Contractor dossier
191 projects on file, including joint ventures this contractor is part of.
Total projects
191
Total budget
₱9.7B
Average progress
94.3%
Completion rate
85.3%
Average risk score
51.9
Medium risk on average, out of 100
Flagged as unusual
4
2.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 171 | ₱8.6B | 51.3 | 2 | 94.3% |
| Region III | 10 | ₱713.5M | 61.4 | 2 | 93.8% |
| Region II | 6 | ₱127.9M | 45.1 | 0 | 100.0% |
| Region IV-A | 4 | ₱295.4M | 64.9 | 0 | 87.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 100 | ₱5.4B | 50.8 | 0 | 97.1% |
| Flood Control and Drainage | 46 | ₱2.6B | 54.4 | 2 | 90.7% |
| Roads | 34 | ₱1.4B | 50.0 | 0 | 95.6% |
| OTHER | 9 | ₱233.4M | 55.1 | 1 | 88.9% |
| GAA 2025 SSP | 1 | ₱94.6M | 94.9 | 1 | 60.8% |
| Bridges | 1 | ₱19.2M | 46.9 | 0 | 15.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OF0157IMPROVEMENT OF DRAINAGE SYSTEMS AT BRGY. HOLY SPIRIT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱94.6M | 61% | High risk95 | Flagged0.022 |
| 23CC0528CONSTRUCTION OF CONCRETE RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAYS AT BARANGAY SANTO CRISTO, MALOLOS CITY, BULACAN PHASE II | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk82 | Flagged0.008 |
| 23CC0527CONSTRUCTION OF CONCRETE RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAYS AT BARANGAY SANTO CRISTO, MALOLOS CITY, BULACAN PHASE I | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk82 | Flagged0.008 |
| 20OG0117FUNDING REQUIREMENT FOR THE RESILIENCE INSTITUTE, U.P. DILIMAN, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48.8M | 0% | High risk82 | Flagged0.082 |
| 24CC0029CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY IGULOT, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 100% | High risk79 | —-0.019 |
| 24DF0073ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG CAÑAS RIVER, BARANGAY BUNGA, PHASE IV, TANZA | Region IV-A | Cavite 1st DEO | Completed | ₱96.5M | 100% | High risk78 | —-0.051 |
| 25CC0180CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY MALIS (PUROK 2), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱78.7M | 59% | High risk76 | —-0.013 |
| 25CC0053CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY DAUNGAN (PUROK 4), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱78.7M | 79% | High risk76 | —-0.022 |
| 24CC0166CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY DALIG (PUROK 2 TO PUROK 3), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | High risk76 | —-0.060 |
| 25DF0075ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMROAD WIDENING - TERTIARY ROADSINDANG-ALFONSO VIA LUKSUHIN RD - K0061 + 356 - K0062 + 895 | Region IV-A | Cavite 1st DEO | On-Going | ₱82.6M | 50% | High risk71 | —-0.028 |
| 25OD0218INSTALLATION OF NEW UNIT PUMPS WITH FLOOD GATE AT COLOONG PUMPING STATION WITH CONSTRUCTION OF PUMP HOUSE AT BARANGAY COLOONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.5M | 29% | High risk67 | —-0.012 |
| 20OD0220CONSTRUCTION OF NEW VALPOLY CAMPUS, BRGY. PARADA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱415.9M | 100% | High risk66 | —-0.047 |
| 21OD0134CONSTRUCTION OF FINANCE BUILDING EXPANSION, VALENZUELA CITY HALL, KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱295.1M | 100% | High risk66 | —-0.013 |
| 25OD0353CONSTRUCTION OF MULTI-PURPOSE BUILDING (FINANCE BUILDING EXPANSION), VALENZUELA CITY (PHASE III) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱191.3M | 0% | High risk66 | —-0.006 |
| 23OD0232CONSTRUCTION OF MULTI-PURPOSE BUILDING (FINANCE BUILDING EXPANSION PHASE II) BRGY. KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱189.4M | 71% | High risk66 | —-0.016 |
| 25OD0201CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CASILI CREEK, CALOOCAN CITY (PHASE 1) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱96M | 55% | High risk65 | —-0.038 |
| 18OG0108CONSTRUCTION OF PDEA HNQ BUILDING COMPLEX, NIA ROAD, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱175.7M | 100% | High risk65 | —-0.056 |
| 21OA0035CONSTRUCTION OF MULTI-PURPOSE FACILITIES, NAVOTAS POLYTECHNIC COLLEGE, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱183.3M | 100% | High risk65 | —-0.061 |
| 24DF0088ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG CAÑAS RIVER, BRGY BUNGA, PHASE V, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.077 |
| 18OD0192CONSTRUCTION OF A MULTI-PURPOSE BUILDING, PAMANTASAN NG LUNGSOD NG VALENZUELA BARANGAY MAYSAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20OG0117FUNDING REQUIREMENT FOR THE RESILIENCE INSTITUTE, U.P. DILIMAN, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48.8M | 0% | High risk82 | Flagged0.082 |
| 25OF0157IMPROVEMENT OF DRAINAGE SYSTEMS AT BRGY. HOLY SPIRIT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱94.6M | 61% | High risk95 | Flagged0.022 |
| 23CC0528CONSTRUCTION OF CONCRETE RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAYS AT BARANGAY SANTO CRISTO, MALOLOS CITY, BULACAN PHASE II | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk82 | Flagged0.008 |
| 23CC0527CONSTRUCTION OF CONCRETE RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAYS AT BARANGAY SANTO CRISTO, MALOLOS CITY, BULACAN PHASE I | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk82 | Flagged0.008 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 23OF0019REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG ILANG - ILANG CREEK LEADING TO TULLAHAN RIVER, BARANGAY STA. MONICA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱48M | 100% | Medium risk50 | —-0.086 |
| 102 | 21OB0058CONSTRUCTION OF TWO (2) STOREY MULTIPURPOSE BUILDING AT TIERRA VERDE, BRGY. MANGGAHAN, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱28.5M | 100% | Medium risk50 | —-0.101 |
| 103 | 25OG0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 5, BARANGAY BAGUMBAYAN, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48M | 19% | Medium risk50 | —-0.033 |
| 104 | 25OG0040CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 6, BARANGAY BAGUMBAYAN, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48M | 19% | Medium risk50 | —-0.033 |
| 105 | 25OG0038CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 4, BARANGAY BAGUMBAYAN, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48M | 24% | Medium risk50 | —-0.036 |
| 106 | 23OG0063REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG SAN JUAN RIVER (PHASE XVIII), QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱47.9M | 100% | Medium risk50 | —-0.088 |
| 107 | 20OG0091CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. UP CAMPUS, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱26.6M | 100% | Medium risk50 | —-0.099 |
| 108 | 24OF0027CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND TRIBUTARIES (PHASE 8), BARANGAY BAGONG SILANGAN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱48.5M | 90% | Medium risk50 | —-0.041 |
| 109 | 25OF0013CONSTRUCTION OF FLOOD STRUCTURE AND TRIBUTARIES AT BARANGAY PAYATAS (PHASE 9), QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱48.5M | 99% | Medium risk50 | —-0.056 |
| 110 | 25OF0011CONSTRUCTION OF FLOOD STRUCTURE AND TRIBUTARIES AT BARANGAY BAGONG SILANGAN (PHASE 9), QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱48.5M | 100% | Medium risk50 | —-0.087 |
| 111 | 23OD0035CONSTRUCTION OF BOX CULVERT AT 3S COMPOUND, BARANGAY UGONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱47.9M | 100% | Medium risk50 | —-0.086 |
| 112 | 23OF0166CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BISTEKVILLE 15 (DISASTER RESILIENCE CENTER), BRGY. SAUYO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱14.6M | 100% | Medium risk49 | —-0.102 |
| 113 | 18OG0104CONSTRUCTION OF 4-STOREY-12 CLASSROOM SCHOOL BUILDING, FLORA YLAGAN HIGH SCHOOL WITH SITE DEVELOPMENT, BRGY. PINYAHAN, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱28.1M | 100% | Medium risk49 | —-0.095 |
| 114 | 17OG0049ASSET PRESERVATION OF NATIONAL ROADS-PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING -E. RODRIGUEZ JR. AVE. - K0012+-406 - K0014+-348, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱21M | 100% | Medium risk49 | —-0.069 |
| 115 | 21OA0038CONST(COMPL.) OF MPB, PHASE 2 AREA 1 BRGY. NBBS DAGAT-DAGATAN, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱19.6M | 100% | Medium risk49 | —-0.101 |
| 116 | 23OF0023CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND TRIBUTARIES AT BARANGAY BAGONG SILANGAN, QUEZON CITY (PHASE 7) | National Capital Region | Quezon City 1st DEO | Completed | ₱48M | 100% | Medium risk49 | —-0.085 |
| 117 | 23OG0064REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG SAN JUAN RIVER (PHASE XIX), QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.088 |
| 118 | 23OG0065REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG SAN JUAN RIVER (PHASE XX), QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.088 |
| 119 | 18OG0114CONSTRUCTION OF 4 STOREY - 16 CLASSROOM BUILDING, PINYAHAN ELEMENTARY SCHOOL, QUEZON CITY 4TH LD | National Capital Region | Quezon City 2nd DEO | Completed | ₱44.8M | 100% | Medium risk49 | —-0.044 |
| 120 | 22O00034CONSTRUCTION OF HPA ANNEX BUILDING WITH PARKING AREA AND GROUND DEVELOPMENT, FORT BONIFACIO, TAGUIG CITY | National Capital Region | National Capital Region | Completed | ₱24.1M | 100% | Medium risk49 | —-0.095 |
| 121 | 22OG0019CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING WITH SITE DEVELOPMENT AT BELARMINO SENIOR HIGH SCHOOL, BARANGAY MILAGROSA, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱19.8M | 100% | Medium risk49 | —-0.102 |
| 122 | 23OA0030CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE II AREA I, BRGY. NBBS DAGAT-DAGATAN, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱14.7M | 100% | Medium risk49 | —-0.103 |
| 123 | 22OA0093CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE II AREA I, BARANGAY DAGAT-DAGATAN, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱11.8M | 100% | Medium risk48 | —-0.104 |
| 124 | 22OG0040CONSTRUCTION OF CGEA 25-BED STATION HOSPITAL, CAMP GENERAL EMILIO AGUINALDO, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱14.7M | 100% | Medium risk48 | —-0.102 |
| 125 | 24OA0060CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE II AREA I, BARANGAY NBBS DAGAT-DAGATAN, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱11.6M | 100% | Medium risk48 | —-0.104 |