22 projects on file, including joint ventures this contractor is part of.
Total projects
22
Total budget
₱184.2M
Average progress
100.0%
Completion rate
95.5%
Average risk score
29.7
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 22 | ₱184.2M | 29.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 16 | ₱117.1M | 30.5 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱54.8M | 34.3 | 0 | 100.0% |
| Buildings and Facilities | 3 | ₱12.2M | 21.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EB0052CONSTRUCTION OF DRAINAGE SYSTEM, SAN JOSE NATIONAL HIGH SCHOOL COMPOUND, BARANGAY BAGONG SIKAT, SAN JOSE, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | On-Going | ₱10.7M | 100% | Medium risk40 | —-0.043 |
| 2 | 20EF0069CONSTRUCTION OF ROAD, BRGY TABUD TO NATIONAL HIGHWAY BRGY. TABUD, BATARAZA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk40 | —-0.061 |
| 3 | 22EB0030CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANAHAWIN RIVER, STA. 0+000 - STA. 0+315, BRGY. POBLACION, CALINTAAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱40M | 100% | Medium risk39 | —-0.072 |
| 4 | 20EG0059CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO TIGMAN BEACH, STATION 00+000 - 00+817, BRGY. TIGMAN, ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱19.4M | 100% | Medium risk39 | —-0.069 |
| 5 | 22EG0011ROAD CONSTRUCTION AT F-RAFOLS ROAD, STATION 00+348 - 00+505, BARANGAY STA. MONICA, CITY OF PUERTO PRINCESA,PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱9.9M | 100% | Medium risk38 | —-0.073 |
| 6 | 19EB0016CLUSTER 2019RD-01: REHABILITATION/RECONSTRUCTION TO ASHPALT/CONCRETE PAVEMENT ALONG VARIOUS ROAD SECTIONS: A) MINDORO ORIENTAL/OCCIDENTAL EAST COASTAL RD (S00094MR) K0223+900 - K0223+950, B) MWCR (LABANGAN)-MURTHA-JCT IRIRON RD (S00142MR) K0250+832 - K025 | Region IV-B | Mindoro Occidental DEO | Completed | ₱10.4M | 100% | Medium risk38 | —-0.092 |
| 7 | 20EB0008RECONSTRUCTION TO CONCRETE PAVEMENT ALONG JCT MWCR (LABANGAN0-MURTHA-JCT IRIRON RD - K0241+718 - K0242+167, K0247+865 - K0248+000, K0279+405 - K0279+487 | Region IV-B | Mindoro Occidental DEO | Completed | ₱19.1M | 100% | Medium risk38 | —-0.091 |
| 8 | 22EB0068CONSTRUCTION OF EVACUATION CENTER, CALINTAAN NATIONAL HIGH SCHOOL, RED HILL, BARANGAY NEW DAGUPAN, CALINTAAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱6.9M | 100% | Medium risk36 | —-0.083 |
| 9 | 18EB0196CONCRETING OF BRGY. PAETAN FMR PHASE II, BRGY. PAETAN, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk33 | —-0.033 |
| 10 | 19EB0146CONCRETING OF BRGY. MAPAYA FMR, SAN JOSE, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk33 | —-0.036 |
| 11 | 20EB0148CONCRETING OF BRGY. SAN NICOLAS TO BRGY. MALISBONG FMR, BRGY. SAN NICOLAS AND BRGY. MALISBONG, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱9.7M | 100% | Medium risk33 | —-0.036 |
| 12 | 18EB0157CONCRETING OF SITIO LAGNAS-VICTORIA FMR, BRGY. PAG-ASA, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.034 |
| 13 | 21EB0161CONCRETING OF SITIO BANGBANG TO TANYAG PROPER FMR, BRGY. TANYAG, CALINTAAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱11.8M | 100% | Medium risk32 | —-0.037 |
| 14 | 17EB0008CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO MATABANG PORT, ABRA DE ILOG, MINDORO OCCIDENTAL LONE DISTRICT | Region IV-B | Mindoro Occidental DEO | Completed | ₱3.7M | 100% | Low risk29 | —-0.045 |
| 15 | 22EG0042DRAINAGE CONSTRUCTION AT BARANGAY KALIPAY, FIRST STATION: STA. 0+000 - STA. 0+213, SECOND STATION: STA. 0+000 - STA. 0+114, CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.2M | 100% | Low risk24 | —-0.054 |
| 16 | 19EG0035ROAD CONCRETING OF PUROK BAGONG SIKAT FEEDER ROAD, STA. 0+000 - 0+213, BRGY. MACARASCAS, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱3.1M | 100% | Low risk22 | —-0.068 |
| 17 | 19EG0068ROAD CONCRETING OF VILLON ROAD, STA. 00+000 - 00+315, BARANGAY SAN MANUEL, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱3.9M | 100% | Low risk22 | —-0.068 |
| 18 | 20EG0028ROAD CONCRETING LEADING TO BARANGAY CENTER, BARANGAY BAGONG BAYAN, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱3M | 100% | Low risk22 | —-0.064 |
| 19 | 20EG0010CONCRETING OF HEREDERO ROAD WITH DRAINAGE, STA. 00+160 - STA. 000+301.09, BARANGAY SAN PEDRO, CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱2M | 100% | Low risk20 | —-0.066 |
| 20 | 19EG0066ROAD CONCRETING OF SITIO ESCALONA, PUROK MAGSASAKA, STA, 00+000.00 - STA. 00+97.00, BRGY. INAGAWAN, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.063 |
| 21 | 22EG0054CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY JOSE RIZAL, MUNICIPALITY OF ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.3M | 100% | Low risk17 | —-0.057 |
| 22 | 20EG0002IMPROVEMENT OF MULTI-PURPOSE BUILDING AT BARANGAY MAUNLAD, CITY OF PUERTO PRINCESA | Region IV-B | Palawan 3rd DEO | Completed | ₱979.9K | 100% | Low risk9 | —-0.065 |