346 projects on file, including joint ventures this contractor is part of.
Total projects
346
Total budget
₱3B
Average progress
93.4%
Completion rate
80.1%
Average risk score
36.3
Medium risk on average, out of 100
Flagged as unusual
17
4.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 346 | ₱3B | 36.3 | 17 | 93.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 155 | ₱768.6M | 29.3 | 1 | 94.4% |
| Roads | 114 | ₱1B | 37.6 | 4 | 94.1% |
| Flood Control and Drainage | 55 | ₱999.7M | 39.9 | 0 | 92.4% |
| GAA 2025 SSP | 10 | ₱116.7M | 90.2 | 9 | 70.3% |
| Bridges | 7 | ₱33.7M | 36.1 | 0 | 100.0% |
| OTHER | 5 | ₱59.7M | 72.7 | 3 | 95.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AJ0121CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY MALABAGO, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 73% | High risk95 | Flagged0.021 |
| 25AJ0125CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 100% | High risk95 | Flagged0.009 |
| 25AH0065CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY POBLACION OESTE, DAGUPAN CITY, PANGASINA | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 60% | High risk90 | Flagged0.025 |
| 25AH0070CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY SANTA MARIA, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 68% | High risk90 | Flagged0.022 |
| 25AH0061CONSTRUCTION (COMPLETION)OF MULTI-PURPOSE BUILDING,BARANGAY MALUED,DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk90 | Flagged0.029 |
| 25AH0047CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. MALABAGO,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 66% | High risk89 | Flagged0.023 |
| 25AH0074CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MAGSAYSAY, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 100% | High risk89 | Flagged0.008 |
| 25AH0072CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BOLO, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 55% | High risk89 | Flagged0.026 |
| 25AH0057CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY MERMER,MANAOAG,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk89 | Flagged0.029 |
| 25AH0068CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY MACAYUG,SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.9M | 100% | High risk85 | —-0.021 |
| 24AJ0093REHABILITATION OF LOCAL ROAD, BARANGAY LASIP, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱33.8M | 92% | High risk76 | Flagged0.001 |
| 24AJ0048REHABILITATION FLOOC CONTROL STRUCTURES ALONG INGALERA RIVER, BARANGAY ICAN, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱9.7M | 91% | High risk74 | Flagged0.003 |
| 25AJ0071ACCESS ROAD LEADING TO ST. VINCENT FERRER STATUE, BICAL NORTE-TANOLONG-INANLORENZA ROAD LINE, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.7M | 100% | High risk73 | —-0.011 |
| 23AJ0107CONSTRUCTION OF ROAD, BRGY. TAMBAC, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱9.6M | 100% | High risk73 | —-0.033 |
| 25AJ0017CONSTRUCTION OF ROAD, BARANGAY SANCAGULIS, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱4.8M | 100% | High risk68 | —-0.034 |
| 22AJ0053CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. CRUZ, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | High risk68 | —-0.057 |
| 24AH0196CONSTRUCTION OF MULTI-PURPOSE BUILDING(BRGY. HALL) AT BRGY. MALABAGO,MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 95% | High risk67 | Flagged0.039 |
| 22AJ0059CONSTRUCTION OF LOCAL ROAD, BRGY. PIAS, MAPANDAN, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.8M | 100% | High risk67 | —-0.056 |
| 22AJ0066CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. GAMATA, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | High risk66 | —-0.058 |
| 17AI0159CONCRETING OF BRGY. SUMABNIT ROAD, BRGY. SUMABNIT, BINALONAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱6.1M | 100% | High risk65 | —-0.055 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AH0196CONSTRUCTION OF MULTI-PURPOSE BUILDING(BRGY. HALL) AT BRGY. MALABAGO,MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 95% | High risk67 | Flagged0.039 |
| 25AH0061CONSTRUCTION (COMPLETION)OF MULTI-PURPOSE BUILDING,BARANGAY MALUED,DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk90 | Flagged0.029 |
| 25AH0057CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY MERMER,MANAOAG,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 40% | High risk89 | Flagged0.029 |
| 25AH0072CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BOLO, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 55% | High risk89 | Flagged0.026 |
| 25AH0065CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY POBLACION OESTE, DAGUPAN CITY, PANGASINA | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 60% | High risk90 | Flagged0.025 |
| 25AH0047CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. MALABAGO,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱1.9M | 66% | High risk89 | Flagged0.023 |
| 25AH0070CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING, BARANGAY SANTA MARIA, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 68% | High risk90 | Flagged0.022 |
| 25AJ0121CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY MALABAGO, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 73% | High risk95 | Flagged0.021 |
| 24A00627CONSTRUCTION OF MULTI-PURPOSE BUILDING (STUDENT CENTER), BAYAMBANG CAMPUS - PANGASINAN STATE UNIVERSITY | Region I | Region I | On-Going | ₱9.8M | 35% | Medium risk44 | Flagged0.014 |
| 24AH0194CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM AT BARANGAY MACAYUG, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.7M | 50% | Medium risk39 | Flagged0.013 |
| 24AH0156CONCRETING OF BRGY. POBLACION TO BRGY.SAN GONZALO FMR,BRGY.POBLACION AND BRGY. SAN GONZALO,LABRADOR, | Region I | Pangasinan 2nd DEO | On-Going | ₱5M | 87% | Medium risk40 | Flagged0.013 |
| 25AJ0125CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 100% | High risk95 | Flagged0.009 |
| 25AH0074CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MAGSAYSAY, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 100% | High risk89 | Flagged0.008 |
| 24AH0147CONCRETING OF BRGY.ANONANG FMR, BRGY. ANONANG, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.5M | 100% | Medium risk44 | Flagged0.005 |
| 24AJ0048REHABILITATION FLOOC CONTROL STRUCTURES ALONG INGALERA RIVER, BARANGAY ICAN, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱9.7M | 91% | High risk74 | Flagged0.003 |
| 25AH0175CONCRETING OF BRGY. STA. INES FMR, BRGY. STA. INES, MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.4M | 78% | Medium risk46 | Flagged0.003 |
| 24AJ0093REHABILITATION OF LOCAL ROAD, BARANGAY LASIP, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱33.8M | 92% | High risk76 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 25AJ0094CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG RIO DE VEGA RIVER, BARANGAY LILIMASAN, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱26.3M | 82% | Medium risk45 | —-0.036 |
| 77 | 25AH0131REHABILITATION OF ROAD, BARANGAY AMANSABINA,MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 68% | Medium risk45 | —-0.045 |
| 78 | 25AH0011CONSTRUCTION OF ROAD AT BARANGAY CAPAOAY, SAN JACINTO, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 100% | Medium risk45 | —-0.058 |
| 79 | 23AJ0023CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG SAN JUAN RIVER, SAN JUAN SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.074 |
| 80 | 20AH0050AGNO RIVER BASIN FLOOD CONTROL PROJ.-CONST'N. OF BANK PROTECTION ALONG BRGY. ANGARIAN BUGALLON, PANG | Region I | Pangasinan 2nd DEO | Completed | ₱17.1M | 100% | Medium risk45 | —-0.072 |
| 81 | 22AJ0024CONSTRUCTION OF ROAD, BARANGAY AMBAYAT 2ND, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.8M | 100% | Medium risk45 | —-0.089 |
| 82 | 25AH0012CONSTRUCTION OF ROAD, BARANGAY LANAS, MANGALDAN, PANGASINAN PHASE 1 | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 58% | Medium risk45 | —-0.042 |
| 83 | 25AH0017CONSTRUCTION OF ROAD AT BARANGAY STA.INES,MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 0% | Medium risk45 | —-0.022 |
| 84 | 25AJ0072CONSTRUCTION OF ACCESS ROAD LEADING TO ST. VINCENT FERRER STATUE, BICAL NORTE-TANOLONG-INANLORENZA ROAD LINE, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱28.4M | 33% | Medium risk45 | —-0.036 |
| 85 | 23AJ0096ACCESS ROAD LEADING TO ST. VINCENT FERRER STATUE, BICAL NORTE - TANOLONG - INANLORENZA ROAD LINE, BAYAMBANG, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱28.5M | 100% | Medium risk45 | —-0.090 |
| 86 | 25AH0014CONSTRUCTION OF ROAD AT BARANGAY TEBAG, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 0% | Medium risk45 | —-0.021 |
| 87 | 25AH0139IMPROVEMENT OF JUDGE JOSE DE VENECIA ROAD EXTENSION,DAGUPAN CITY, PANGASINAN (PHASE II) | Region I | Pangasinan 2nd DEO | On-Going | ₱19.2M | 0% | Medium risk45 | —-0.023 |
| 88 | 24AH0130CONSTRUCTION OF RIVER BANK PROTECTION, BARANGAY SAN JOSE, AGUILAR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱9.9M | 100% | Medium risk45 | —-0.070 |
| 89 | 25AJ0028CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY TALOSPATANG, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱9.5M | 100% | Medium risk45 | —-0.046 |
| 90 | 24AH0007ASSET PRESERVATION-PREVENTIVE MAINT.-MANGALDAN-MANAOAG-BINALONAN RD.-K0198+(-263)-K0198+200,K0198+20 | Region I | Pangasinan 2nd DEO | Completed | ₱28.7M | 100% | Medium risk45 | —-0.089 |
| 91 | 23AJ0030CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG INGALERA RIVER, BARANGAY AGDAO, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱19.4M | 100% | Medium risk45 | —-0.075 |
| 92 | 23AH0153CONST'N.OF MODIFIED STANDARD TWO(2)STOREY,TEN(10)CL,SB AT DAGUAPN CITY NHS,DAG.CITY,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱29.7M | 100% | Medium risk45 | —-0.036 |
| 93 | 22AJ0038CONSTRUCTION OF BOX CULVERT, BARANGAY BACNAR, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.073 |
| 94 | 25AH0135CONSTRUCTION OF DRAINAGE CANAL IN BARANGAY BOGTONG SILAG, MANGATAREM, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱9.6M | 0% | Medium risk45 | —-0.011 |
| 95 | 20AJ0079CONSTRUCTION OF SLOPE PROTECTION ALONG SINUCALAN RIVER, ALIBAGO, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱7.5M | 100% | Medium risk45 | —-0.075 |
| 96 | 24AH0008ASSET PRESERVATION-PREVENTIVE MAINT.-MANGALDAN-MANAOAG-BINALONAN RD.K0207+871-K0211+000,SAN JACINTO | Region I | Pangasinan 2nd DEO | Completed | ₱30.4M | 100% | Medium risk45 | —-0.088 |
| 97 | 23AH0074CONSTRUCTION OF RIVERBANK PROTECTION, BRGY.ORAAN EAST, MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱19.6M | 70% | Medium risk45 | —-0.016 |
| 98 | 23AH0039CONSTRUCTION OF DRAINAGE SYSTEM AT BARANGAY ANOLID, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.074 |
| 99 | 23AJ0053CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG APONIT RIVER, BARANGAY ABANON, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.074 |
| 100 | 19AI0136CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGALACAN RIVER, BRGY. MALASIN, POZORRUBIO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱24.1M | 100% | Medium risk45 | —-0.074 |