Contractor dossier
60 projects on file, including joint ventures this contractor is part of.
Total projects
60
Total budget
₱995.4M
Average progress
98.8%
Completion rate
95.0%
Average risk score
29.8
Low risk on average, out of 100
Flagged as unusual
1
1.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 60 | ₱995.4M | 29.8 | 1 | 98.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 34 | ₱504.1M | 26.2 | 0 | 99.7% |
| Buildings and Facilities | 13 | ₱160.6M | 22.9 | 0 | 100.0% |
| Flood Control and Drainage | 9 | ₱217.4M | 32.2 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱60.7M | 91.9 | 1 | 69.4% |
| OTHER | 2 | ₱52.6M | 63.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CG0225SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF MAIN ROAD (LAPUT - CONCEPCION ROAD INCLUDING DRAINAGE SYSTEM), ME | Region III | Pampanga 1st DEO | On-Going | ₱46.8M | 39% | High risk93 | Flagged0.015 |
| 25CG0182SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF GATIAWIN-LACMIT ROAD, ARAYAT, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱13.9M | 100% | High risk91 | —-0.035 |
| 17CG0093ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPEMENT MANAGEMENT-4 (HDM-4) PRIMARY AT MANILA NORTH ROAD K0064+547-K0064+878, | Region III | Pampanga 1st DEO | Completed | ₱17.4M | 100% | High risk69 | —-0.068 |
| 17CG0048REHABILITATION/IMPROVEMENT AND SLOPE PROTECTION OF PALIGUI-SAN AGUSTIN-LOURDES RIVER, SAN SIMON, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱22.7M | 100% | High risk65 | —-0.009 |
| 18CG0375NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING (TERTIARY ROADS) CANDABA - SAN MIGUEL ROAD K0073+408 - K0073+674; K0074+000 TO K0075+753, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱43.5M | 100% | High risk64 | —-0.041 |
| 18CG0036REHABILITATION/UPGRADING OF EMERGENCY ROAD, VILLA BAROSA PHASE 3 DOLORES, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱9.1M | 100% | High risk62 | —-0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CG0225SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF MAIN ROAD (LAPUT - CONCEPCION ROAD INCLUDING DRAINAGE SYSTEM), ME | Region III | Pampanga 1st DEO | On-Going | ₱46.8M | 39% | High risk93 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 20CG0011CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAPLAD DAVID, MACABEBE, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.3M | 100% | Low risk12 | —-0.108 |
| 52 | 20CG0125ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS - SN FERNANDO - LUBAO RD - K0068+556 - K0068+653, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.1M | 100% | Low risk11 | —-0.098 |
| 53 | 20CG0042CONSTRUCTION OF MULTI-PURPOSE BUILDING, CANDELARIA, MACABEBE, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.102 |
| 54 | 18CG0124ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE-BALIWAG-CANDABA-STA. ANA ROAD-K0063+870-K0064+050, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.4M | 100% | Low risk11 | —-0.099 |
| 55 | 20CG0034CONSTRUCTION OF MULTI-PURPOSE BUILDING STA. LUTGARDA, MACABEBE, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.107 |
| 56 | 22CG0092BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN LORENZO, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.102 |
| 57 | 20CG0012REHABILITATION/ CONCRETING OF ROAD, TAGULOD, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.100 |
| 58 | 20CG0010REHABILITATION/ CONCRETING OF ROAD, SALAPUNGAN, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.100 |
| 59 | 20CG0014REHABILITATION/ CONCRETING OF ROAD, LOURDES, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.100 |
| 60 | 18CG0011REHABILITATION/IMPROVEMENT OF ANAO ROAD, MEXICO, PAMPANGA, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.8M | 100% | Low risk10 | —-0.100 |