Contractor dossier
9 projects on file, including joint ventures this contractor is part of.
Total projects
9
Total budget
₱170.3M
Average progress
78.0%
Completion rate
0.0%
Below 70%
Average risk score
66.0
High risk on average, out of 100
Flagged as unusual
5
55.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 9 | ₱170.3M | 66.0 | 5 | 78.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 6 | ₱141.4M | 69.7 | 2 | 98.4% |
| Water Provision and Storage | 3 | ₱28.9M | 58.6 | 3 | 37.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24J00276CONSTRUCTION OF KAGAY TO MALIMBAYA ROAD, INDANAN, SULU | Region IX | Region IX | On-Going | ₱49.7M | 91% | High risk73 | Flagged0.044 |
| 24J00308REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ALONG MAIMBUNG-PARANG ROAD, MAIMBUNG, SULU | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk70 | Flagged0.031 |
| 24J00076REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - JOLO - TAGLIBI - TIPTIPON ROAD | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk69 | —-0.010 |
| 24J00087ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LAPA, MAIMBUNG, SULU | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk69 | —-0.010 |
| 24J00180REHABILITATION OF BRGY. BUANSA TO LAUM SAING ROAD KM. 0 + 000 - KM. 0 + 320.00, BRGY. KAGAY INDANAN | Region IX | Region IX | On-Going | ₱9.6M | 100% | High risk69 | —-0.020 |
| 24J00181REHABILITATION OF SITIO MUMANG TO SITIO IGANGAN ROAD KM. 0 + 000 - KM 0 + 362.00 BRGY. TANDUH BAGUA, PATIKUL | Region IX | Region IX | On-Going | ₱9.6M | 100% | High risk68 | —-0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24J00276CONSTRUCTION OF KAGAY TO MALIMBAYA ROAD, INDANAN, SULU | Region IX | Region IX | On-Going | ₱49.7M | 91% | High risk73 | Flagged0.044 |
| 24J00308REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ALONG MAIMBUNG-PARANG ROAD, MAIMBUNG, SULU | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk70 | Flagged0.031 |
| 23J00277CONSTRUCTION OF SOLAR WATER SYSTEM, SULU STATE COLLEGE, JOLO, SULU | Region IX | Region IX | On-Going | ₱9.6M | 26% | Medium risk59 | Flagged0.014 |
| 23J00276CONSTRUCTION OF SOLAR WATER SYSTEM, SULU SANITARIUM AND GENERAL HOSPITAL, JOLO, SULU | Region IX | Region IX | On-Going | ₱9.6M | 43% | Medium risk59 | Flagged0.008 |
| 23J00275CONSTRUCTION OF SOLAR WATER SYSTEM, SULU PROVINCIAL CAPITOL, PATIKUL, SULU | Region IX | Region IX | On-Going | ₱9.6M | 43% | Medium risk59 | Flagged0.008 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24J00276CONSTRUCTION OF KAGAY TO MALIMBAYA ROAD, INDANAN, SULU | Region IX | Region IX | On-Going | ₱49.7M | 91% | High risk73 | Flagged0.044 |
| 2 | 24J00308REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ALONG MAIMBUNG-PARANG ROAD, MAIMBUNG, SULU | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk70 | Flagged0.031 |
| 3 | 24J00076REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - JOLO - TAGLIBI - TIPTIPON ROAD | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk69 | —-0.010 |
| 4 | 24J00087ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LAPA, MAIMBUNG, SULU | Region IX | Region IX | On-Going | ₱24.1M | 100% | High risk69 | —-0.010 |
| 5 | 24J00180REHABILITATION OF BRGY. BUANSA TO LAUM SAING ROAD KM. 0 + 000 - KM. 0 + 320.00, BRGY. KAGAY INDANAN | Region IX | Region IX | On-Going | ₱9.6M | 100% | High risk69 | —-0.020 |
| 6 | 24J00181REHABILITATION OF SITIO MUMANG TO SITIO IGANGAN ROAD KM. 0 + 000 - KM 0 + 362.00 BRGY. TANDUH BAGUA, PATIKUL | Region IX | Region IX | On-Going | ₱9.6M | 100% | High risk68 | —-0.012 |
| 7 | 23J00276CONSTRUCTION OF SOLAR WATER SYSTEM, SULU SANITARIUM AND GENERAL HOSPITAL, JOLO, SULU | Region IX | Region IX | On-Going | ₱9.6M | 43% | Medium risk59 | Flagged0.008 |
| 8 | 23J00277CONSTRUCTION OF SOLAR WATER SYSTEM, SULU STATE COLLEGE, JOLO, SULU | Region IX | Region IX | On-Going | ₱9.6M | 26% | Medium risk59 | Flagged0.014 |
| 9 | 23J00275CONSTRUCTION OF SOLAR WATER SYSTEM, SULU PROVINCIAL CAPITOL, PATIKUL, SULU | Region IX | Region IX | On-Going | ₱9.6M | 43% | Medium risk59 | Flagged0.008 |