Opening the dossier…
Opening the dossier…
Contractor dossier
53 projects on file, including joint ventures this contractor is part of.
Total projects
53
Total budget
₱1.5B
Average progress
93.3%
Completion rate
54.7%
Below 70%
Average risk score
51.7
Medium risk on average, out of 100
Flagged as unusual
5
9.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 53 | ₱1.5B | 51.7 | 5 | 93.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 25 | ₱415.6M | 45.0 | 0 | 99.4% |
| Buildings and Facilities | 14 | ₱272.7M | 43.1 | 1 | 91.0% |
| GAA 2025 SSP | 4 | ₱196.8M | 95.0 | 3 | 66.1% |
| OTHER | 3 | ₱293.9M | 80.6 | 1 | 79.9% |
| Flood Control and Drainage | 2 | ₱191.8M | 59.8 | 0 | 100.0% |
| Bridges | 2 | ₱68.7M | 48.0 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱14.7M | 44.2 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱14.6M | 85.4 | 0 | 83.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KL0126CONSTRUCTION OF ROAD, BARANGAY RIZAL TO BARANGAY HINAPLANAN, CLAVERIA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱48.9M | 93% | High risk95 | —-0.001 |
| 25KL0123COMPLETION OF ST. PAUL HOSPITAL, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱98.9M | 41% | High risk95 | Flagged0.023 |
| 25KL0102CONSTRUCTION OF MULTI PURPOSE BUILDING (ALUBIJID PUBLIC MARKET) ALUBIJID, MISAMIS ORIENTAL (PHASE 2) | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.5M | 43% | High risk95 | Flagged0.011 |
| 25KL0033CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LANAO, ALUBIJID, MISAMIS ORIENTALALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.4M | 87% | High risk95 | Flagged0.001 |
| 24KL0123NORTHEASTERN MISAMIS GENERAL HOSPITAL VILLANUEVA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱148.5M | 55% | High risk89 | Flagged0.074 |
| 25KL0010CONSTRUCTION OF PROTECTION DIKE, ALTUBO-GUINOTANG CIS, ALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱14.6M | 83% | High risk85 | —-0.021 |
| 24KL0001CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SOLANA RIVER (UPSTREAM & DOWNSTREAM OF SOLANA BY-PASS BRIDGE) PACKAGE 2, JASAAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱96.5M | 100% | High risk78 | —-0.025 |
| 25KL0039CONSTRUCTION OF MISAMIS ORIENTAL 2ND DEO BUILDING, BALASE ST., POBLACION, EL SALVADOR CITY, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱48.9M | 84% | High risk75 | —-0.011 |
| 24KL0034CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULIG RIVER, UPSTREAM OF CABULIG BRIDGE I, JASAAN MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱95.3M | 100% | High risk61 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24KL0123NORTHEASTERN MISAMIS GENERAL HOSPITAL VILLANUEVA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱148.5M | 55% | High risk89 | Flagged0.074 |
| 25KL0123COMPLETION OF ST. PAUL HOSPITAL, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱98.9M | 41% | High risk95 | Flagged0.023 |
| 25KL0102CONSTRUCTION OF MULTI PURPOSE BUILDING (ALUBIJID PUBLIC MARKET) ALUBIJID, MISAMIS ORIENTAL (PHASE 2) | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.5M | 43% | High risk95 | Flagged0.011 |
| 24K00481CONST. OF REGIONAL METROLOGY & TESTING LABORATORY, AND MISAMIS ORIENTAL PROVINCIAL SCIENCE & TECHNOLOGY OFFICE | Region X | Region X | On-Going | ₱39.7M | 69% | Medium risk44 | Flagged0.003 |
| 25KL0033CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LANAO, ALUBIJID, MISAMIS ORIENTALALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.4M | 87% | High risk95 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25KL0126CONSTRUCTION OF ROAD, BARANGAY RIZAL TO BARANGAY HINAPLANAN, CLAVERIA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱48.9M | 93% | High risk95 | —-0.001 |
| 2 | 25KL0123COMPLETION OF ST. PAUL HOSPITAL, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱98.9M | 41% | High risk95 | Flagged0.023 |
| 3 | 25KL0102CONSTRUCTION OF MULTI PURPOSE BUILDING (ALUBIJID PUBLIC MARKET) ALUBIJID, MISAMIS ORIENTAL (PHASE 2) | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.5M | 43% | High risk95 | Flagged0.011 |
| 4 | 25KL0033CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LANAO, ALUBIJID, MISAMIS ORIENTALALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.4M | 87% | High risk95 | Flagged0.001 |
| 5 | 24KL0123NORTHEASTERN MISAMIS GENERAL HOSPITAL VILLANUEVA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱148.5M | 55% | High risk89 | Flagged0.074 |
| 6 | 25KL0010CONSTRUCTION OF PROTECTION DIKE, ALTUBO-GUINOTANG CIS, ALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱14.6M | 83% | High risk85 | —-0.021 |
| 7 | 24KL0001CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SOLANA RIVER (UPSTREAM & DOWNSTREAM OF SOLANA BY-PASS BRIDGE) PACKAGE 2, JASAAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱96.5M | 100% | High risk78 | —-0.025 |
| 8 | 25KL0039CONSTRUCTION OF MISAMIS ORIENTAL 2ND DEO BUILDING, BALASE ST., POBLACION, EL SALVADOR CITY, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱48.9M | 84% | High risk75 | —-0.011 |
| 9 | 24KL0034CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULIG RIVER, UPSTREAM OF CABULIG BRIDGE I, JASAAN MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱95.3M | 100% | High risk61 | —-0.070 |
| 10 | 24KL0002CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SOLANA RIVER (UPSTREAM & DOWNSTREAM OF SOLANA BY-PASS BRIDGE) PACKAGE 1, JASAAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱96.5M | 100% | Medium risk59 | —-0.069 |
| 11 | 23KL0087CONSTRUCTION OF HOSPITAL, SITIO MALA-IBA, NATUMOLAN, TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱99M | 100% | Medium risk56 | —-0.074 |
| 12 | 23KL0018NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, GINGOOG-CLAVERIA-VILLANUEVA RD K1357 + 000 - K1357 + 210, K1357 + 730 - K1358 + 120, K1358 + 230 - K1359 + 400, K1359 + 700 - K1360 + 000 | Region X | Misamis Oriental 2nd DEO | Completed | ₱65.2M | 100% | Medium risk51 | —-0.088 |
| 13 | 24K00099CONST. OF BY-PASS AND DIVERSION ROADS-PUERTO-CLAVERIA BY-PASS ROAD, TAGOLOAN BRIDGE 3 (PHASE III), MISAMIS ORIENTAL | Region X | Region X | On-Going | ₱49.1M | 100% | Medium risk49 | —-0.029 |
| 14 | 24K00114CONST. OF BY-PASS AND DIVERSION ROADS, CLAVERIA-BALINGOAN BY-PASS ROAD, PACKAGE 14, MISAMIS ORIENTAL | Region X | Region X | On-Going | ₱47.8M | 98% | Medium risk49 | —-0.054 |
| 15 | 23KL0069CONSTRUCTION OF ROAD AT BARANGAY HINAPLANAN TO BRGY. RIZAL, CLAVERIA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.093 |
| 16 | 24KB0192CONSTRUCTION OF BRIDGE INCLUDING APPROACHES, BRGY KIULOM, KITAOTAO, BUKIDNON | Region X | Bukidnon 2nd DEO | On-Going | ₱19.6M | 100% | Medium risk47 | —-0.026 |
| 17 | 24KL0085CONSTRUCTION OF EVACUATION CENTER, LUGAIT, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱27.7M | 100% | Medium risk46 | —-0.095 |
| 18 | 25KL0029CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY POBLACION TAGOLOAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱24.4M | 38% | Medium risk46 | —-0.043 |
| 19 | 24KL0113CONCRETING OF BRGY. MAPUTI FMR PHASE II, BRGY. MAPUTI, NAAWAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱14.9M | 100% | Medium risk46 | —-0.044 |
| 20 | 24KL0114CONCRETING OF BRGY. CALANGAHAN FMR, BRGY. CALANGAHAN, LUGAIT, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱14.9M | 100% | Medium risk46 | —-0.044 |
| 21 | 25KL0097ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - GINGOOG - CLAVERIA - VILLANUEVA RD - K1369+785 - K1370+000; K1377+200 - K1377+245; K1379+760 - K1380+742; K1385+000 - K1385+200; K1385+320 - K1385+480 | Region X | Misamis Oriental 2nd DEO | On-Going | ₱40.4M | 94% | Medium risk46 | —-0.059 |
| 22 | 24KL0111CONCRETING OF BRGY. LANISE FMR, BRGY. LANISE, CLAVERIA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱14.9M | 100% | Medium risk45 | —-0.041 |
| 23 | 23KL0048CONCRETING OF BRGY. PLARIDEL FMR, BRGY. PLARIDEL, CLAVERIA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱14.9M | 100% | Medium risk45 | —-0.042 |
| 24 | 24KL0087CONSTRUCTION OF ROAD, SITIO MIGBANDAY, BARANGAY POBLACION - SITIO MABINI, BARANGAY STA. CRUZ, CLAVERIA, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱29.7M | 100% | Medium risk45 | —-0.094 |
| 25 | 25KL0066CONSTRUCTION OF ROAD, BARANGAY ARGAYOSO, MANTICAO, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk45 | —-0.063 |