Contractor dossier
32 projects on file, including joint ventures this contractor is part of.
Total projects
32
Total budget
₱708.6M
Average progress
99.1%
Completion rate
87.5%
Average risk score
49.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 11 | ₱357.7M | 56.4 | 0 | 99.2% |
| Roads | 10 | ₱96.9M | 41.2 | 0 | 100.0% |
| Buildings and Facilities | 4 | ₱40.3M | 52.8 | 0 | 95.1% |
| Water Provision and Storage | 4 | ₱195.7M | 44.6 | 0 | 100.0% |
| Bridges | 2 | ₱7.6M | 41.5 | 0 | 100.0% |
| OTHER | 1 | ₱10.4M | 77.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18JA0038CONCRETING OF ROAD INCLUDING DRAINAGE FACILITIES AT TUMAGA-AURORA, TUMAGA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱10.4M | 100% | High risk78 | —-0.023 |
| 20J00024CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PONOT DIUT RIVER (DOWNSTREAM) BOTH SIDES, JOSE DALMAN, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱99.1M | 100% | High risk73 | —-0.002 |
| 17JA0030CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PASONANCA-STA. MARIA-TUMAGA SECTION (INCLUDING RIGHT OF WAY), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱36M | 100% | High risk65 | —-0.038 |
| 17JA0021CONSTRUCTION OF FLOOD CONTROL AT MAASIN CREEK, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱23.6M | 100% | High risk65 | —-0.036 |
| 22J00090CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT AYALA RIVER, BRGY. AYALA, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱56.2M | 91% | High risk62 | —-0.007 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18JA0038CONCRETING OF ROAD INCLUDING DRAINAGE FACILITIES AT TUMAGA-AURORA, TUMAGA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱10.4M | 100% | High risk78 | —-0.023 |
| 2 | 20J00024CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PONOT DIUT RIVER (DOWNSTREAM) BOTH SIDES, JOSE DALMAN, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱99.1M | 100% | High risk73 | —-0.002 |
| 3 | 17JA0030CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PASONANCA-STA. MARIA-TUMAGA SECTION (INCLUDING RIGHT OF WAY), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱36M | 100% | High risk65 | —-0.038 |
| 4 | 17JA0021CONSTRUCTION OF FLOOD CONTROL AT MAASIN CREEK, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱23.6M | 100% | High risk65 | —-0.036 |
| 5 | 22J00090CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT AYALA RIVER, BRGY. AYALA, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱56.2M | 91% | High risk62 | —-0.007 |
| 6 | 22JA0067CONCRETING OF BRGY. LIMAONG FMR PHASE II, BRGY. LIMAONG, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱14.8M | 100% | Medium risk56 | —-0.031 |
| 7 | 21JA0047CONSTRUCTION OF SHORELINE PROTECTION, SAN RAMON SECTION, TALISAYAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱42M | 100% | Medium risk55 | —-0.063 |
| 8 | 23JA0065SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY AYALA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱31.3M | 100% | Medium risk55 | —-0.026 |
| 9 | 20JA0012CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAASIN CREEK, BARANGAY MAASIN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.5M | 100% | Medium risk55 | —-0.067 |
| 10 | 20JA0022CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION AT TALISAYAN SECTION, TALISAYAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱34.3M | 100% | Medium risk55 | —-0.064 |
| 11 | 18JA0020CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MAASIN CREEK (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱14M | 100% | Medium risk55 | —-0.062 |
| 12 | 23JA0035BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY TUMITUS, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Region IX | Zamboanga City 2nd DEO | Completed | ₱29.7M | 100% | Medium risk55 | —-0.082 |
| 13 | 23JA0039BASIC INFRASTRUCTURE PROGRAM(BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY AYALA, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.8M | 100% | Medium risk55 | —-0.068 |
| 14 | 18JF0076CONSTRUCTION OF WATER SUPPLY PROJECT, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱71.3M | 100% | Medium risk54 | —-0.031 |
| 15 | 18JF0077CONSTRUCTION OF WATER SUPPLY PROJECT, ROSELLER LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱69.4M | 100% | Medium risk54 | —-0.024 |
| 16 | 21J00006CONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY - CONSTRUCTION OF VITALI POLICE STATION - 1 BUILDING, VITALI, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Region IX | Region IX | Completed | ₱10.3M | 100% | Medium risk53 | —-0.076 |
| 17 | 21J00004CONSTRUCTION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY - CONSTRUCTION OF LABUAN POLICE STATION-10 BUILDING, LABUAN, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Region IX | Region IX | Completed | ₱10.2M | 100% | Medium risk53 | —-0.075 |
| 18 | 19JA0177CONSTRUCTION OF CONCRETE BRIDGE, BARANGAY TAGUITI, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.8M | 100% | Medium risk53 | —-0.055 |
| 19 | 24JA0101CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY TUMITUS, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱14.8M | 80% | Medium risk52 | —-0.035 |
| 20 | 21JI0075CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING (INTEGRATED BUS TERMINAL) (PHASE 2) IN MABUHAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk52 | —-0.081 |
| 21 | 18JF0075CONSTRUCTION OF WATER SUPPLY PROJECT, KABASALAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱53.2M | 100% | Medium risk52 | —-0.027 |
| 22 | 19JA0173CONCRETING OF SITIO SAN RAMON, BRGY. TALISAYAN FMR, BRGY. TALISAYAN, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱5.8M | 100% | Medium risk47 | —-0.030 |
| 23 | 19JA0168CONCRETING OF BRGY. LIMPAPA FMR, BRGY. LIMPAPA, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.029 |
| 24 | 21JA0140CONCRETING OF SITIO CENTRO TO SITIO TAGUI, BRGY. LIMAONG FMR, BRGY. LIMAONG, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱11.9M | 100% | Medium risk47 | —-0.033 |
| 25 | 23KH0030CONSTRUCTION/INSTALLATION OF STREET LIGHTS ALONG CDO AIRPORT (BAUNGON ROAD) BARANGAY LUMBIA, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | Completed | ₱19.2M | 100% | Medium risk45 | —-0.095 |