Opening the dossier…
Opening the dossier…
Contractor dossier
55 projects on file, including joint ventures this contractor is part of.
Total projects
55
Total budget
₱245.3M
Average progress
93.0%
Completion rate
60.0%
Below 70%
Average risk score
35.9
Medium risk on average, out of 100
Flagged as unusual
3
5.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 54 | ₱239.4M | 34.9 | 2 | 94.1% |
| Region XII | 1 | ₱5.9M | 93.8 | 1 | 32.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 42 | ₱174.7M | 33.9 | 0 | 93.6% |
| Water Provision and Storage | 7 | ₱30.6M | 29.5 | 0 | 99.1% |
| Roads | 3 | ₱23.2M | 35.4 | 0 | 100.0% |
| OTHER | 2 | ₱10.9M | 72.6 | 2 | 76.8% |
| GAA 2025 SSP | 1 | ₱5.9M | 93.8 | 1 | 32.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ME0089CONSTRUCTION OF SAPU PADIDU MULTI-PURPOSE BUILDING, SAPU PADIDU, MALAPATAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.9M | 33% | High risk94 | Flagged0.038 |
| 24LD0131CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRIBAL HALL), MAGSAYSAY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱5.9M | 97% | High risk73 | Flagged0.006 |
| 24LD0104CONSTRUCTION OF MULTI-PURPOSE BUILDING ( TRIBAL HALL OF TAGAKAOLO TRIBE), PUROK ACASIA 1, ASUCENA STREET, BARANGAY POBLACION, MALALAG, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱5M | 57% | High risk72 | Flagged0.023 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ME0089CONSTRUCTION OF SAPU PADIDU MULTI-PURPOSE BUILDING, SAPU PADIDU, MALAPATAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.9M | 33% | High risk94 | Flagged0.038 |
| 24LD0104CONSTRUCTION OF MULTI-PURPOSE BUILDING ( TRIBAL HALL OF TAGAKAOLO TRIBE), PUROK ACASIA 1, ASUCENA STREET, BARANGAY POBLACION, MALALAG, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱5M | 57% | High risk72 | Flagged0.023 |
| 24LD0131CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRIBAL HALL), MAGSAYSAY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱5.9M | 97% | High risk73 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22LD0021CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY NORTHERN PALIGUE, PADADA, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2M | 100% | Low risk15 | —-0.090 |
| 52 | 22LD0016CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HARADA BUTAI, SULOP, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2M | 100% | Low risk15 | —-0.089 |
| 53 | 24LD0047CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY POBLACION, SULOP, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2M | 100% | Low risk15 | —-0.089 |
| 54 | 21LD0036CONSTRUCTION/REHABILITATION OF EVACUATION CENTER/GYMNASIUM AT APO BEACH, ZONE III, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱2M | 100% | Low risk15 | —-0.090 |
| 55 | 21LD0015REHABILITATION OF MULTI-PURPOSE BUILDING (BARANGAY GYMNASIUM), BARANGAY LITOS, SULOP, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱1.5M | 100% | Low risk11 | —-0.089 |