11 projects on file, including joint ventures this contractor is part of.
Total projects
11
Total budget
₱110.9M
Average progress
89.9%
Completion rate
9.1%
Below 70%
Average risk score
59.6
Medium risk on average, out of 100
Flagged as unusual
2
18.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 11 | ₱110.9M | 59.6 | 2 | 89.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3 | ₱20.8M | 53.1 | 0 | 90.5% |
| GAA 2025 SSP | 2 | ₱11.7M | 93.9 | 2 | 67.9% |
| Roads | 2 | ₱56.3M | 48.7 | 0 | 95.4% |
| GAA 2025 OO-2 | 1 | ₱14.7M | 87.8 | 0 | 90.9% |
| OTHER | 1 | ₱2.6M | 70.0 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱2M | 27.1 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱2.9M | 26.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PK0049BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LOWER UMA, LUBUAGAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱5.9M | 73% | High risk95 | Flagged0.016 |
| 25PD0098BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT PUROK 6, ASIN ROAD, BAGUIO CITY | Cordillera Administrative Region | Baguio City DEO | On-Going | ₱5.8M | 63% | High risk93 | Flagged0.017 |
| 25PK0018ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱14.7M | 91% | High risk88 | —-0.005 |
| 25PK0044CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTOR SYSTEMS - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR SYSTEM | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱2.6M | 100% | High risk70 | —-0.002 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PD0098BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT PUROK 6, ASIN ROAD, BAGUIO CITY | Cordillera Administrative Region | Baguio City DEO | On-Going | ₱5.8M | 63% | High risk93 | Flagged0.017 |
| 25PK0049BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LOWER UMA, LUBUAGAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱5.9M | 73% | High risk95 | Flagged0.016 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PK0049BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LOWER UMA, LUBUAGAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱5.9M | 73% | High risk95 | Flagged0.016 |
| 2 | 25PD0098BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT PUROK 6, ASIN ROAD, BAGUIO CITY | Cordillera Administrative Region | Baguio City DEO | On-Going | ₱5.8M | 63% | High risk93 | Flagged0.017 |
| 3 | 25PK0018ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱14.7M | 91% | High risk88 | —-0.005 |
| 4 | 25PK0044CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTOR SYSTEMS - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR SYSTEM | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱2.6M | 100% | High risk70 | —-0.002 |
| 5 | 24PL0039CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (OPEN GYM) AT BNHS/SNHS, BARANGAY BANTAY AND BARANGAY SANTOR, TABUK CITY AND RIZAL, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱5.9M | 94% | Medium risk54 | —-0.038 |
| 6 | 24PK0062CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN LUBUAGAN NATIONAL HIGH SCHOOL, BARANGAY UMA, LUBUAGAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱5M | 100% | Medium risk53 | —-0.008 |
| 7 | 24PK0073BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (WEAVING CENTER), LUBUAGAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱9.9M | 78% | Medium risk52 | —-0.038 |
| 8 | 24PK0023ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS: TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0459+(-260)-K0459+000, K0459+(-320)-K0459+(-287), K0459+(-350)-K0459+(-3 | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱29.6M | 91% | Medium risk49 | —-0.045 |
| 9 | 24PK0037ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: PAVING OF UNPAVED ROADS - TERTIARY ROADS: LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0471+400 - K0472+054, LUBUAGAN, KALINGA | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱26.6M | 100% | Medium risk48 | —-0.049 |
| 10 | 25PK0015ORGANIZATIONAL OUTCOME 2: PROTECTS LIVES AND PROPERTIES AGAINST MAJOR FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, COMPOP SONG-AK, MABILENG, LUBUAGAN, | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱2M | 100% | Low risk27 | —-0.036 |
| 11 | 24PK0067CONVERGENCE AND SPECIAL SUPPRT PROGRAM / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTOR SYSTEMS - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR SYSTEM | Cordillera Administrative Region | Upper Kalinga DEO | Completed | ₱2.9M | 100% | Low risk27 | —-0.045 |