Contractor dossier
345 projects on file, including joint ventures this contractor is part of.
Total projects
345
Total budget
₱31.6B
Average progress
87.7%
Completion rate
68.7%
Below 70%
Average risk score
60.8
High risk on average, out of 100
Flagged as unusual
50
14.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 120 | ₱9B | 56.6 | 8 | 86.4% |
| Region IV-A | 86 | ₱6.7B | 58.5 | 4 | 93.6% |
| Region V | 45 | ₱4.4B | 69.5 | 8 | 89.6% |
| Region III | 43 | ₱4.5B | 61.4 | 14 | 89.4% |
| Region VII | 26 | ₱2.8B | 69.0 | 10 | 75.5% |
| Region IV-B | 12 | ₱2.5B | 64.1 | 1 | 90.8% |
| Region VI | 9 | ₱1.1B | 61.3 | 3 | 80.0% |
| Central Office | 3 | ₱659.8M | 76.6 | 2 | 33.3% |
| Cordillera Administrative Region | 1 | ₱48.3M | 47.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 133 | ₱11.6B | 58.3 | 5 | 91.5% |
| Flood Control and Drainage | 124 | ₱12.5B | 62.1 | 26 | 87.0% |
| Buildings and Facilities | 54 | ₱4B | 56.4 | 3 | 84.7% |
| OTHER | 16 | ₱1.7B | 73.4 | 9 | 86.7% |
| Bridges | 7 | ₱357.7M | 53.0 | 0 | 100.0% |
| GAA 2025 SSP | 5 | ₱691.2M | 95.6 | 5 | 35.2% |
| Bridges, Roads | 3 | ₱512.4M | 61.5 | 1 | 90.2% |
| GAA 2025 OO-2 | 2 | ₱187.1M | 90.9 | 0 | 79.2% |
| GAA 2025 OO-1 | 1 | ₱94.6M | 94.1 | 1 | 37.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FD0097CONSTRUCTION OF SITIO CENTRO WEST COASTAL ROAD, BARANGAY ANIB, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱141.1M | 0% | High risk96 | Flagged0.039 |
| 25F00389CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES-CONSTRUCTION OF SITIO COBCOBAN, BARANGAY CALAMPINAY COASTAL ROAD, SIPOCOT, CAMARINES SUR, | Region V | Region V | On-Going | ₱215M | 2% | High risk96 | Flagged0.050 |
| 25FD0095CONSTRUCTION OF SITIO CALONGGO COASTAL ROAD, BARANGAY SAN VICENTE, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱140.1M | 0% | High risk96 | Flagged0.039 |
| 25CJ0215IMPROVEMENT OF SEPUNG CALZADA - BACULONG DIVERSION ROAD (SEGMENT A), TARLAC | Region III | Tarlac DEO | On-Going | ₱99M | 88% | High risk95 | Flagged0.011 |
| 25OA0023CONSTRUCTION OF DAMPALIT PUMPING STATION, (PHASE 5), BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱96M | 85% | High risk94 | Flagged0.015 |
| 25OG0125PREVENTIVE MAINTENANCE - SECONDARY ROADS: QUEZON AVE - K0009 + 094 - K0009 + 340, K0010 + 000 - K0010 + 604, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱94.6M | 38% | High risk94 | Flagged0.003 |
| 24F00482CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAGSANGAHAN, BA | Region V | Region V | On-Going | ₱234M | 89% | High risk92 | Flagged0.065 |
| 23HO0299CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD DIKE AT SITIO POBLACION | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 100% | High risk91 | Flagged0.059 |
| 25OA0021CONSTRUCTION OF DAMPALIT PUMPING STATION, PHASE 3, BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱93.6M | 75% | High risk91 | —-0.010 |
| 25OA0022CONSTRUCTION OF DAMPALIT PUMPING STATION, PHASE 4, BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱93.6M | 83% | High risk91 | —-0.011 |
| 24CJ0403INSTALLATION OF SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD TO TARLAC CITY - SN JOSE VIA TIBAG-BURGOS RD (SAN JOSE SECTION), TARLAC | Region III | Tarlac DEO | On-Going | ₱103M | 99% | High risk88 | Flagged0.048 |
| 23HO0309CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.075 |
| 23HO0298CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.075 |
| 24HO0164CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO AB | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 24HO0166CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 24HO0167CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO P | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 17F00018MFO1-CONSTRUCTION OF BY-PASSES/DIVERSION ROADS, INCLUDING ROW:DARAGA ALBAY DIVERSION ROAD, INCLUDING ROW, ROAD CONCRETING, SLOPE PROTECTION AND BRIDGE, ALBAY 2ND LD, DARAGA, ALBAY PROVINCE | Region V | Region V | Terminated | ₱142.5M | 100% | High risk82 | Flagged0.024 |
| 24F00447ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0384+1215-K0385+012, K0386+239-K0387+000, K0389+737-K0389+876, K0391+000-K0391+200, SIPOCOT, CAMARINES SU | Region V | Region V | On-Going | ₱122.1M | 47% | High risk82 | Flagged0.018 |
| 24CD0302CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER AND ITS TRIBUTARIES STA. 09+728 STA. 10+128, (SAN JOSE PATAG PULONG BUHANGIN SECTION), STA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱115.8M | 28% | High risk82 | Flagged0.053 |
| 24CD0303CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER AND ITS TRIBUTARIES STA. 10+128 STA. 10+528, (SAN JOSE PATAG PULONG BUHANGIN SECTION), STA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱115.8M | 30% | High risk82 | Flagged0.051 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24HO0164CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO AB | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 24HO0166CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 24HO0167CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO P | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 23HO0309CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.075 |
| 23HO0298CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.075 |
| 24F00482CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAGSANGAHAN, BA | Region V | Region V | On-Going | ₱234M | 89% | High risk92 | Flagged0.065 |
| 23HO0299CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD DIKE AT SITIO POBLACION | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 100% | High risk91 | Flagged0.059 |
| 24CD0302CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER AND ITS TRIBUTARIES STA. 09+728 STA. 10+128, (SAN JOSE PATAG PULONG BUHANGIN SECTION), STA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱115.8M | 28% | High risk82 | Flagged0.053 |
| 24CD0303CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER AND ITS TRIBUTARIES STA. 10+128 STA. 10+528, (SAN JOSE PATAG PULONG BUHANGIN SECTION), STA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱115.8M | 30% | High risk82 | Flagged0.051 |
| 25F00389CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES-CONSTRUCTION OF SITIO COBCOBAN, BARANGAY CALAMPINAY COASTAL ROAD, SIPOCOT, CAMARINES SUR, | Region V | Region V | On-Going | ₱215M | 2% | High risk96 | Flagged0.050 |
| 24CJ0403INSTALLATION OF SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD TO TARLAC CITY - SN JOSE VIA TIBAG-BURGOS RD (SAN JOSE SECTION), TARLAC | Region III | Tarlac DEO | On-Going | ₱103M | 99% | High risk88 | Flagged0.048 |
| 24HO0165CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 90% | High risk75 | Flagged0.043 |
| 24HO0168CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 91% | High risk75 | Flagged0.043 |
| 25FD0095CONSTRUCTION OF SITIO CALONGGO COASTAL ROAD, BARANGAY SAN VICENTE, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱140.1M | 0% | High risk96 | Flagged0.039 |
| 25FD0097CONSTRUCTION OF SITIO CENTRO WEST COASTAL ROAD, BARANGAY ANIB, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱141.1M | 0% | High risk96 | Flagged0.039 |
| 24F00481CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY MANDAZO, BASUD, CAMAR | Region V | Region V | On-Going | ₱234M | 89% | High risk77 | Flagged0.036 |
| 24OG0137CONSTRUCTION OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG SAN JUAN RIVER, PACKAGE 8, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱141.8M | 42% | High risk74 | Flagged0.034 |
| 20O00038CONSTRUCTION OF SLOPE PROTECTION AND LINEAR PARKS ALONG TAGUIG RIVER, BRGY. WAWA, TAGUIG CITY | National Capital Region | National Capital Region | On-Going | ₱187.4M | 31% | High risk68 | Flagged0.033 |
| 23O00045CONSTRUCTION OF CAYETANO SPORTS COMPLEX, BRGY. BAGUMBAYAN, TAGUIG CITY (PHASE 2) | National Capital Region | National Capital Region | On-Going | ₱141.8M | 26% | High risk74 | Flagged0.032 |
| 24DF0297ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF FLOOD CONTROL STRUCTURE ALONG CANAS RIVER, BRGY PASONG KA | Region IV-A | Cavite 1st DEO | On-Going | ₱95.5M | 70% | High risk73 | Flagged0.026 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25FD0097CONSTRUCTION OF SITIO CENTRO WEST COASTAL ROAD, BARANGAY ANIB, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱141.1M | 0% | High risk96 | Flagged0.039 |
| 2 | 25F00389CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES-CONSTRUCTION OF SITIO COBCOBAN, BARANGAY CALAMPINAY COASTAL ROAD, SIPOCOT, CAMARINES SUR, | Region V | Region V | On-Going | ₱215M | 2% | High risk96 | Flagged0.050 |
| 3 | 25FD0095CONSTRUCTION OF SITIO CALONGGO COASTAL ROAD, BARANGAY SAN VICENTE, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱140.1M | 0% | High risk96 | Flagged0.039 |
| 4 | 25CJ0215IMPROVEMENT OF SEPUNG CALZADA - BACULONG DIVERSION ROAD (SEGMENT A), TARLAC | Region III | Tarlac DEO | On-Going | ₱99M | 88% | High risk95 | Flagged0.011 |
| 5 | 25OA0023CONSTRUCTION OF DAMPALIT PUMPING STATION, (PHASE 5), BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱96M | 85% | High risk94 | Flagged0.015 |
| 6 | 25OG0125PREVENTIVE MAINTENANCE - SECONDARY ROADS: QUEZON AVE - K0009 + 094 - K0009 + 340, K0010 + 000 - K0010 + 604, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱94.6M | 38% | High risk94 | Flagged0.003 |
| 7 | 24F00482CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAGSANGAHAN, BA | Region V | Region V | On-Going | ₱234M | 89% | High risk92 | Flagged0.065 |
| 8 | 23HO0299CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD DIKE AT SITIO POBLACION | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 100% | High risk91 | Flagged0.059 |
| 9 | 25OA0021CONSTRUCTION OF DAMPALIT PUMPING STATION, PHASE 3, BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱93.6M | 75% | High risk91 | —-0.010 |
| 10 | 25OA0022CONSTRUCTION OF DAMPALIT PUMPING STATION, PHASE 4, BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱93.6M | 83% | High risk91 | —-0.011 |
| 11 | 24CJ0403INSTALLATION OF SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD TO TARLAC CITY - SN JOSE VIA TIBAG-BURGOS RD (SAN JOSE SECTION), TARLAC | Region III | Tarlac DEO | On-Going | ₱103M | 99% | High risk88 | Flagged0.048 |
| 12 | 23HO0309CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.075 |
| 13 | 23HO0298CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.075 |
| 14 | 24HO0164CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO AB | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 15 | 24HO0166CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 16 | 24HO0167CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) AT SITIO P | Region VII | Cebu 7th DEO | On-Going | ₱142.6M | 0% | High risk86 | Flagged0.082 |
| 17 | 17F00018MFO1-CONSTRUCTION OF BY-PASSES/DIVERSION ROADS, INCLUDING ROW:DARAGA ALBAY DIVERSION ROAD, INCLUDING ROW, ROAD CONCRETING, SLOPE PROTECTION AND BRIDGE, ALBAY 2ND LD, DARAGA, ALBAY PROVINCE | Region V | Region V | Terminated | ₱142.5M | 100% | High risk82 | Flagged0.024 |
| 18 | 24F00447ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0384+1215-K0385+012, K0386+239-K0387+000, K0389+737-K0389+876, K0391+000-K0391+200, SIPOCOT, CAMARINES SU | Region V | Region V | On-Going | ₱122.1M | 47% | High risk82 | Flagged0.018 |
| 19 | 24CD0302CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER AND ITS TRIBUTARIES STA. 09+728 STA. 10+128, (SAN JOSE PATAG PULONG BUHANGIN SECTION), STA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱115.8M | 28% | High risk82 | Flagged0.053 |
| 20 | 24CD0303CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER AND ITS TRIBUTARIES STA. 10+128 STA. 10+528, (SAN JOSE PATAG PULONG BUHANGIN SECTION), STA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱115.8M | 30% | High risk82 | Flagged0.051 |
| 21 | 17F00021MFO1-NATIONAL ROAD NETWORK SERVICES-ASSET PRESERVATION OF NATIONAL ROADS, REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE:SECONDARY ROADS-LEGAZPI CITY-PUNTA DE JESUS ROAD, K0560+380-K0578+780 WITH EXCEPTIONS,MANITO, ALBAY 2ND LD | Region V | Region V | Completed | ₱104.4M | 100% | High risk81 | —-0.021 |
| 22 | 24C00300FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONST. OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER (RIGHT SIDE), MEYCAUAYAN CITY, PROVINCE OF BULACAN | Region III | Region III | On-Going | ₱170.2M | 79% | High risk80 | Flagged0.001 |
| 23 | 24C00299FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONST. OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER (RIGHT SIDE), MEYCAUAYAN CITY, PROVINCE OF BULACAN | Region III | Region III | On-Going | ₱170.2M | 81% | High risk80 | —-0.000 |
| 24 | 24CL0217CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTO TOMAS RIVER (MACULCOL DIKE), PHASE 5, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱93.1M | 100% | High risk80 | Flagged0.012 |
| 25 | 24CL0216CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTO TOMAS RIVER (MACULCOL DIKE), PHASE 4, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱93.1M | 100% | High risk80 | Flagged0.012 |