1520+204 - K1520+339, K1520+850 - K1520+950, K1520+871 - K1520+952, K1521+042 - K1521+088, K1523+561 - K1523+731, ET AL | Region XI | Davao City DEO | Completed | ₱9.2M | 100% | Medium risk45 | —-0.091 |
| 15 | 20LB0013CONSTRUCTION OF DRAINAGE STRUCTURE - DAVAO - COTABATO OLD RD - K1520+513, K1520+720, K1521+204 | Region XI | Davao City DEO | Completed | ₱11M | 100% | Medium risk45 | —-0.092 |
| 16 | 20LB0125CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK SAGITTARIUS 2, BRGY. LASANG, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.089 |
| 17 | 24LD0192CONCRETING OF BRGY. LINAWAN FMR, BRGY. LINAWAN, BANSALAN, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱10M | 94% | Medium risk42 | Flagged0.005 |
| 18 | 19LB0156CONCRETING OF ROAD, FROM VETERANS VILLAGE TO ESTORES VILLAGE, BRGY. PANACAN, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱3M | 100% | Low risk21 | —-0.088 |
| 19 | 19LB0055RECONSTRUCTION OF ROAD, BRGY. BUHANGIN, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱2.1M | 100% | Low risk20 | —-0.088 |
| 20 | 20LB0141CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BAGO APLAYA, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱2M | 100% | Low risk13 | —-0.092 |
| 21 | 20LB0139REHABILITATION OF EXISTING MULTI-PURPOSE BUILDING, BRGY. 76-A BUCANA, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱2M | 100% | Low risk13 | —-0.091 |
| 22 | 20LB0138REHABILITATION OF EXISTING MULTI-PURPOSE BUILDING, BRGY. 4-A, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱2M | 100% | Low risk13 | —-0.092 |
| 23 | 20LB0143REHABILITATION OF EXISTING MULTI-PURPOSE BUILDING, BRGY. LANGUB, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱2M | 100% | Low risk13 | —-0.093 |