Opening the dossier…
Opening the dossier…
Contractor dossier
346 projects on file, including joint ventures this contractor is part of.
Total projects
346
Total budget
₱3B
Average progress
93.4%
Completion rate
80.1%
Average risk score
36.3
Medium risk on average, out of 100
Flagged as unusual
17
4.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 346 | ₱3B | 36.3 | 17 | 93.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 155 | ₱768.6M | 29.3 | 1 | 94.4% |
| Roads | 114 | ₱1B | 37.6 | 4 | 94.1% |
| Flood Control and Drainage | 55 | ₱999.7M | 39.9 | 0 | 92.4% |
| GAA 2025 SSP | 10 | ₱116.7M | 90.2 | 9 | 70.3% |
| Bridges | 7 | ₱33.7M | 36.1 | 0 | 100.0% |
| OTHER | 5 | ₱59.7M | 72.7 | 3 | 95.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AJ0121CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY MALABAGO, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 73% | High risk95 | Flagged0.021 |
| 25AJ0125CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 100% | High risk95 | Flagged0.009 |
| 25AH0065CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY POBLACION OESTE, DAGUPAN CITY, PANGASINA | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 60% | High risk90 | Flagged0.025 |
| 25AH0070CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY SANTA MARIA, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 68% | High risk90 | Flagged0.022 |
| 25AH0061CONSTRUCTION (COMPLETION)OF MULTI-PURPOSE BUILDING,BARANGAY MALUED,DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk90 | Flagged0.029 |
| 25AH0047CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. MALABAGO,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 66% | High risk89 | Flagged0.023 |
| 25AH0074CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MAGSAYSAY, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 100% | High risk89 | Flagged0.008 |
| 25AH0072CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BOLO, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 55% | High risk89 | Flagged0.026 |
| 25AH0057CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY MERMER,MANAOAG,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk89 | Flagged0.029 |
| 25AH0068CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY MACAYUG,SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.9M | 100% | High risk85 | —-0.021 |
| 24AJ0093REHABILITATION OF LOCAL ROAD, BARANGAY LASIP, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱33.8M | 92% | High risk76 | Flagged0.001 |
| 24AJ0048REHABILITATION FLOOC CONTROL STRUCTURES ALONG INGALERA RIVER, BARANGAY ICAN, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱9.7M | 91% | High risk74 | Flagged0.003 |
| 25AJ0071ACCESS ROAD LEADING TO ST. VINCENT FERRER STATUE, BICAL NORTE-TANOLONG-INANLORENZA ROAD LINE, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.7M | 100% | High risk73 | —-0.011 |
| 23AJ0107CONSTRUCTION OF ROAD, BRGY. TAMBAC, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.6M | 100% | High risk73 | —-0.033 |
| 25AJ0017CONSTRUCTION OF ROAD, BARANGAY SANCAGULIS, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.8M | 100% | High risk68 | —-0.034 |
| 22AJ0053CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. CRUZ, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | High risk68 | —-0.057 |
| 24AH0196CONSTRUCTION OF MULTI-PURPOSE BUILDING(BRGY. HALL) AT BRGY. MALABAGO,MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 95% | High risk67 | Flagged0.039 |
| 22AJ0059CONSTRUCTION OF LOCAL ROAD, BRGY. PIAS, MAPANDAN, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.8M | 100% | High risk67 | —-0.056 |
| 22AJ0066CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. GAMATA, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | High risk66 | —-0.058 |
| 17AI0159CONCRETING OF BRGY. SUMABNIT ROAD, BRGY. SUMABNIT, BINALONAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱6.1M | 100% | High risk65 | —-0.055 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AH0196CONSTRUCTION OF MULTI-PURPOSE BUILDING(BRGY. HALL) AT BRGY. MALABAGO,MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 95% | High risk67 | Flagged0.039 |
| 25AH0061CONSTRUCTION (COMPLETION)OF MULTI-PURPOSE BUILDING,BARANGAY MALUED,DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk90 | Flagged0.029 |
| 25AH0057CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY MERMER,MANAOAG,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk89 | Flagged0.029 |
| 25AH0072CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BOLO, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 55% | High risk89 | Flagged0.026 |
| 25AH0065CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY POBLACION OESTE, DAGUPAN CITY, PANGASINA | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 60% | High risk90 | Flagged0.025 |
| 25AH0047CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. MALABAGO,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 66% | High risk89 | Flagged0.023 |
| 25AH0070CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY SANTA MARIA, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 68% | High risk90 | Flagged0.022 |
| 25AJ0121CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY MALABAGO, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 73% | High risk95 | Flagged0.021 |
| 24A00627CONSTRUCTION OF MULTI-PURPOSE BUILDING (STUDENT CENTER), BAYAMBANG CAMPUS - PANGASINAN STATE UNIVERSITY | Region I | Region I | On-Going | ₱9.8M | 35% | Medium risk44 | Flagged0.014 |
| 24AH0194CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM AT BARANGAY MACAYUG, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.7M | 50% | Medium risk39 | Flagged0.013 |
| 24AH0156CONCRETING OF BRGY. POBLACION TO BRGY.SAN GONZALO FMR,BRGY.POBLACION AND BRGY. SAN GONZALO,LABRADOR, | Region I | Pangasinan 2nd DEO | On-Going | ₱5M | 87% | Medium risk40 | Flagged0.013 |
| 25AJ0125CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 100% | High risk95 | Flagged0.009 |
| 25AH0074CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MAGSAYSAY, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 100% | High risk89 | Flagged0.008 |
| 24AH0147CONCRETING OF BRGY.ANONANG FMR, BRGY. ANONANG, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.5M | 100% | Medium risk44 | Flagged0.005 |
| 24AJ0048REHABILITATION FLOOC CONTROL STRUCTURES ALONG INGALERA RIVER, BARANGAY ICAN, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱9.7M | 91% | High risk74 | Flagged0.003 |
| 25AH0175CONCRETING OF BRGY. STA. INES FMR, BRGY. STA. INES, MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.4M | 78% | Medium risk46 | Flagged0.003 |
| 24AJ0093REHABILITATION OF LOCAL ROAD, BARANGAY LASIP, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱33.8M | 92% | High risk76 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 251 | 19AH0007CONSTRUCTION OF MULTI-PURPOSE BUILDING(BRGY. HALL)AT BRGY. GUEGUESANGEN, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.087 |
| 252 | 18AH0058CONSTRUCTION OF BUILDING, BRGY. NALSIAN, MANAOAG,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.087 |
| 253 | 21AJ0022CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), BARANGAY CANAN NORTE, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2M | 100% | Low risk24 | —-0.086 |
| 254 | 19AJ0087CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (DAY CARE CENTER) BRGY. DON PEDRO, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2M | 100% | Low risk24 | —-0.083 |
| 255 | 20AJ0025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. VIADO, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2M | 100% | Low risk24 | —-0.083 |
| 256 | 24AH0015ASSET PRESERVATION-CONST'N./UPGRADING/REHAB.FOR DRAINAGE-JUDGE JOSE DE VENECIA SR.AVE-K0209+500-K020 | Region I | Pangasinan 2nd DEO | Completed | ₱4.3M | 100% | Low risk24 | —-0.090 |
| 257 | 22AH0140CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BRGY. MALABAGO, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.4M | 100% | Low risk24 | —-0.087 |
| 258 | 19AH0031CONSTRUCTION OF MULTI-PURPOSE BUILDING(MANGALDAN NATIONAL H/S)MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱1.9M | 100% | Low risk23 | —-0.087 |
| 259 | 19AH0001CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT)AT BRGY.MERMER, MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱1.9M | 100% | Low risk23 | —-0.087 |
| 260 | 19AH0163CONSTRUCTION OF MULTI-PURPOSE BUILDING(BARANGAY HALL),BARANGAY 1, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2M | 100% | Low risk23 | —-0.088 |
| 261 | 24AH0005ASSET PRESERVATION-PREVENTIVE MAINT.-PANG.-LA UNION INTER PROVL.ROAD-K0380+600-K0380+694,DAG.CITY,PA | Region I | Pangasinan 2nd DEO | Completed | ₱2.2M | 100% | Low risk22 | —-0.084 |
| 262 | 19AG0157CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CAYUCAY, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱3.3M | 100% | Low risk22 | —-0.081 |
| 263 | 20AH0090CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MALUED, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.086 |
| 264 | 20AJ0072CONCRETING OF LOCAL ROAD, SITIO NEBALEW PUROK 2, 110M SITIO PUROK 1 AT BRGY. PANGALANGAN, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.086 |
| 265 | 20AH0109CONSTRUCTION OF ROAD, BRGY. CAPANDANAN, LINGAYEN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.087 |
| 266 | 20AH0085CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. LOMBOY, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.088 |
| 267 | 20AH0111CONSTRUCTION OF ROAD, BRGY. DULIG, LABRADOR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.086 |
| 268 | 20AH0106CONSTRUCTION OF ROAD, BRGY. BONGALON, LABRADOR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.086 |
| 269 | 19AJ0088CONSTRUCTION OF MULTI-PURPOSE BUILDING (AMPHITHEATER), DEPED SCHOOL DIVISION OFFICE, ROXAS BLVD., SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.087 |
| 270 | 20AJ0067CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (RED CROSS BUILDING), AGDAO, SAN CARLOS CITY,PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.082 |
| 271 | 20AH0060CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. BUER, AGUILAR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.086 |
| 272 | 19AH0217CONSTRUCTION OF STUDENT CENTER AT PANGASINAN STATE UNIVERSITY, LINGAYEN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.084 |
| 273 | 20AH0139CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JOSE, AGUILAR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.085 |
| 274 | 20AJ0022CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (RED CROSS BUILDING), BRGY. AGDAO, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2M | 100% | Low risk22 | —-0.082 |
| 275 | 20AJ0024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ABANON, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱2M | 100% | Low risk22 | —-0.082 |