Contractor dossier
37 projects on file, including joint ventures this contractor is part of.
Total projects
37
Total budget
₱949.2M
Average progress
91.4%
Completion rate
86.5%
Average risk score
44.6
Medium risk on average, out of 100
Flagged as unusual
3
8.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 37 | ₱949.2M | 44.6 | 3 | 91.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 12 | ₱165.4M | 37.9 | 0 | 100.0% |
| Bridges | 8 | ₱396M | 52.6 | 1 | 80.9% |
| Buildings and Facilities | 7 | ₱61.7M | 38.4 | 0 | 94.3% |
| Flood Control and Drainage | 7 | ₱156.5M | 37.2 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱57.9M | 96.2 | 1 | 72.8% |
| GAA 2025 OO-1 | 1 | ₱107M | 95.1 | 1 | 1.3% |
| OTHER | 1 | ₱4.9M | 54.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25II0029REHAB. OF ROAD, DOÑA ANECITA-DALE ROAD, NORTHERN SAMAR, SECOND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱57.9M | 73% | High risk96 | Flagged0.015 |
| 25I00173BRIDGE - WIDENING OF PERMANENT BRIDGES - LABUYAO BR (B00343SM) ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) | Region VIII | Region VIII | On-Going | ₱107M | 1% | High risk95 | Flagged0.027 |
| 24I00392BRIDGE - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - MAWO BR. (B00246SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.) | Region VIII | Region VIII | On-Going | ₱96.4M | 47% | High risk63 | —-0.005 |
| 20I00060BRIDGE - REPLACEMENT OF BRIDGES (TEMPORARY TO PERMANENT) - SAN ROQUE BRIDGE (B000317SM) ALONG SN ROQUE - CABABTOAN OLD RD., SAN ROQUE, NORTHERN SAMAR | Region VIII | Region VIII | Completed | ₱122.8M | 100% | High risk63 | —-0.040 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00173BRIDGE - WIDENING OF PERMANENT BRIDGES - LABUYAO BR (B00343SM) ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) | Region VIII | Region VIII | On-Going | ₱107M | 1% | High risk95 | Flagged0.027 |
| 25I00183BRIDGE - WIDENING OF PERMANENT BRIDGES - NAGA BR. (B00349SM) ALONG MAHARLIKA (SN ISIDRO - SN JUANICO BR) | Region VIII | Region VIII | On-Going | ₱24.1M | 0% | Medium risk45 | Flagged0.017 |
| 25II0029REHAB. OF ROAD, DOÑA ANECITA-DALE ROAD, NORTHERN SAMAR, SECOND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱57.9M | 73% | High risk96 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25II0029REHAB. OF ROAD, DOÑA ANECITA-DALE ROAD, NORTHERN SAMAR, SECOND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | On-Going | ₱57.9M | 73% | High risk96 | Flagged0.015 |
| 2 | 25I00173BRIDGE - WIDENING OF PERMANENT BRIDGES - LABUYAO BR (B00343SM) ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) | Region VIII | Region VIII | On-Going | ₱107M | 1% | High risk95 | Flagged0.027 |
| 3 | 24I00392BRIDGE - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - MAWO BR. (B00246SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.) | Region VIII | Region VIII | On-Going | ₱96.4M | 47% | High risk63 | —-0.005 |
| 4 | 20I00060BRIDGE - REPLACEMENT OF BRIDGES (TEMPORARY TO PERMANENT) - SAN ROQUE BRIDGE (B000317SM) ALONG SN ROQUE - CABABTOAN OLD RD., SAN ROQUE, NORTHERN SAMAR | Region VIII | Region VIII | Completed | ₱122.8M | 100% | High risk63 | —-0.040 |
| 5 | 20II0015WIDENING OF PERMANENT BRIDGES, BANTAYAN BR. (B00296SM) ALONG CATARMAN - LAOANG RD, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱78.3M | 100% | Medium risk55 | —-0.048 |
| 6 | 22IH0045CONSTRUCTION OF ROAD AT BARANGAY EAST, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱4.9M | 100% | Medium risk54 | —-0.066 |
| 7 | 25II0026INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0824+500-K0828+000, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Northern Samar 2nd DEO | Completed | ₱49M | 100% | Medium risk52 | —-0.093 |
| 8 | 19II0027CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS, CONSTRUCTION OF BANTAYAN RIVER CONTROL, BANTAYAN RIVER BASIN, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱55.6M | 100% | Medium risk52 | —-0.079 |
| 9 | 19IH0136CONCRETING OF BRGY. PALANIT - SITIO IGOT FARM TO MARKET ROAD, BRGY. PALANIT, SAN ISIDRO, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱19M | 100% | Medium risk51 | —-0.040 |
| 10 | 20IH0086CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MULTIPURPOSE BUILDING (NEW PUBLIC MARKET), SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱11.6M | 100% | Medium risk51 | —-0.095 |
| 11 | 23IH0123CONSTRUCTION OF MULTIPURPOSE BUILDING COVERED COURT), BRGY. GERATAG, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱9.9M | 100% | Medium risk51 | —-0.096 |
| 12 | 22II0032CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY SIMORA, LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱14.6M | 100% | Medium risk51 | —-0.092 |
| 13 | 24II0059CONSTRUCTION OF DPWH NORTHERN SAMAR 2ND DEO, BRGY BURABOD, LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱19.6M | 100% | Medium risk49 | —-0.092 |
| 14 | 23II0016CONSTRUCTION OF PALAPAG FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, PALAPAG RIVER BASIN, PALAPAG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱54.9M | 100% | Medium risk49 | —-0.077 |
| 15 | 23IH0036WIDENING OF PERMANENT BRIDGES - CAAGUIT-ITAN BR. 3 (B00240SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO-SN JUANICO BR) SAN ISIDRO, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱23.5M | 100% | Medium risk49 | —-0.059 |
| 16 | 20IH0007WIDENING OF PERMANENT BRIDGES DANCALAN BR. (B00290SM) ALONG ALLEN - CATARMAN RD., CATARMAN, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱19.9M | 100% | Medium risk49 | —-0.053 |
| 17 | 21IH0046REPLACEMENT OF PERMANENT WEAK BRIDGES - NAHIBANG BR. (B00292SM) ALONG ALLEN CATARMAN RD., BOBON, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱24.4M | 100% | Medium risk48 | —-0.058 |
| 18 | 19II0013ROAD WIDENING, TERTIARY ROADS, ARTECHE - JIPAPAD - LAS NAVAS ROAD, K0812+807 - K0813+000, K0813+650 - K0813+800, K0814+323 - K0815+005, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱37.5M | 100% | Medium risk48 | —-0.094 |
| 19 | 20IH0002WIDENING OF PERMANENT BRIDGES, GERATAG BR. 1 (B00289SM) ALONG ALLEN - CATARMAN RD., SAN JOSE, N. SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱6.5M | 100% | Medium risk48 | —-0.056 |
| 20 | 19II0050ASSET PRESERVATION, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS, TERTIARY ROADS, ARTECHE-JIPAPAD-LAS NAVAS-RAWIS RD - K0815+127, K0815+874, LAS NAVAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱18.5M | 100% | Medium risk47 | —-0.094 |
| 21 | 19II0006REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSED AND LANDSLIDE ALONG CATARMAN - LAOANG RD, K0770+189 - K0770+295, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱15.5M | 100% | Medium risk47 | —-0.094 |
| 22 | 22IH0078REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE- CATARMAN-CALBAYOG RD - K0774+273 - K0774+302, LOPE DE VEGA, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱7.6M | 100% | Medium risk47 | —-0.093 |
| 23 | 19IH0022CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF ALLEN (POB.) SHORE PROTECTION, ALLEN, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱15.6M | 100% | Medium risk47 | —-0.083 |
| 24 | 21IH0033CONSTRUCTION OF ROAD, BARANGAY BAGONG SABANG, SAN JOSE, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.094 |
| 25 | 25I00183BRIDGE - WIDENING OF PERMANENT BRIDGES - NAGA BR. (B00349SM) ALONG MAHARLIKA (SN ISIDRO - SN JUANICO BR) | Region VIII | Region VIII | On-Going | ₱24.1M | 0% | Medium risk45 | Flagged0.017 |