Contractor dossier
152 projects on file, including joint ventures this contractor is part of.
Total projects
152
Total budget
₱3.5B
Average progress
89.2%
Completion rate
74.3%
Average risk score
48.9
Medium risk on average, out of 100
Flagged as unusual
7
4.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 151 | ₱3.5B | 48.9 | 7 | 89.2% |
| National Capital Region | 1 | ₱7.8M | 48.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 130 | ₱3.1B | 48.3 | 3 | 89.0% |
| Roads | 13 | ₱190.2M | 46.4 | 0 | 98.5% |
| Flood Control and Drainage | 5 | ₱33.8M | 47.3 | 0 | 80.0% |
| OTHER | 4 | ₱144.7M | 80.0 | 4 | 77.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DN0172CONSTRUCTION OF SCHOOL BUILDING, VICENTE MADRIGAL NATIONAL HIGH SCHOOL BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | On-Going | ₱49M | 95% | High risk85 | Flagged0.043 |
| 24DF0321CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), PHASE II, IMUS CITY, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱49M | 17% | High risk84 | Flagged0.062 |
| 24DF0275CONSTRUCTION OF 4-STOREY 16-CLASSROOM SCHOOL BUILDING IN AGUINALDO ELEMENTARY SCHOOL, BARANGAY TABON 2, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱39.8M | 100% | High risk82 | Flagged0.039 |
| 22DF0377LOCAL PROGRAM- NATIONAL BUILDING PROGRAM BUILDINGS AND OTHER STRUCTURES MULTIPURPOSE/ FACILITIES CONSTRUCTION OF CAVITE CITY HOSPITAL, CAVITE CITY | Region IV-A | Cavite 1st DEO | Completed | ₱143.3M | 100% | High risk79 | —-0.044 |
| 25DB0104LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF DPWH BATANGAS 1ST DEO OFFICE BUILDING, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱47.5M | 0% | High risk75 | —-0.006 |
| 24DF0203CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIESCONSTRUCTION (COMPLETION) OF CAVITE CITY HOSPITAL, CAVITE CITY, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱19.6M | 100% | High risk72 | —-0.065 |
| 24DB0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LUCSUHIN, CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱29.7M | 100% | High risk72 | —-0.039 |
| 25DC0165CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BOOT, TANAUAN CITY, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱7.8M | 51% | High risk72 | —-0.028 |
| 17DQ0064LOCALLY FUNDED PROJECTS - LOCAL INFRASTRUCTURE PROGRAM (LIP) - BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES, CONSTRUCTION/COMPLETION OF LIVELIHOOD CENTER IN BRGY. SAN NICOLAS, BACOOR CITY, CAVITE AND CONSTRUCTION OF BACOOR CITY JAIL, BACOOR | Region IV-A | Cavite 3rd DEO | Completed | ₱23.5M | 100% | High risk71 | —-0.073 |
| 22DF0191CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING AT CARSADANG BAGO II, IMUS, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱6.9M | 100% | High risk69 | Flagged0.006 |
| 24DI0180CONSTRUCTION OF A MULTI-PURPOSE BUILDING FOR THE LAGUNA REGIONAL HOSPITAL IN BARANGAY PUYPUY, MUNICIPALITY OF BAY, PROVINCE OF LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱141.4M | 55% | High risk65 | —-0.025 |
| 25DI0125CONSTRUCTION OF MULTI PURPOSE BUILDING (LAGUNA REGIONAL HOSPITAL) IN BRGY. PUYPUY, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱97.1M | 8% | High risk63 | —-0.022 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DF0321CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), PHASE II, IMUS CITY, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱49M | 17% | High risk84 | Flagged0.062 |
| 24DN0172CONSTRUCTION OF SCHOOL BUILDING, VICENTE MADRIGAL NATIONAL HIGH SCHOOL BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | On-Going | ₱49M | 95% | High risk85 | Flagged0.043 |
| 24DF0275CONSTRUCTION OF 4-STOREY 16-CLASSROOM SCHOOL BUILDING IN AGUINALDO ELEMENTARY SCHOOL, BARANGAY TABON 2, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱39.8M | 100% | High risk82 | Flagged0.039 |
| 23DQ0149CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENTRONG PANGKULTURA NG LUNGSOD NG BACOOR, PHASE 4), BARANGAY TABING DAGAT, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱66.9M | 48% | Medium risk55 | Flagged0.019 |
| 24DF0278CONSTRUCTION OF 2 UNITS 4-STOREY 8-CLASSROOM SCHOOL BUILDING IN CAVITE NATIONAL HIGH SCHOOL, CAVITE CITY, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱64.6M | 95% | Medium risk53 | Flagged0.015 |
| 24DD0294CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, LODLOD ELEMENTARY SCHOOL, BARANGAY LODLOD, LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱69.1M | 47% | Medium risk55 | Flagged0.010 |
| 22DF0191CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING AT CARSADANG BAGO II, IMUS, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱6.9M | 100% | High risk69 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 23DB0075CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY RIZAL, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱6.2M | 100% | Medium risk49 | —-0.104 |
| 77 | 23DQ0091REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MOLINO IV, BACOOR CITY, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱5.1M | 100% | Medium risk49 | —-0.103 |
| 78 | 24DD0014CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING IN SAN JUAN SENIOR HIGH SCHOOL, BARANGAY LIPAHAN, SAN JUAN, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱8.6M | 100% | Medium risk48 | —-0.106 |
| 79 | 22DF0237CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING AT MALAGASANG I-G PHASE II, IMUS, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.104 |
| 80 | 19DB0113CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH BATANGAS 1ST DEO, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱12.2M | 100% | Medium risk48 | —-0.101 |
| 81 | 22OC0087CONSTRUCTION OF MULTI-PURPOSE BUILDING AT AREA 3 PHASE 1, UPS 5, BARANGAY SAN ISIDRO,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱7.8M | 100% | Medium risk48 | —-0.101 |
| 82 | 21DC0226CONCRETING OF BRGY. SAN JUAN TO BRGY. POBLACION EAST FMR, BRGY. SAN JUAN AND BRGY. POBLACION EAST, ALITAGTAG, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱19.9M | 100% | Medium risk48 | —-0.050 |
| 83 | 24DN0130CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING IN BINANGONAN INTEGRATED NHS, BARANGAY TATALA BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | On-Going | ₱39.8M | 98% | Medium risk48 | —-0.012 |
| 84 | 18DN0210CONSTRUCTION OF 4 STOREY, 16 CLASSROOM, BINAYOYO ES (BINAYOYO INTEGRATED HS) ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱38.5M | 100% | Medium risk48 | —-0.049 |
| 85 | 22DB0133CONSTRUCTION (COMPLETION) OF BARANGAY HEALTH CENTER, BARANGAY NATIPUAN, NASUGBU,BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.105 |
| 86 | 24DC0160CONCRETING OF BRGY. SAN GREGORIO FMR, BRGY. SAN GREGORIO, LAUREL, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱15M | 81% | Medium risk48 | —-0.007 |
| 87 | 18DN0209CONSTRUCTION OF 3 STOREY, 15 CLASSROOM, JANOSA NATIONAL HIGH SCHOOL, BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱38.7M | 100% | Medium risk48 | —-0.048 |
| 88 | 18DI0167CONSTRUCTION OF 4 STOREY 12 CLASSROOMS AT P. RIZAL ES (PUTHO ES), LOS BAÑOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱40.4M | 100% | Medium risk48 | —-0.048 |
| 89 | 18DC0171CONSTRUCTION OF CLASSROOMS BATCH 3, FOUR STOREY SIXTEEN CLASSROOM LAUREL SENIOR HIGH SCHOOL, LAUREL, | Region IV-A | Batangas 3rd DEO | Completed | ₱37M | 100% | Medium risk48 | —-0.052 |
| 90 | 23DB0140CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION), RURAL HEALTH UNIT (PRIMARY HOSPITAL), TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.105 |
| 91 | 24DB0049CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY BIHIS, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.106 |
| 92 | 24DI0059CONSTRUCTION OF DRAINAGE CANAL, MULAWIN CIRCLE (GUIJO ST. GOING TO BARANGAY ESTRELLA), BARANGAY LANGGAM, SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.8M | 0% | Medium risk47 | —-0.013 |
| 93 | 24DI0046REHABILITATION OF DRAINAGE CANAL SYSTEM, BARANGAY SAN LORENZO, SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.8M | 100% | Medium risk47 | —-0.045 |
| 94 | 24DI0061CONSTRUCTION OF DRAINAGE CANAL ALONG LAGUNA RESETTLEMENT COMMUNITY SCHOOL GOING TO MAGSAYSAY, BARANGAY UNITED BAYANIHAN, SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.087 |
| 95 | 22DB0073CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY QUILITISAN, CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱5M | 100% | Medium risk47 | —-0.097 |
| 96 | 18DC0154CONSTRUCTION OF CLASSROOMS BATCH 1, THREE STOREY TWELVE CLASSROOM, JP LAUREL NATIONAL HIGH SCHOOL, T | Region IV-A | Batangas 3rd DEO | Completed | ₱29.1M | 100% | Medium risk47 | —-0.055 |
| 97 | 24DI0060CONSTRUCTION OF DRAINAGE CANAL SYSTEM, BARANGAY LANDAYAN, SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.087 |
| 98 | 18DH0117CONSTRUCTION OF FOUR (4) STOREY, SIXTEEN (16) CLASSROOM SCHOOL BUILDING, GATID E/S, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱36.9M | 100% | Medium risk47 | —-0.053 |
| 99 | 24DB0043CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUIDLING (BARANGAY HALL), BARANGAY CALAN, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱5M | 100% | Medium risk47 | —-0.105 |
| 100 | 24DI0028REHABILITATION OF REVETMENT ALONG SAN ISIDRO RIVER, BARANGAY RIVERSIDE, CITY OF SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱14.5M | 100% | Medium risk47 | —-0.089 |