Contractor dossier
7 projects on file, including joint ventures this contractor is part of.
Total projects
7
Total budget
₱97.7M
Average progress
85.7%
Completion rate
71.4%
Average risk score
45.9
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 7 | ₱97.7M | 45.9 | 0 | 85.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 5 | ₱43.8M | 41.7 | 0 | 80.0% |
| OTHER | 1 | ₱4.9M | 62.4 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱49M | 50.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24HN0047CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD WITH DRAINAGE FACILITIES, BARANGAY PAGSABUNGAN, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | High risk62 | —-0.033 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24HN0047CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD WITH DRAINAGE FACILITIES, BARANGAY PAGSABUNGAN, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | High risk62 | —-0.033 |
| 2 | 24HN0111CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TINGUB CREEK, BRGY. PAGSABUNGAN, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱49M | 100% | Medium risk50 | —-0.034 |
| 3 | 25HN0051SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CASILI, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱14.6M | 0% | Medium risk48 | —-0.027 |
| 4 | 25HN0009SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING PHASE 2, BARANGAY PAGSABUNGAN, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱6.9M | 100% | Medium risk48 | —-0.096 |
| 5 | 25HN0050SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), PHASE 2, BARANGAY UMAPAD, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.096 |
| 6 | 23HN0177CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER) AT BRGY. UMAPAD, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱9.6M | 100% | Medium risk44 | —-0.055 |
| 7 | 24HN0015CSSP: MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT, PHASE 2), PAGSABUNGAN NATIONAL HIGH SCHOOL, BARANGAY PAGSABUNGAN, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱3M | 100% | Low risk20 | —-0.097 |