Contractor dossier
37 projects on file, including joint ventures this contractor is part of.
Total projects
37
Total budget
₱1.4B
Average progress
97.9%
Completion rate
83.8%
Average risk score
48.0
Medium risk on average, out of 100
Flagged as unusual
1
2.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 35 | ₱1.3B | 46.9 | 0 | 98.4% |
| Region XIII | 2 | ₱120M | 65.9 | 1 | 88.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 24 | ₱863.1M | 47.6 | 0 | 97.8% |
| Buildings and Facilities | 7 | ₱112.1M | 39.6 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱95.5M | 43.4 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱82.4M | 94.3 | 1 | 77.2% |
| OTHER | 1 | ₱96.5M | 62.1 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱84.7M | 58.3 | 0 | 100.0% |
| Bridges | 1 | ₱86.8M | 54.7 | 0 | 96.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NB0034BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA JOSEFA RD - K1309+118 - K1309+172, K1309+287.50 - K1309+347.90, K1309+581.30 - K1309+593.40, K1311+687.80 - K1311+739.20, K1311+748 - K1311+932.70, K1312+072.30 - K1312+100.70, SAN LUIS, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱82.4M | 77% | High risk94 | Flagged0.011 |
| 18L00021WIDENING (2 INTO 4 LANES) OF MONTEVISTA-COMPOSTELA-MATI BDRY. RD (BRGY. MARAPAT-BRGY. LAGAB SECT.) I | Region XI | Region XI | Completed | ₱132.5M | 100% | High risk62 | —-0.062 |
| 20LA0130CONSTRUCTION OF REVETMENT ALONG AGUSAN RIVER, BRGY. NEW PANAY, MARAGUSAN COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.031 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NB0034BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA JOSEFA RD - K1309+118 - K1309+172, K1309+287.50 - K1309+347.90, K1309+581.30 - K1309+593.40, K1311+687.80 - K1311+739.20, K1311+748 - K1311+932.70, K1312+072.30 - K1312+100.70, SAN LUIS, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱82.4M | 77% | High risk94 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25NB0034BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA JOSEFA RD - K1309+118 - K1309+172, K1309+287.50 - K1309+347.90, K1309+581.30 - K1309+593.40, K1311+687.80 - K1311+739.20, K1311+748 - K1311+932.70, K1312+072.30 - K1312+100.70, SAN LUIS, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱82.4M | 77% | High risk94 | Flagged0.011 |
| 2 | 18L00021WIDENING (2 INTO 4 LANES) OF MONTEVISTA-COMPOSTELA-MATI BDRY. RD (BRGY. MARAPAT-BRGY. LAGAB SECT.) I | Region XI | Region XI | Completed | ₱132.5M | 100% | High risk62 | —-0.062 |
| 3 | 20LA0130CONSTRUCTION OF REVETMENT ALONG AGUSAN RIVER, BRGY. NEW PANAY, MARAGUSAN COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.031 |
| 4 | 21L00001CONSTRUCTION OF CONCRETE ROAD - MONKAYO - BOSTON (MONKAYO SECTION) PACKAGE F, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱98.5M | 99% | Medium risk60 | —-0.008 |
| 5 | 21L00016CONSTRUCTION OF CONCRETE ROAD - NABUNTURAN - NEW CORELLA - TAGUM ROAD (NABUNTURAN SECTION), DAVAO DE ORO | Region XI | Region XI | On-Going | ₱84.7M | 100% | Medium risk58 | —-0.001 |
| 6 | 21L00084CONSTRUCTION OF CONCRETE ROAD - PANABO CITY BYPASS ROAD, DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱80.7M | 100% | Medium risk56 | —-0.077 |
| 7 | 24LI0106REPLACEMENT OF MAYAON BRIDGE ALONG MONTEVISTA (JCT. MAYAON) - LAAK DIVERSION ROAD, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱86.8M | 96% | Medium risk55 | —-0.012 |
| 8 | 20LA0140ROAD WIDENING - ALONG MONTEVISTA - COMPOSTELA - MATI BDRY. (S00133MN) COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱77.1M | 100% | Medium risk54 | —-0.073 |
| 9 | 21LA0126ROAD WIDENING - ALONG MONTEVISTA - COMPOSTELA - MATI BDRY. RD (S00135MN), MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱47.7M | 100% | Medium risk52 | —-0.079 |
| 10 | 23LI0026CONSTRUCTION OF REVETMENT ALONG MANAT RIVER (UPSTREAM AND DOWNSTREAM) LEADING TO AGUSAN RIVER AT PRK1C, 1B, 1A, 7, 8 AND MANAT BRIDGE POBLACION, MONTEVISTA, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | Completed | ₱57.9M | 100% | Medium risk49 | —-0.068 |
| 11 | 20LA0308CONSTRUCTION OF MPB (3 STOREY) KOLEHIYO AND PANTUKAN (KNP) 12 CLASSROOMS, PANTUKAN COMPOSTELA VALLEY | Region XI | Davao de Oro 1st DEO | Completed | ₱33.8M | 100% | Medium risk47 | —-0.081 |
| 12 | 22LA0072ROAD WIDENING - ALONG ASUNCION - SAN ISIDRO - LAAK - VERUELA ROAD (S01377MN) LAAK, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱45M | 100% | Medium risk47 | —-0.085 |
| 13 | 22LA0055ROAD WIDENING - ALONG ASUNCION - SAN ISIDRO - LAAK - VERUELA ROAD (S01377MN) LAAK, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱46M | 100% | Medium risk47 | —-0.086 |
| 14 | 22L00053CONSTRUCTION OF CONCRETE ROAD - NABUNTURAN - NEW CORELLA - TAGUM ROAD (NABUNTURAN SECTION), DAVAO DE ORO | Region XI | Region XI | On-Going | ₱36.2M | 66% | Medium risk46 | —-0.015 |
| 15 | 22LA0070CONSTRUCTION OF ROAD, PROSPERIDAD, MONTEVISTA TO CASOON, MONKAYO, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱34.3M | 100% | Medium risk46 | —-0.084 |
| 16 | 21LA0138ROAD WIDENING ALONG ASUNCION - SAN ISIDRO - LAAK - VERUELA RD (S01377MN), DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱31.3M | 100% | Medium risk46 | —-0.086 |
| 17 | 21LA0140ROAD WIDENING - ALONG ASUNCION - SAN ISIDRO - LAAK - VERUELA RD (S01377MN), DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱31.3M | 100% | Medium risk46 | —-0.087 |
| 18 | 22LA0107CONSTRUCTION OF ROAD, IMELDA-MANGLOY, BINASBAS ROAD, LAAK, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱29.4M | 100% | Medium risk46 | —-0.088 |
| 19 | 19LB0078RECONSTRUCTION TO CONCRETE PAVEMENT: JCT. DEL PILAR EXTENSION-JCT. UBALDE ROAD LEADING TO SMX CONVENTION CENTER, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱14.4M | 100% | Medium risk46 | —-0.092 |
| 20 | 21LA0143CONSTRUCTION OF CONCRETE ROAD, FUENTES, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.085 |
| 21 | 24L00068CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - DAANG MAHARLIKA (MN) - K1450+618 - K1451+018.100, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱19.2M | 83% | Medium risk46 | —-0.043 |
| 22 | 19LB0082CONSTRUCTION OF CONCRETE ROAD: SITIO BINATON-SITIO POLOKON-JCT KTC ROAD LEADING TO MEGKAWAYAN PEAK RESORT AND REMY AREJA'S RESORT, BRGY. MALABOG, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.093 |
| 23 | 21LA0171CONCRETING OF ROAD, CANIDKID - NEW CALAPE, PHASE 2, MONTEVISTA, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱23.5M | 100% | Medium risk46 | —-0.085 |
| 24 | 19LA0478CONCRETING OF ROAD BRGY. LANGTUD, LAAK, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.087 |
| 25 | 22LA0136CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, KNP, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | Completed | ₱14.7M | 100% | Medium risk46 | —-0.086 |