Opening the dossier…
Opening the dossier…
Contractor dossier
129 projects on file, including joint ventures this contractor is part of.
Total projects
129
Total budget
₱1.3B
Average progress
96.9%
Completion rate
87.6%
Average risk score
27.8
Low risk on average, out of 100
Flagged as unusual
3
2.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 129 | ₱1.3B | 27.8 | 3 | 96.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 60 | ₱374M | 24.4 | 0 | 97.6% |
| Roads | 52 | ₱566.5M | 29.0 | 1 | 98.1% |
| Flood Control and Drainage | 10 | ₱312.2M | 30.5 | 0 | 96.8% |
| Water Provision and Storage | 3 | ₱25M | 40.8 | 0 | 96.1% |
| Bridges | 3 | ₱21.8M | 32.3 | 1 | 68.0% |
| GAA 2025 SSP | 1 | ₱19.6M | 94.2 | 1 | 77.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CI0084SIPAG-MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; REHABILITATION OF PNP REGIONAL TRAINING CENTER-MAGALANG, PAMPANGA | Region III | Pampanga 3rd DEO | On-Going | ₱19.6M | 78% | High risk94 | Flagged0.004 |
| 25CM0030CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, NBI BUILDING, KALAKLAN, OLONGAPO CITY | Region III | Zambales 2nd DEO | On-Going | ₱39.2M | 0% | High risk75 | —-0.005 |
| 25CM0065CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT ILWAS, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱19.7M | 88% | High risk74 | —-0.032 |
| 25CM0013ASSET PRESERVATION PROGRAM, CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS, OLONGAPO-BUGALLON RD., K0134+760-K0135+548, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱49M | 90% | High risk73 | —-0.035 |
| 25CM0061CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES AT AGLAO ELEMENTARY SCHOOL, BRGY. AGLAO, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱9.8M | 80% | High risk72 | —-0.032 |
| 25CM0054CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY BURGOS, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱5M | 100% | High risk72 | —-0.041 |
| 24CM0045BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT CASTILLEJOS SKILLS TRAINING INSTITUTE, BARANGAY SAN ROQUE, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱9.9M | 100% | High risk72 | —-0.066 |
| 25CM0073CONCRETING OF SITIO MALINGAW, BRGY. CAWAG FMR, BRGY. CAWAG, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱14.9M | 52% | High risk66 | Flagged0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21CL0095REPLACEMENT OF SAN JUAN LIPAY BRIDGE, LIPAY, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱9.4M | 4% | Medium risk53 | Flagged0.036 |
| 25CM0073CONCRETING OF SITIO MALINGAW, BRGY. CAWAG FMR, BRGY. CAWAG, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱14.9M | 52% | High risk66 | Flagged0.028 |
| 25CI0084SIPAG-MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; REHABILITATION OF PNP REGIONAL TRAINING CENTER-MAGALANG, PAMPANGA | Region III | Pampanga 3rd DEO | On-Going | ₱19.6M | 78% | High risk94 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 18CL0030PACKAGE 3- A. CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. BANGCOL, STA. CRUZ, ZAMBALES; B. CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. TAPOSO, CANDELARIA, ZAMBALES; C. CONSTRUCTION OF MULTI- PURPOSE BUILDING, | Region III | Zambales 1st DEO | Completed | ₱14.4M | 100% | Medium risk34 | —-0.092 |
| 27 | 25CM0028CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), PUROK 4, BARANGAY MANGAN-VACA, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱4.9M | 88% | Medium risk34 | —-0.061 |
| 28 | 24CM0037CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PUROK 3B, BRGY. CALAPACUAN, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱9.9M | 100% | Medium risk34 | —-0.100 |
| 29 | 20CM0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, NEW CABALAN SENIOR HIGH SCHOOL, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱4.8M | 100% | Medium risk34 | —-0.102 |
| 30 | 23CM0037CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CASTILLEJOS ELEMENTARY SCHOOL, BARANGAY SAN JUAN, CASTILL | Region III | Zambales 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk34 | —-0.055 |
| 31 | 20CM0069CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) WITH PAVEMENT AND BLEACHER, SAN NICOLAS, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱9.6M | 100% | Medium risk34 | —-0.099 |
| 32 | 24CI0060NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS: MANILA NORTH ROAD-K0090+291-K0090+949, K0090+949-K0093+499 | Region III | Pampanga 3rd DEO | Completed | ₱35M | 100% | Medium risk34 | —-0.101 |
| 33 | 20CM0065CONSTRUCTION OF GORDON HEIGHTS ROAD, BARANGAY GORDON HEIGHTS, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱9.7M | 100% | Medium risk33 | —-0.101 |
| 34 | 21CM0050REHABILITATION OF ROAD AT ELISEO TALA ST. PUROK 7, NEW CABALAN, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱8.6M | 100% | Medium risk33 | —-0.100 |
| 35 | 24CM0027FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, IMPROVEMENT OF MATAIN RIVER, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱49M | 100% | Medium risk33 | —-0.088 |
| 36 | 22CM0040MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, STA. FE ELEMENTARY SCHOOL, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱4.8M | 100% | Medium risk33 | —-0.101 |
| 37 | 20CM0008NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT- TERTIARY ROADS, SAN MARCELINO - NAGBAYTO ROAD - K0151+(-999) TO K0151+040, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱13.8M | 100% | Medium risk33 | —-0.098 |
| 38 | 25CM0033ASSET PRESERVATION PROGRAM, CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS SAN MARCELINO - SAN ANTONIO - SAN NARCISO RD, K0152+870 - K0153+000, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱9.8M | 100% | Medium risk33 | —-0.069 |
| 39 | 21CM0055REHABILITATION OF ROAD IPIL LANE TO MULAWIN LANE, BARANGAY OLD CABALAN, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱7.2M | 100% | Medium risk33 | —-0.100 |
| 40 | 21CM0054LOCAL PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, REHABILITATION OF ROAD AT UPPER MERCURIO ST. MABAYUAN, OLONGAPO CITY | Region III | Zambales 2nd DEO | Completed | ₱8.6M | 100% | Medium risk33 | —-0.100 |
| 41 | 21CM0020REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS OLONGAPO-BUGALLON ROAD, K0150+505 -K0151+000, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱10.7M | 100% | Medium risk33 | —-0.098 |
| 42 | 21CL0029CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY OMAYA, MUNICIPALITY OF SAN NARCISO ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱4.8M | 100% | Medium risk33 | —-0.099 |
| 43 | 24CI0054BASIC INFRASTRUCTURE PROGRAM BIP-BIP MULTI-PURPOSE BUILDINGS/FACILITIES SUPPORT SOCIAL SERVICES/CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAGALANG, PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱15.8M | 100% | Medium risk33 | —-0.105 |
| 44 | 23CM0033ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT SITIO BUKID, BARANGAY CALAPACUAN, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.100 |
| 45 | 21CL0039CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY LAPAZ, MUNICIPALITY OF SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱4.8M | 100% | Medium risk33 | —-0.099 |
| 46 | 25CM0004ASSET PRESERVATION PROGRAM, CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS, OLONGAPO-BUGALLON RD., K0153+474-K0153+542, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱7.8M | 100% | Medium risk33 | —-0.070 |
| 47 | 18CM0085CONST. OF LYING-IN AND BIRTHING FACILITY BARANGAY BALAYBAY, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱5.8M | 100% | Medium risk33 | —-0.100 |
| 48 | 20CL0027CONSTRUCTION OF MULTI-PURPOSE BUILDING, NAMATACAN, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.100 |
| 49 | 24CM0023CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT SITIO TIBAG PLAZA (COVERED COURT), BRGY. NAUGSOL, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.102 |
| 50 | 23CM0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CASTILLEJOS SKILLS TRAINING INSTITUTE, BARANGAY SAN ROQUE | Region III | Zambales 2nd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.100 |