140 projects on file, including joint ventures this contractor is part of.
Total projects
140
Total budget
₱3.1B
Average progress
88.4%
Completion rate
74.3%
Average risk score
47.7
Medium risk on average, out of 100
Flagged as unusual
7
5.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 140 | ₱3.1B | 47.7 | 7 | 88.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 76 | ₱1.7B | 43.6 | 0 | 92.0% |
| Buildings and Facilities | 24 | ₱264.3M | 43.4 | 0 | 88.4% |
| Bridges | 15 | ₱297.9M | 49.0 | 0 | 94.7% |
| OTHER | 9 | ₱392.7M | 69.3 | 1 | 88.9% |
| Flood Control and Drainage | 9 | ₱440.7M | 54.2 | 1 | 88.5% |
| GAA 2025 SSP | 4 | ₱24.2M | 94.1 | 4 | 11.4% |
| Water Provision and Storage | 3 | ₱8M | 31.7 | 1 | 66.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DP0102CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MOJON, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.024 |
| 25DO0095CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY AMPID I, SAN MATEO, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.9M | 36% | High risk94 | Flagged0.012 |
| 25DO0072CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALANDAY, SAN MATEO, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.9M | 10% | High risk94 | Flagged0.024 |
| 25DP0104CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD, BARANGAY TALANGAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱9.6M | 0% | High risk94 | Flagged0.024 |
| 17D00027NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASSES/DIVERSION ROADS INCL. ROW TIAONG BY-PASS ROAD, ROAD AND BRIDGE WIDENING, QUEZON 2ND L.D., QUEZON PROVINCE | Region IV-A | Quezon 2nd DEO | Completed | ₱144.7M | 100% | High risk72 | —-0.048 |
| 16DJ0052OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN-CANDELARIA JCT.-CANDELARIA-BOLBOC ROAD, S02002LZ, K0153+520-K0155+225 CANDELARIA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱48.9M | 100% | High risk72 | —-0.041 |
| 16DJ0050IMPROVEMENT/WIDENING OF NATIONAL ROADS-TERTIARY, S02002LZ, SAN JUAN CANDELARIA JCT.-CANDELARIA-BOLBOC ROAD, K0146+-440-K0146+670, CANDELARIA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱48.5M | 100% | High risk72 | —-0.042 |
| 18DP0032ASSET PRESERVATION PROGRAM REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PRIMARY ROADS, SAN PABLO-RIZAL-NAGCARLAN-LILIW RD. K0103 + -177.2 K0103 + -049.5, K0103 + -128.7 - K0103 + -049.5 | Region IV-A | Laguna 3rd DEO | Completed | ₱19.1M | 100% | High risk71 | —-0.042 |
| 22DP0058SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF JCT. DAANG MAHARLIKA TO SAN FRANCISCO (BALOC) ROAD, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱64.7M | 100% | High risk71 | —-0.040 |
| 22DP0059SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION/IMPROVEMENT OF CIRCUMFERENTIAL ROAD AT SAMPALOC LAKE, BRGY. CONCEPCION, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱57.9M | 100% | High risk71 | —-0.041 |
| 18DP0045CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS AT SAMPALOC LAKE CIRCUMFERENTIAL ROAD, SAN PABLO, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱48.7M | 100% | High risk70 | —-0.043 |
| 19DP0008ASSET PRESERVATION PROGRAM REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE -TERTIARY ROADS AT LIPA CITY - ALAMINOS RD., K0079 + 100 - K0079 +250, K0080 + 200 -K0080 + 300, K0080 + 500 - K008 + 750 | Region IV-A | Laguna 3rd DEO | Completed | ₱55.6M | 100% | High risk70 | —-0.042 |
| 25DF0118CONVERGENCE & SPECIAL SUPPORT PROGSUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS RDS &/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIES CONST OF PUNTA-OPEN CANAL DIVERSION RD PASONG KAWAYAN I SEC GEN.TRI | Region IV-A | Cavite 1st DEO | On-Going | ₱50.5M | 0% | High risk70 | —-0.018 |
| 25DO0025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE OF RIVERBANK, BARAN | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.9M | 91% | High risk69 | —-0.024 |
| 20DI0101WIDENING AND EXTENSION OF IPB ROAD, LOS BAÑOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱46.5M | 100% | High risk69 | —-0.037 |
| 25DO0006ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MANILA EAST RD - K0041 + 515 - K0042 + 613 | Region IV-A | Rizal 2nd DEO | On-Going | ₱40.1M | 100% | High risk66 | —-0.051 |
| 25DO0024ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - MARIKINA-INFANTA RD - K0038 + (-493) - K0038 + 400 | Region IV-A | Rizal 2nd DEO | On-Going | ₱45.6M | 48% | High risk66 | —-0.032 |
| 24DI0174CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. ROSA RIVER (NEAR TRUSS BRIDGE), STO. DOMINGO SIDE, SANTA ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱93.9M | 91% | High risk65 | —-0.039 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DP0102CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MOJON, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱4.8M | 0% | High risk95 | Flagged0.024 |
| 25DP0104CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD, BARANGAY TALANGAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱9.6M | 0% | High risk94 | Flagged0.024 |
| 25DO0072CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALANDAY, SAN MATEO, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.9M | 10% | High risk94 | Flagged0.024 |
| 24DP0112CSSP - RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTORS IN PUBLIC FACILITIES | Region IV-A | Laguna 3rd DEO | On-Going | ₱2.9M | 0% | Medium risk58 | Flagged0.019 |
| 24DP0204CSSP - (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF DRAINAGE CANAL (PHASE 2), BARANGAY NANHAYA, BARANGAY SAN ROQUE, AND BARANGAY PAGALANGAN, VICTORIA, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱18.9M | 41% | Medium risk51 | Flagged0.016 |
| 25DO0095CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY AMPID I, SAN MATEO, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.9M | 36% | High risk94 | Flagged0.012 |
| 25DO0120CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM AT VARIOUS SITES, TANAY, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱2.6M | 0% | Medium risk46 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 19DP0047LOCAL INFRASTRUCTURE PROGRAM - ASPHALT OVERLAY ALONG BALAGTAS BLVD. (S05821LZ) STA. 0+000 TO STA. 0+390, BRGY. 3-F, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱13.4M | 100% | Medium risk46 | —-0.106 |
| 102 | 23DP0070NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - SN PABLO-RIZAL-NAGCARLAN-LILIW RD - K0086 + 089 - K0086 + 252 (L/S) | Region IV-A | Laguna 3rd DEO | Completed | ₱7.2M | 100% | Medium risk46 | —-0.108 |
| 103 | 20DP0040NETWORK DEVELOPMENT - ROAD WIDENING TERTIARY ROADS - SN PABLO-RIZAL-NAGCARLAN-LILIW RD - K0098 + 870 - K0099 + 240 | Region IV-A | Laguna 3rd DEO | Completed | ₱13.2M | 100% | Medium risk46 | —-0.111 |
| 104 | 25DO0014CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONTRUCTION OF ROAD, MARCOS H | Region IV-A | Rizal 2nd DEO | On-Going | ₱9.5M | 58% | Medium risk46 | —-0.063 |
| 105 | 20DP0036LOCAL PROGRAM - CONCRETING OF BARANGAY ROAD, BRGY. SAN NICOLAS, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 106 | 24DP0040CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY TUY, RIZAL, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.106 |
| 107 | 24DP0042CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY ILAYANG PALINA, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.103 |
| 108 | 18DP0094CONSTRUCTION OF TWO (2) STOREY TWELVE (12) CLASSROOM AT BANKA-BANKA ELEMENTARY SCHOOL, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱26M | 100% | Medium risk45 | —-0.055 |
| 109 | 21DP0077CONSTRUCTION/COMPLETION (4STY8CL) OF RIZAL ES, RIZAL, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱26.9M | 100% | Medium risk45 | —-0.056 |
| 110 | 21DP0079CONSTRUCTION/COMPLETION (3STY6CL) OF BANAAD ELEMENTARY SCHOOL, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱20.5M | 100% | Medium risk45 | —-0.057 |
| 111 | 20DP0076CONSTRUCTION OF FOUR (4) STOREY EIGHT (8) CLASSROOM AT GUERILLA ELEMENTARY SCHOOL, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱20.5M | 100% | Medium risk45 | —-0.058 |
| 112 | 23DP0127CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING WITH EVACUATION CENTER AT BRGY. DANIW, LILIW, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.058 |
| 113 | 24DP0160CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN TAYTAY MALAYA ELEMENTARY SCHOOL, BARANGAY TAYTAY, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱9.9M | 100% | Medium risk44 | —-0.022 |
| 114 | 24DP0163CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN BANILAD ELEMENTARY SCHOOL, BARANGAY BANILAD, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱9.9M | 100% | Medium risk44 | —-0.022 |
| 115 | 24DP0165CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN DE MESA ELEMENTARY SCHOOL, BARANGAY SAN GREGORIO, ALAMINOS, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱9.9M | 100% | Medium risk44 | —-0.061 |
| 116 | 24DP0164CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN SINIPIAN ELEMENTARY SCHOOL, BARANGAY SINIPIAN, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱9.9M | 100% | Medium risk43 | —-0.022 |
| 117 | 22DP0078CONCRETING OF SITIO TALANGAN, BRGY. PEREZ FMR, BRGY. PEREZ, CALAUAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱10M | 100% | Medium risk43 | —-0.057 |
| 118 | 22DP0079CONSTRUCTION OF FARM-TO-MARKET ROAD AT BRGY. SANTISIMO, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.055 |
| 119 | 21DP0075CONCRETING OF BRGY. BAUTISTA FMR, BRGY. BAUTISTA, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱12.4M | 100% | Medium risk42 | —-0.057 |
| 120 | 22DP0077CONCRETING OF BRGY. TALA FMR, BRGY. TALA, RIZAL, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱11.9M | 100% | Medium risk42 | —-0.056 |
| 121 | 20DP0009LOCAL PROGRAM - ASPHALT OVERLAY OF BARANGAY ROAD, BRGY. SAN ROQUE,VICTORIA, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4M | 100% | Low risk25 | —-0.101 |
| 122 | 20DP0005LOCAL PROGRAM - ASPHALT OVERLAY OF BARANGAY ROAD, BRGY. MASAPANG, VICTORIA, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4M | 100% | Low risk25 | —-0.101 |
| 123 | 24DP0007NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - CALAUAN-NAGCARLAN BDRY RD - K0080 + 252 - K0080 + 284, K0080 + 860 - K0080 + 919 | Region IV-A | Laguna 3rd DEO | Completed | ₱3.1M | 100% | Low risk25 | —-0.105 |
| 124 | 20DP0011LOCAL PROGRAM - CONCRETING OF BARANGAY ROAD, BRGY. ABO, NAGCARLAN, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱4M | 100% | Low risk25 | —-0.107 |
| 125 | 19DP0045LOCAL INFRASTRUCTURE PROGRAM - REHABILITATION OF CONCRETE ROAD, BRGY. 2-F, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.105 |