Contractor dossier
14 projects on file, including joint ventures this contractor is part of.
Total projects
14
Total budget
₱96.6M
Average progress
91.8%
Completion rate
50.0%
Below 70%
Average risk score
57.0
Medium risk on average, out of 100
Flagged as unusual
3
21.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 14 | ₱96.6M | 57.0 | 3 | 91.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 8 | ₱45.6M | 42.9 | 0 | 99.5% |
| GAA 2025 SSP | 2 | ₱16.8M | 95.2 | 2 | 83.4% |
| OTHER | 2 | ₱19.7M | 83.8 | 1 | 61.4% |
| Water Provision and Storage | 1 | ₱9.7M | 49.6 | 0 | 100.0% |
| Roads | 1 | ₱4.8M | 46.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IJ0051CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BAGACAY INTEGRATED SCHOOL, BARANGAY BAGACAY, CALBAYOG CITY | Region VIII | Samar 1st DEO | On-Going | ₱9.9M | 72% | High risk95 | Flagged0.014 |
| 25IJ0046CSSP: REHABILITATION/RECONSTRUCTION OF ROAD, BARANGAY RIZAL I, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱6.9M | 95% | High risk95 | Flagged0.007 |
| 25IJ0061CONCRETING OF BRGY. CURRY TO BRGY. MATAYONAS FMR, BRGY. CURRY AND BRGY. MATAYONAS, STA. MARGARITA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱14.8M | 37% | High risk90 | Flagged0.058 |
| 25IJ0033CSSP: CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) LIBUCAN DAKU CIRCUMFERENTIAL ROAD, TARANGNAN, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱4.9M | 86% | High risk78 | —-0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IJ0061CONCRETING OF BRGY. CURRY TO BRGY. MATAYONAS FMR, BRGY. CURRY AND BRGY. MATAYONAS, STA. MARGARITA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱14.8M | 37% | High risk90 | Flagged0.058 |
| 25IJ0051CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BAGACAY INTEGRATED SCHOOL, BARANGAY BAGACAY, CALBAYOG CITY | Region VIII | Samar 1st DEO | On-Going | ₱9.9M | 72% | High risk95 | Flagged0.014 |
| 25IJ0046CSSP: REHABILITATION/RECONSTRUCTION OF ROAD, BARANGAY RIZAL I, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱6.9M | 95% | High risk95 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25IJ0051CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BAGACAY INTEGRATED SCHOOL, BARANGAY BAGACAY, CALBAYOG CITY | Region VIII | Samar 1st DEO | On-Going | ₱9.9M | 72% | High risk95 | Flagged0.014 |
| 2 | 25IJ0046CSSP: REHABILITATION/RECONSTRUCTION OF ROAD, BARANGAY RIZAL I, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱6.9M | 95% | High risk95 | Flagged0.007 |
| 3 | 25IJ0061CONCRETING OF BRGY. CURRY TO BRGY. MATAYONAS FMR, BRGY. CURRY AND BRGY. MATAYONAS, STA. MARGARITA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱14.8M | 37% | High risk90 | Flagged0.058 |
| 4 | 25IJ0033CSSP: CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) LIBUCAN DAKU CIRCUMFERENTIAL ROAD, TARANGNAN, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱4.9M | 86% | High risk78 | —-0.005 |
| 5 | 24IJ0097CSSP: CONSTRUCTION OF MULTI-PURPOSE BLDG, CALBAYOG CITY NATIONAL HIGH SCHOOL (GYMNASIUM), BRGY. HAMORAWON, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱9.9M | 96% | Medium risk51 | —-0.056 |
| 6 | 23IJ0083CSSP: CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY CAUTOD, STA. MARGARITA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱9.7M | 100% | Medium risk50 | —-0.017 |
| 7 | 25IJ0001CSSP: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM TRIP), ACCESS ROAD LEADING TO PINIPISAKAN FALLS, SAN JORGE, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱4.8M | 100% | Medium risk47 | —-0.062 |
| 8 | 23IJ0092CONSTRUCTION OF ONR (1) STOREY - TWO (2) CLASSROOM SCHOOL BUILDING, SAN ISIDRO ELEMENTARY SCHOOL, ALMAGRO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱5.7M | 100% | Medium risk47 | —-0.055 |
| 9 | 22IJ0089CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN POLICARPO, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.097 |
| 10 | 23IJ0095CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOM SCHOOL BUILDING STO. NIÑO CENTRAL ELEMENTARY SCHOOL, SANTO NIÑO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱5.8M | 100% | Medium risk45 | —-0.055 |
| 11 | 23IJ0097CONSTRUCTION OF ONE (1) STOREY -TWO (2) CLASSROOM SCHOOL BUILDING, INUBOD ELEMENTARY SCHOOL, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.048 |
| 12 | 23IJ0101CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOM SCHOOL BUILDING, NAGPAPACAO ELEMENTARY SCHOOL, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.048 |
| 13 | 22IJ0091CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DAWO, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Medium risk43 | —-0.097 |
| 14 | 24IJ0085CSSP: CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY PALANAS CARA, CALBAYOG, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱3M | 100% | Low risk25 | —-0.099 |