Contractor dossier
161 projects on file, including joint ventures this contractor is part of.
Total projects
161
Total budget
₱8.1B
Average progress
95.0%
Completion rate
78.3%
Average risk score
40.3
Medium risk on average, out of 100
Flagged as unusual
14
8.7% of their projects
Risk mix
Exhibit A
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 71 | ₱4.9B | 49.1 | 5 | 91.9% |
| Buildings and Facilities | 51 | ₱289.8M | 19.5 | 0 | 99.8% |
| Flood Control and Drainage | 15 | ₱1.6B | 58.6 | 1 | 98.0% |
| Water Provision and Storage | 12 | ₱41.6M | 25.5 | 0 | 100.0% |
| OTHER | 5 | ₱711.3M | 79.3 | 5 | 78.1% |
| Bridges | 4 | ₱105M | 48.3 | 0 | 98.9% |
| Bridges, Roads | 2 | ₱397M | 68.0 | 2 | 94.5% |
| GAA 2025 SSP | 1 | ₱143.3M | 95.6 | 1 | 43.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LJ0103CONSTRUCTION OF BUKIDNON - DAVAO DEL NORTE CONNECTOR ROAD, PACKAGE 1, SANTO TOMAS, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱143.3M | 44% | High risk96 | Flagged0.039 |
| 23LB0129CONSTRUCTION OF NRJ DAANG MAHARLIKA ROAD, BARANGAY SAN ISIDRO - TO FATIMA - MALABOG ROAD VIA MALATIVAS, PHASE 2, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱138M | 99% | High risk79 | Flagged0.029 |
| 24LI0113CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MANAT RIVER LEADING TO AGUSAN RIVER, BARANGAY NEW VISAYAS, MONTEVISTA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.7M | 100% | High risk79 | Flagged0.025 |
| 24L00203DESIGN AND CONSTRUCTION OF MULTI-PURPOSE BUILDING (DSWD WAREHOUSE), BARANGAY LA FILIPINA, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 57% | High risk79 | Flagged0.048 |
| 22L00110CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG - GUMITAN), PACKAGE 4, DAVAO CITY | Region XI | Region XI | On-Going | ₱92.7M | 51% | High risk79 | Flagged0.045 |
| 23LB0128CONSTRUCTION OF NRJ DAANG MAHARLIKA ROAD, BARANGAY SAN ISIDRO - TO FATIMA - MALABOG ROAD VIA MALATIVAS, PHASE 1, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱144.8M | 84% | High risk79 | Flagged0.037 |
| 23L00023DAVAO DE ORO BYPASS ROAD (KAHAYAG - PAGSABANGAN - PANANSALAN SECTION), PHASE 1, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱191.1M | 96% | High risk68 | Flagged0.006 |
| 22L00076REPLACEMENT OF BRIDGES - NRJ PANABO CITY - JCT. FATIMA - MALABOG ROAD, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱205.9M | 93% | High risk68 | Flagged0.011 |
| 23L00205CONSTRUCTION OF ACCESS ROAD LEADING TO MATI FISH PORT, PHASE 2, MATI CITY, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱143.4M | 88% | High risk66 | —-0.011 |
| 23L00204CONSTRUCTION OF ACCESS ROAD LEADING TO MATI FISH PORT, PHASE 1, MATI CITY, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱143.3M | 91% | High risk66 | —-0.012 |
| 23L00203CONSTRUCTION OF ACCESS ROAD LEADING TO MATI FISH PORT, MATI CITY, DAVAO ORIENTAL, PHASE 3 | Region XI | Region XI | On-Going | ₱143.3M | 94% | High risk66 | —-0.013 |
| 24LG0085CONSTRUCTION OF CONCRETE ROAD ALONG COASTAL BARANGAYS: CABANGCALAN-CALUBIHAN-MOGBONGCOGON-BAGUMBAYAN, LUPON, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱143.3M | 71% | High risk66 | —-0.019 |
| 24L00240CONSTRUCTION OF ROAD, MABUNAO TO SAN NICOLAS, PANABO CITY, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱143.3M | 72% | High risk66 | —-0.029 |
| 22L00044CONSTRUCTION OF POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 5, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱140M | 80% | High risk66 | Flagged0.001 |
| 23L00188CONSTRUCTION OF CONCRETE ROAD, MABUHAY, CARMEN TO FATIMA, DAVAO CITY, DAVAO CITY PHASE 1 | Region XI | Region XI | On-Going | ₱172M | 47% | High risk66 | —-0.002 |
| 23L00078CONSTRUCTION OF PANABO CITY COASTAL ROAD PANABO WHARF TO TUGANAY, PACKAGE A, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 85% | High risk66 | —-0.008 |
| 23L00184CONSTRUCTION OF PANABO CITY COASTAL ROAD, PANABO WHARF TO TUGANAY, PACKAGE B, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 75% | High risk65 | —-0.006 |
| 22L00038CONSTRUCTION OF POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 2, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱140M | 83% | High risk65 | —-0.000 |
| 23L00185CONSTRUCTION OF ROAD, CARMEN-STO. TOMAS DIVERSION, SAN MIGUEL TO NEW CASAY SECTION B.E. DUJALI, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱144.7M | 95% | High risk65 | —-0.018 |
| 24L00325CONSTRUCTION OF BANK PROTECTION STRUCTURE ALONG TUGANAY RIVER, PACKAGE 2, CARMEN, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱143.3M | 80% | High risk65 | —-0.010 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24L00203DESIGN AND CONSTRUCTION OF MULTI-PURPOSE BUILDING (DSWD WAREHOUSE), BARANGAY LA FILIPINA, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱191.1M | 57% | High risk79 | Flagged0.048 |
| 22L00110CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG - GUMITAN), PACKAGE 4, DAVAO CITY | Region XI | Region XI | On-Going | ₱92.7M | 51% | High risk79 | Flagged0.045 |
| 25L00138CONSTRUCTION OF ACCESS ROAD LEADING TO MATI FISH PORT, PHASE 4, MATI CITY, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱283.7M | 3% | Medium risk52 | Flagged0.044 |
| 25LJ0103CONSTRUCTION OF BUKIDNON - DAVAO DEL NORTE CONNECTOR ROAD, PACKAGE 1, SANTO TOMAS, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱143.3M | 44% | High risk96 | Flagged0.039 |
| 23LB0128CONSTRUCTION OF NRJ DAANG MAHARLIKA ROAD, BARANGAY SAN ISIDRO - TO FATIMA - MALABOG ROAD VIA MALATIVAS, PHASE 1, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱144.8M | 84% | High risk79 | Flagged0.037 |
| 23LB0129CONSTRUCTION OF NRJ DAANG MAHARLIKA ROAD, BARANGAY SAN ISIDRO - TO FATIMA - MALABOG ROAD VIA MALATIVAS, PHASE 2, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱138M | 99% | High risk79 | Flagged0.029 |
| 24LI0113CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MANAT RIVER LEADING TO AGUSAN RIVER, BARANGAY NEW VISAYAS, MONTEVISTA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.7M | 100% | High risk79 | Flagged0.025 |
| 25LJ0106IMPROVEMENT OF JCT. PANABO CITY COASTAL ROAD TO JCT. TAGUM TO SANTO TOMAS DIVERSION ROAD, PACKAGE 1, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱143.3M | 1% | Medium risk55 | Flagged0.021 |
| 25LJ0107IMPROVEMENT OF JCT. PANABO CITY COASTAL ROAD TO JCT. TAGUM TO SANTO TOMAS DIVERSION ROAD, PACKAGE 2, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱143.3M | 2% | Medium risk54 | Flagged0.021 |
| 21L00135CONSTRUCTION OF FLOOD PROTECTION DIKE GABION TYPE, TAMIA, COMPOSTELA, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱187.7M | 100% | High risk64 | Flagged0.013 |
| 22L00076REPLACEMENT OF BRIDGES - NRJ PANABO CITY - JCT. FATIMA - MALABOG ROAD, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱205.9M | 93% | High risk68 | Flagged0.011 |
| 23L00023DAVAO DE ORO BYPASS ROAD (KAHAYAG - PAGSABANGAN - PANANSALAN SECTION), PHASE 1, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱191.1M | 96% | High risk68 | Flagged0.006 |
| 18LA0321OPENING OF BRGY. DIWATA, MONKAYO-BRGY. SIMULAO, BOSTON ROAD, MONKAYO, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱98M | 100% | High risk62 | Flagged0.002 |
| 22L00044CONSTRUCTION OF POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 5, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱140M | 80% | High risk66 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23LI0105DAVAO DE ORO BYPASS ROAD (KAHAYAG-PAGSABANGAN-PANANSALAN SECTION), PHASE 3, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | Completed | ₱144.7M | 100% | High risk64 | —-0.053 |
| 27 | 23G00068CONSTRUCTION OF SEAWALL (SECTION 8), ILOILO CITY | Region VI | Region VI | Completed | ₱96.5M | 100% | High risk63 | —-0.055 |
| 28 | 24LG0071CONSTRUCTION OF CONCRETE BYPASS ROAD: BARANGAY LANGKA LUPON-BRGY.CAGANGANAN-PRES. DIOSDADO MAPACAPGAL NATIONAL HIGHWAY, BANAYBANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱95.5M | 87% | High risk63 | —-0.031 |
| 29 | 20L00074CONSTRUCTION OF CONCRETE ROAD-PANABO CITY BYPASS ROAD, DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱125M | 100% | High risk62 | —-0.069 |
| 30 | 22LA0113MAPAWA-BAHI-LANGGAWISAN, MARAGUSAN, DAVAO DE ORO BYPASS ROAD, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱94.5M | 100% | High risk62 | —-0.065 |
| 31 | 23L00198CONSTRUCTION OF ROAD, BARANGAY SAN ISIDRO, BABAK DISTRICT, IGACOS, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱95.5M | 57% | High risk62 | —-0.022 |
| 32 | 23L00206CONSTRUCTION OF MULTI-PURPOSE FACILITY INCLUDING SITE DEVELOPMENT, FISH PORT COMPLEX, PHASE 1, MATI CITY, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱143.3M | 91% | High risk62 | —-0.007 |
| 33 | 18LA0321OPENING OF BRGY. DIWATA, MONKAYO-BRGY. SIMULAO, BOSTON ROAD, MONKAYO, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱98M | 100% | High risk62 | Flagged0.002 |
| 34 | 24LI0063CONSTRUCTION OF REVETMENT ALONG MANAT RIVER (UPSTREAM AND DOWNSTREAM L/S) LEADING TO AGUSAN RIVER PHASE 1, BANKERUHAN NORTE, MONTEVISTA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱114.8M | 92% | High risk62 | —-0.014 |
| 35 | 22LC0193CONSTRUCTION OF CONCRETE REVETMENT INCLUDING PUMP STATION, SADPUDON CREEK, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱99M | 100% | High risk62 | —-0.061 |
| 36 | 21LB0288CONSTRUCTION OF REVETMENT ALONG MATINA RIVER, MATINA APLAYA SECTION, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱96.5M | 100% | High risk61 | —-0.008 |
| 37 | 22LC0188CONSTRUCTION OF ROAD, ANIBONGAN - SALVACION - CABAY-ANGAN, ANIBONGAN SECTION, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱99M | 100% | High risk61 | —-0.072 |
| 38 | 24L00027CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG - GUMITAN), PACKAGE I, DAVAO CITY | Region XI | Region XI | On-Going | ₱112.7M | 99% | High risk61 | —-0.042 |
| 39 | 23LI0067CONSTRUCTION OF PROTECTION DIKE AT CAMBAONG CREEK, POBLACION, COMPOSTELA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.050 |
| 40 | 23LI0053CONSTRUCTION OF REVETMENT ALONG AGUIBAWA RIVER, SAN MIGUEL-OSMEÑA, COMPOSTELA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.052 |
| 41 | 23LI0043CONSTRUCTION OF REVETMENT ALONG AGUIBAWA CREEK LEADING TO AGUSAN RIVER AT BRGY. POBLACION, COMPOSTELA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.053 |
| 42 | 21LA0108ASPHALT OVERLAY - ALONG BENIGNO S. AQUINO JR. NATIONAL HIGWAY (S01432MN), COMPOSTELA, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱94.6M | 100% | High risk60 | —-0.066 |
| 43 | 23L00157JCT. CARMEN - STO. TOMAS DIVERSION ROAD, BRGY. SAN MIGUEL TO LA LIBERTAD, STO. TOMAS, DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱91.7M | 100% | Medium risk57 | —-0.072 |
| 44 | 21LC0222CONCRETING OF BRGY. TAGBAOBO TO BRGY. SION TO BRGY. BANDERA FMR, BRGY. TAGBAOBO , BRGY. SION AND BRGY. BANDERA, ISLAND GARDEN CITY OF SAMAL, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱59.7M | 100% | Medium risk56 | —-0.019 |
| 45 | 21LC0221CONCRETING OF PUROK SOLID ROCK TO SITIO SAGRADA, BRGY. POBLACION TO BRGY. KAPUTIAN TO BRGY. SAN ISIDRO FMR, BRGY. POBLACION , BRGY. KAPUTIAN AND BRGY. SAN ISIDRO, KAPUTIAN DISTRICT, ISLAND GARDEN CITY OF SAMAL, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱59.7M | 100% | Medium risk56 | —-0.020 |
| 46 | 23L00021CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG-GUMITAN), PACKAGE H, DAVAO CITY | Region XI | Region XI | Completed | ₱85M | 100% | Medium risk55 | —-0.077 |
| 47 | 21LA0234MAPAWA-BAHI-LANGGAWISAN, MARAGUSAN, DAVAO DE ORO BYPASS ROAD, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱72.4M | 100% | Medium risk55 | —-0.069 |
| 48 | 25LJ0106IMPROVEMENT OF JCT. PANABO CITY COASTAL ROAD TO JCT. TAGUM TO SANTO TOMAS DIVERSION ROAD, PACKAGE 1, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱143.3M | 1% | Medium risk55 | Flagged0.021 |
| 49 | 21LA0121ASPHALT OVERLAY - ALONG MONTEVISTA - COMPOSTELA - MATI BDRY RD (S00135MN) NEW BATAAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱72.7M | 100% | Medium risk55 | —-0.071 |
| 50 | 22L00108CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG - GUMITAN), PACKAGE 2, DAVAO CITY | Region XI | Region XI | On-Going | ₱69.9M | 91% | Medium risk54 | —-0.022 |