Opening the dossier…
Opening the dossier…
Contractor dossier
7 projects on file, including joint ventures this contractor is part of.
Total projects
7
Total budget
₱108.2M
Average progress
96.8%
Completion rate
71.4%
Average risk score
48.1
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 6 | ₱59.7M | 47.7 | 0 | 96.3% |
| Region VII | 1 | ₱48.4M | 50.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3 | ₱29.4M | 48.5 | 0 | 94.5% |
| Roads | 3 | ₱73.2M | 48.4 | 0 | 98.1% |
| Flood Control and Drainage | 1 | ₱5.5M | 46.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24IF0068CONSTRUCTION OF MULTI-PURPOSE BUILDING, DOG POUND FACILITY, BRGY. CAGBUHANGIN, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱14.7M | 100% | Medium risk52 | —-0.097 |
| 2 | 24IF0105CONSTRUCTION OF MULTI-PURPOSE BUILDING (ORMOC WELLNESS CENTER), ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱9.8M | 84% | Medium risk51 | —-0.051 |
| 3 | 22HB0083ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - REHABLITATION/RECONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - TAGBILARAN CITY CORELLA - SIKATUNA - LOBOC RD K0023+144 - K0023+234; K0023+407 - K00 | Region VII | Bohol 3rd DEO | Completed | ₱48.4M | 100% | Medium risk50 | —-0.093 |
| 4 | 23IF0031OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - ORMOC - BAYBAY - SOUTHERN LEYTE BDRY. RD. - K1013+064 - K1013+710, K1015+100 - K1015+503 | Region VIII | Leyte 4th DEO | Completed | ₱18.9M | 100% | Medium risk48 | —-0.095 |
| 5 | 25IF0033CONSTRUCTION OF IPIL DRAINAGE STRUCTURE, ORMOC CITY, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱5.9M | 94% | Medium risk47 | —-0.059 |
| 6 | 24IF0019CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY IPIL, ORMOC CITY | Region VIII | Leyte 4th DEO | Completed | ₱5.5M | 100% | Medium risk46 | —-0.079 |
| 7 | 23IF0128CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MACARIO, MERIDA, LEYTE | Region VIII | Leyte 4th DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.055 |