Contractor dossier
106 projects on file, including joint ventures this contractor is part of.
Total projects
106
Total budget
₱1.5B
Average progress
91.8%
Completion rate
77.4%
Average risk score
42.9
Medium risk on average, out of 100
Flagged as unusual
1
0.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 106 | ₱1.5B | 42.9 | 1 | 91.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 42 | ₱285.2M | 35.0 | 0 | 96.0% |
| Buildings and Facilities | 40 | ₱352.8M | 47.3 | 0 | 93.6% |
| Flood Control and Drainage | 24 | ₱824.7M | 49.3 | 1 | 81.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0654CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER, BARANGAY MERCADO, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.6M | 93% | High risk77 | Flagged0.026 |
| 25CC0082CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG ANGAT RIVER AT BARANGAY SANTO CRISTO, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱77.2M | 100% | High risk76 | —-0.034 |
| 25CC0067CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABANGAN CHANNEL AT BARANGAY IBA ESTE (PUROK 6) - IBA-IBAYO (PUROK 1), CALUMPIT AND HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 0% | High risk76 | —-0.000 |
| 25CC0357CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY STA. LUCIA, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱4.9M | 96% | High risk75 | —-0.044 |
| 24CC0363CONSTRUCTION OF MULTI-PURPOSE, PUROK 1, MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.8M | 100% | High risk74 | —-0.073 |
| 24CC0284CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY LONGOS, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.8M | 100% | High risk74 | —-0.074 |
| 24CC0224CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SUCOL, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.5M | 97% | High risk74 | —-0.036 |
| 24CC0126CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CUTCOT, ,PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk74 | —-0.076 |
| 24CC0321REHABILITATION OF MULTI-PURPOSE BUILDING AT SANTISIMA TRININDAD ELEMENTARY SCHOOL, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk73 | —-0.072 |
| 24CC0505CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY CALILIGAWAN, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk73 | —-0.076 |
| 25CC0549CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY PINAGBAKAHAN, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱6.8M | 54% | High risk73 | —-0.027 |
| 25CC0160CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN PABLO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱9.7M | 100% | High risk73 | —-0.045 |
| 24CC0527CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARAMGAY STO. CRISTO, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱7.2M | 100% | High risk73 | —-0.075 |
| 25CC0235CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY GATBUCA, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱7.8M | 0% | High risk73 | —-0.010 |
| 24CC0132CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY COFRADIA, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱5.9M | 100% | High risk73 | —-0.074 |
| 25CC0226CONSTRUCTION OF DRAINAGE AT BARANGAY BULIHAN, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱4.8M | 0% | High risk72 | —-0.005 |
| 25CC0343CONSTRUCTION OF DRAINAGE AT BARANGAY SANTIAGO, CITY F MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱4.8M | 61% | High risk72 | —-0.019 |
| 24CC0437REPAIR AND REHABILITATION OF MULTI-PURPOSE BUILDING (SPED BUILDING), BUSTOS CENTRAL SCHOOL, BARANGAY POBLACION, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk72 | —-0.075 |
| 25CC0188CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SULIVAN, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk72 | —-0.076 |
| 24CC0109CONSTRUCTION OF DRAINAGE STRUCTURE AT BARANGAY SUMAPANG MATANDA, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.8M | 100% | High risk72 | —-0.066 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0654CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER, BARANGAY MERCADO, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.6M | 93% | High risk77 | Flagged0.026 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 23CC0259CONSTRUCTION/IMPROVEMENT OF ROAD AT SAN ISIDRO II, PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | Medium risk31 | —-0.105 |
| 77 | 23CC0195CONSTRUCTION OF ROAD AND DRAINAGE OF BARANGAY STO. NINO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱6.9M | 100% | Medium risk30 | —-0.107 |
| 78 | 24CC0113IMPROVEMENT OF ROAD AT BARANGAY POBLACION, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | Medium risk30 | —-0.103 |
| 79 | 24CC0112IMPROVEMENT OF ROAD AT BARANGAY CALIZON, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | Medium risk30 | —-0.104 |
| 80 | 23CC0113REHABILITATION OF ROAD INCLUDING DRAINAGE, STO. CRISTO, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | Medium risk30 | —-0.106 |
| 81 | 24CC0303CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. SAN VICENTE, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.8M | 100% | Low risk30 | —-0.056 |
| 82 | 21CC0100CONSTRUCTION OF SLOPE CONCRETE RIVER WALL, MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.1M | 100% | Low risk30 | —-0.093 |
| 83 | 21CC0063CONSTRUCTION OF SLOPE CONCRETE RIVER WALL, BULUSAN, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱13.7M | 100% | Low risk30 | —-0.094 |
| 84 | 23CC0185CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BRGY. ABULALAS, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱24.5M | 100% | Low risk29 | —-0.093 |
| 85 | 23CC0120CONSTRUCTION OF REVETMENT AT IBA, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱28.9M | 100% | Low risk29 | —-0.093 |
| 86 | 23CC0118CONSTRUCTION OF REVETMENT AT TAAL, PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱28.9M | 100% | Low risk29 | —-0.092 |
| 87 | 18CC0332CONSTRUCTION OF TWO STOREY EIGHT CLASSROOM - PULILAN CENTRAL SCHOOL PULILAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱16.5M | 100% | Low risk28 | —-0.052 |
| 88 | 18CC0301CONSTRUCTION OF BARANGAY ROAD PUROK 1 & 2 AND SITIO BORNEO, PIO CRUZCOSA, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱3.3M | 100% | Low risk14 | —-0.106 |
| 89 | 19CC0051CONCRETING OF ROAD BARANGAY LICIADA, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱2.4M | 100% | Low risk13 | —-0.103 |
| 90 | 20CC0054REHABILITATION OF LOCAL ROAD INCLUDING DRAINAGE BINANG 2ND, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk13 | —-0.103 |
| 91 | 21CC0232REHABILITATION OF ROAD INCLUDING SLOPE PROTECTION, NIA ROAD, PUROK 4, TABANG, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱2M | 100% | Low risk13 | —-0.102 |
| 92 | 21CC0141REHABILITATION OF DRAINAGE CANAL AT BARANGAY LUGAM, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.090 |
| 93 | 20CC0025ASPHALTING OF NIA ROAD AT SAN NICHOLAS, BULAKAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.5M | 100% | Low risk12 | —-0.098 |
| 94 | 19CC0215UPGRADING OF BARANGAY ROAD WITH DRAINAGE CANAL, SAN AGUSTIN, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.102 |
| 95 | 21CC0144REHABILITATION OF ROAD AT BARANGAY SERGIO BAYAN, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.103 |
| 96 | 21CC0094REHABILITATION OF ROAD, TUMANA, PUROK 3, TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.103 |
| 97 | 21CC0092REHABILITATION OF ROAD AT BARANGAY CORAZON, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.104 |
| 98 | 19CC0058CONSTRUCTION OF ROAD WITH DRAINAGE BRGY. POBLACION, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.102 |
| 99 | 20CC0159CONSTRUCTION OF ROAD, BRGY. SAN JUAN, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.5M | 100% | Low risk12 | —-0.099 |
| 100 | 19CC0222ROAD IMPROVEMENT OF LOCAL ROAD INCLUDING DRAINAGE BAGUMBAYAN, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk12 | —-0.102 |