Contractor dossier
99 projects on file, including joint ventures this contractor is part of.
Total projects
99
Total budget
₱5B
Average progress
93.7%
Completion rate
77.8%
Average risk score
39.3
Medium risk on average, out of 100
Flagged as unusual
13
13.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 98 | ₱4.8B | 38.9 | 12 | 94.1% |
| Central Office | 1 | ₱215M | 83.0 | 1 | 59.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 48 | ₱2.4B | 31.6 | 0 | 98.1% |
| Flood Control and Drainage | 18 | ₱1B | 34.9 | 0 | 100.0% |
| OTHER | 11 | ₱913.9M | 79.3 | 8 | 81.1% |
| Buildings and Facilities | 8 | ₱57.4M | 20.2 | 0 | 100.0% |
| Bridges | 6 | ₱335M | 31.3 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱19.3M | 24.5 | 0 | 100.0% |
| GAA 2025 OO-1 | 2 | ₱69.6M | 91.8 | 2 | 11.1% |
| GAA 2025 OO-2 | 2 | ₱163M | 87.9 | 2 | 66.3% |
| GAA 2025 SSP | 1 | ₱4.7M | 89.8 | 1 | 24.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MI0034CONSTRUCTION OF LUMAYONG FLOOD CONTROL PROJECT (DOWNSTREAM OF CARMEN BRIDGE, KAYAGA TO SITIO PUNOL, PHASE V) ALONG PULANGI RIVER, KABACAN COTABATO | Region XII | Cotabato 3rd DEO | On-Going | ₱136.3M | 77% | High risk92 | Flagged0.007 |
| 25M00117WIDENING OF BRIDGE - LANGKONG BR. (B02133MN) ALONG MAHARLIKA HIGHWAY( COTABATO-LANAO RD), K1901+481-K1901+513, MATANOG, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱34.8M | 8% | High risk92 | Flagged0.029 |
| 25M00113WIDENING OF BRIDGE - BUGASAN BR. (B02131MN) ALONG MAHARLIKA HIGHWAY( COTABATO-LANAO RD), K1887+986.000-K1888+046.000, MATANOG, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱34.8M | 14% | High risk92 | Flagged0.028 |
| 25MI0096COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. TINIMBACAN, BANISILAN, COTABATO | Region XII | Cotabato 3rd DEO | On-Going | ₱4.7M | 25% | High risk90 | Flagged0.035 |
| 24M00319CONSTRUCTION OF ROAD, STA 0+000 - STA 1+200, BARANGAY SOLON, SULTAN MASTURA, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱18.7M | 23% | High risk87 | Flagged0.065 |
| 25MC0021CONSTRUCTION OF FLOOD CONTROL DIKE ALONG BULATUKAN RIVER PACKAGE 6, BARANGAY NEW BULATUKAN, MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱26.6M | 55% | High risk84 | Flagged0.001 |
| 21Z00018CONTRACT PACKAGE 4A - CONSTRUCTION OF ROROGAGUS BRIDGE, RECONSTRUCTION AND DEVELOPMENT PLAN FOR A GREATER MARAWI - STAGE 2 UNDER ADB LOAN NO. 3769 - PHI: EMERGENCY ASSISTANCE FOR RECONSTRUCTION AND RECOVERY OF MARAWI (EARRM) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱215M | 60% | High risk83 | Flagged0.013 |
| 24M00006WIDENING OF BRIDGE - LUMAYONG PARALLEL BR. ALONG BUKIDNON-COTABATO RD (PHASE II), K1652+371 - K1652+555.7, KABACAN, NORTH COTABATO | Region XII | Region XII | On-Going | ₱137M | 100% | High risk81 | Flagged0.010 |
| 23M00004CONSTRUCTION OF FLOOD CONTROL STRUCTURE, RIO GRANDE DE MINDANAO (LIBUNGAN TORETA SECTION) LIBUNGAN TORETA, STA. 0+000 STA. 0+238, PIGCAWAYAN, COTABATO | Region XII | Region XII | On-Going | ₱106.2M | 100% | High risk81 | Flagged0.018 |
| 24M00235CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG RIO GRANDE DE MINDANAO, PHASE I, BARANGAY SALIMBAO, STA. 0+000 - STA. 0+350, SULTAN KUDARAT, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱66.5M | 100% | High risk79 | —-0.000 |
| 24M00234CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG RIO GRANDE DE MINDANAO, BARANGAY SALIMBAO (PHASE II), STA. 0+000 - STA. 0+340, SULTAN KUDARAT, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱66.5M | 100% | High risk79 | —-0.000 |
| 23M00030CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - SAYRE ROAD-SITIO TAWAGON-KILAMBAY, BRGY. KIBUDTUNGAN CONNECTING TO SALAMA, BANISILAN ROAD IN SUPPORT OF COCONUT PROCESSING INDUSTRY (TREE LIFE ORGANIC COCO SUGAR | Region XII | Region XII | On-Going | ₱101.3M | 73% | High risk79 | Flagged0.025 |
| 24MC0011CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1666 + 620 - K1666 + 766, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱72.4M | 96% | High risk79 | Flagged0.005 |
| 24M00060WIDENING OF BRIDGE - PIGCALAGAN BR. BR. (B02135MN) ALONG DAVAO-COTABATO ROAD (JCT. DIGOS-COTABATO SECT), K1719 + 008.5 - K1719 + 026.5, SULTAN KUDARAT, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱18.4M | 41% | High risk76 | Flagged0.013 |
| 23M00235REHABILITATION OF PANATAN BRIDGE ALONG DAVAO-COTABATO ROAD, K1717+(-809) - K1717+(-797), SULTAN KUDARAT, MAGUINDANAO-PHASE II | Region XII | Region XII | Completed | ₱19.3M | 100% | High risk74 | —-0.035 |
| 23M00169ROAD WIDENING - COTABATO-LANAO ROAD, K1901+290 - K1903+280, MATANOG, MAGUINDANAO | Region XII | Region XII | On-Going | ₱92.6M | 100% | High risk74 | Flagged0.013 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24M00319CONSTRUCTION OF ROAD, STA 0+000 - STA 1+200, BARANGAY SOLON, SULTAN MASTURA, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱18.7M | 23% | High risk87 | Flagged0.065 |
| 25MI0096COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. TINIMBACAN, BANISILAN, COTABATO | Region XII | Cotabato 3rd DEO | On-Going | ₱4.7M | 25% | High risk90 | Flagged0.035 |
| 25M00117WIDENING OF BRIDGE - LANGKONG BR. (B02133MN) ALONG MAHARLIKA HIGHWAY( COTABATO-LANAO RD), K1901+481-K1901+513, MATANOG, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱34.8M | 8% | High risk92 | Flagged0.029 |
| 25M00113WIDENING OF BRIDGE - BUGASAN BR. (B02131MN) ALONG MAHARLIKA HIGHWAY( COTABATO-LANAO RD), K1887+986.000-K1888+046.000, MATANOG, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱34.8M | 14% | High risk92 | Flagged0.028 |
| 23M00030CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - SAYRE ROAD-SITIO TAWAGON-KILAMBAY, BRGY. KIBUDTUNGAN CONNECTING TO SALAMA, BANISILAN ROAD IN SUPPORT OF COCONUT PROCESSING INDUSTRY (TREE LIFE ORGANIC COCO SUGAR | Region XII | Region XII | On-Going | ₱101.3M | 73% | High risk79 | Flagged0.025 |
| 23M00004CONSTRUCTION OF FLOOD CONTROL STRUCTURE, RIO GRANDE DE MINDANAO (LIBUNGAN TORETA SECTION) LIBUNGAN TORETA, STA. 0+000 STA. 0+238, PIGCAWAYAN, COTABATO | Region XII | Region XII | On-Going | ₱106.2M | 100% | High risk81 | Flagged0.018 |
| 23M00169ROAD WIDENING - COTABATO-LANAO ROAD, K1901+290 - K1903+280, MATANOG, MAGUINDANAO | Region XII | Region XII | On-Going | ₱92.6M | 100% | High risk74 | Flagged0.013 |
| 24M00060WIDENING OF BRIDGE - PIGCALAGAN BR. BR. (B02135MN) ALONG DAVAO-COTABATO ROAD (JCT. DIGOS-COTABATO SECT), K1719 + 008.5 - K1719 + 026.5, SULTAN KUDARAT, MAGUINDANAO DEL NORTE | Region XII | Region XII | On-Going | ₱18.4M | 41% | High risk76 | Flagged0.013 |
| 21Z00018CONTRACT PACKAGE 4A - CONSTRUCTION OF ROROGAGUS BRIDGE, RECONSTRUCTION AND DEVELOPMENT PLAN FOR A GREATER MARAWI - STAGE 2 UNDER ADB LOAN NO. 3769 - PHI: EMERGENCY ASSISTANCE FOR RECONSTRUCTION AND RECOVERY OF MARAWI (EARRM) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱215M | 60% | High risk83 | Flagged0.013 |
| 24M00006WIDENING OF BRIDGE - LUMAYONG PARALLEL BR. ALONG BUKIDNON-COTABATO RD (PHASE II), K1652+371 - K1652+555.7, KABACAN, NORTH COTABATO | Region XII | Region XII | On-Going | ₱137M | 100% | High risk81 | Flagged0.010 |
| 25MI0034CONSTRUCTION OF LUMAYONG FLOOD CONTROL PROJECT (DOWNSTREAM OF CARMEN BRIDGE, KAYAGA TO SITIO PUNOL, PHASE V) ALONG PULANGI RIVER, KABACAN COTABATO | Region XII | Cotabato 3rd DEO | On-Going | ₱136.3M | 77% | High risk92 | Flagged0.007 |
| 24MC0011CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1666 + 620 - K1666 + 766, ARAKAN, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱72.4M | 96% | High risk79 | Flagged0.005 |
| 25MC0021CONSTRUCTION OF FLOOD CONTROL DIKE ALONG BULATUKAN RIVER PACKAGE 6, BARANGAY NEW BULATUKAN, MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱26.6M | 55% | High risk84 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22M00087CONSTRUCTION OF BRIDGE AT RARADANGAN TO MACABASA, ALAMADA, NORTH COTABATO | Region XII | Region XII | Completed | ₱77.2M | 100% | Medium risk31 | —-0.044 |
| 52 | 22M00038CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LADIA, SULTAN KUDARAT, MAGUINDANAO. | Region XII | Region XII | Completed | ₱4.9M | 100% | Medium risk31 | —-0.089 |
| 53 | 23M00015ROAD WIDENING - PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD, K1656+987 - K1658+680, ANTIPAS, NORTH COTABATO | Region XII | Region XII | Completed | ₱57.9M | 100% | Medium risk31 | —-0.086 |
| 54 | 17MD0087CONCRETING OF BULUCAON-PAG-ASA FMR, BRGY. BULUCAON, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱6.2M | 100% | Low risk30 | —-0.004 |
| 55 | 22M00114CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY CROSSING SIMUAY, SULTAN KUDARAT, MAGUINDANAO | Region XII | Region XII | Completed | ₱19.7M | 100% | Low risk29 | —-0.084 |
| 56 | 20MA0024WIDENING OF COTABATO - LANAO ROAD WITH EXCEPTION (KM 1854+902-KM1905+988.40), SULTAN KUDARAT, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱48.9M | 100% | Low risk29 | —-0.089 |
| 57 | 20MA0021CONCRETING OF COTABATO - LANAO ROAD (SULTAN MASTURA & PARANG SECTION, KM 1869+850-KM1875+000), PARANG, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱48.9M | 100% | Low risk29 | —-0.089 |
| 58 | 23MD0023ROAD WIDENING - BANISILAN-GUILING-ALAMADA-LIBUNGAN RD, GUILING, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱49M | 100% | Low risk28 | —-0.090 |
| 59 | 22MI0092ROAD WIDENING ALONG MATALAM-MLANG-BAGONTAPAY JCT RD - K1648+700 - K1650+553 | Region XII | Cotabato 3rd DEO | Completed | ₱48.4M | 100% | Low risk28 | —-0.087 |
| 60 | 22MD0075CONSTRUCTION OF CONCRETE ROAD, BRGY. ULAMIAN - BODEGA DEL PARAISO RESORT - SITIO TINAGO LEADING TO TINAGO FALLS, BRGY. ULAMIAN, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱48.2M | 100% | Low risk28 | —-0.089 |
| 61 | 20MA0118CONSTRUCTION OF PIGCALANGAN-TODOK PALAO ROAD, BRGY. PIGCALANGAN, SULTAN KUDARAT, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱48.2M | 100% | Low risk28 | —-0.089 |
| 62 | 20MA0025WIDENING OF DAVAO - COTABATO ROAD WITH EXCEPTION (KM 1716+050-KM1724+803.20), SULTAN KUDARAT, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱48.9M | 100% | Low risk28 | —-0.089 |
| 63 | 25MI0021CONSTRUCTION OF ROAD, BARANGAY PINAMULAAN, BANISILAN, NORTH COTABATO | Region XII | Cotabato 3rd DEO | On-Going | ₱9.8M | 75% | Low risk27 | —-0.048 |
| 64 | 22MD0057CONSTRUCTION OF REVETMENT - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, LIBUNGAN RIVER (NALIN SECTION - PHASE V), NALIN, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱48.9M | 100% | Low risk27 | —-0.076 |
| 65 | 20MA0051CONSTRUCTION OF SIMUAY FLOOD CONTROL (RIVER BANK PROTECTION WITH REVETMENT) STA. 0+00-STA.0+940, STA. 1+440-STA. 2+460, MACAGUILING, SULTAN KUDARAT, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱48.9M | 100% | Low risk27 | —-0.077 |
| 66 | 20MH0019CONSTRUCTION OF FLOOD CONTROL (ALA RIVER), ESPERANZA, SULTAN KUDARAT ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱47.5M | 100% | Low risk27 | —-0.074 |
| 67 | 22M00110REHABILITATION OF ROAD FROM SITIO PAYONG 2, BRGY. MACABISO TO SITIO MARGUES, STA. 0+000-STA. 0+521.5 BRGY. TAPAYAN, SULTAN MASTURA, MAGUINDANAO | Region XII | Region XII | Completed | ₱9.8M | 100% | Low risk27 | —-0.091 |
| 68 | 18MD0020CONST./IMPVT. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONE ALONG ALEOSAN BRGY. ROAD FROM KATALICANAN-CAWILIHAN CONNECTING TO LAWILI IN SUPPORT OF RUBBER, PALM OIL & COCONUT INDUSTRIES, ALEOSAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱37.3M | 100% | Low risk27 | —-0.090 |
| 69 | 24MD0047REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -SECONDARY ROAD - ALONG BANISILAN-GUILING-ALAMADA-LIBUNGAN ROAD, ALAMADA, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱34M | 100% | Low risk26 | —-0.089 |
| 70 | 23MI0103REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM CANOPY) IN BARANGAY GASTAV, BANISILAN, COTABATO | Region XII | Cotabato 3rd DEO | Completed | ₱4.9M | 100% | Low risk26 | —-0.087 |
| 71 | 21M00091CONSTRUCTION OF NARRA-KATIDTUAN ROAD IN BARANGAY NARRA, STA. 0+250.00 STA. 0+500.00, SULTAN KUDARAT, MAGUINDANAO | Region XII | Region XII | Completed | ₱9.8M | 100% | Low risk26 | —-0.091 |
| 72 | 20MA0026WIDENING OF LAMSAN-SIMUAY JUNCTION ROAD (KM 1862+9760-KM1863+736), SULTAN KUDARAT, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱25.1M | 100% | Low risk26 | —-0.091 |
| 73 | 18MD0037REHABILITATION OF PAVED ROAD-BANISILAN-GUILING-ALAMADA-LIBUNGAN ROAD, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱29.3M | 100% | Low risk26 | —-0.091 |
| 74 | 18MD0054CONST. OF DIKE - CONST. OF OLANDANG (HWAY JUNCTION)-KADIGASAN-DAMATULAN EARTH DIKE ALONG MINDANAO RIVER, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱21.4M | 100% | Low risk25 | —-0.077 |
| 75 | 21MD0061ROAD WIDENING ALONG MIDSAYAP-MAKAR ROAD, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱19.3M | 100% | Low risk25 | —-0.089 |