Contractor dossier
176 projects on file, including joint ventures this contractor is part of.
Total projects
176
Total budget
₱19.2B
Average progress
77.8%
Completion rate
44.3%
Below 70%
Average risk score
61.2
High risk on average, out of 100
Flagged as unusual
38
21.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 55 | ₱7.5B | 56.5 | 9 | 83.0% |
| Region VII | 28 | ₱2.7B | 73.9 | 12 | 86.2% |
| Region IV-A | 25 | ₱3.1B | 66.1 | 9 | 44.8% |
| Region III | 19 | ₱1.3B | 55.4 | 1 | 70.3% |
| Region XI | 11 | ₱1.1B | 68.6 | 2 | 45.5% |
| Region II | 11 | ₱1.2B | 55.6 | 0 | 100.0% |
| Cordillera Administrative Region | 8 | ₱721.5M | 58.8 | 0 | 97.8% |
| Region XII | 6 | ₱576.1M | 58.9 | 3 | 98.0% |
| Negros Island Region | 5 | ₱330.1M | 60.4 | 2 | 100.0% |
| Region XIII | 5 | ₱646.5M | 47.6 | 0 | 100.0% |
| Region VIII | 3 | ₱196.8M | 55.8 | 0 | 98.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 139 | ₱15.4B | 56.2 | 16 | 79.4% |
| GAA 2025 OO-1 | 14 | ₱1.4B | 92.7 | 11 | 90.7% |
| Flood Control and Drainage | 13 | ₱1.3B | 67.2 | 2 | 50.7% |
| OTHER | 6 | ₱683.9M | 77.5 | 6 | 94.8% |
| GAA 2025 SSP | 2 | ₱193M | 95.7 | 2 | 13.2% |
| Bridges, Roads | 2 | ₱249.4M | 68.3 | 1 | 72.5% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LJ0134CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE (EARTH DIKE) ALONG TAGUM LIBUGANON RIVER BASIN, CARMEN - B.E. JUALI, STO. TOMAS, DAVAO DEL NORTE, SECTION 5, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱96M | 6% | High risk96 | Flagged0.048 |
| 25LG0073CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PANGYAN UPPER SUMLOG RIVER, LUPON, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱97M | 21% | High risk95 | Flagged0.050 |
| 25HB0010ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - SECONDARY ROADS THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0200 + 000 - K0201 + 000, K0208 + 000 - K0209 + 235 | Region VII | Bohol 3rd DEO | On-Going | ₱122.8M | 89% | High risk94 | Flagged0.014 |
| 25HB0039OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PRORAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. (TER) JAGNA-SIERRA BULLONES RD - K0088+000 - K0089+382 | Region VII | Bohol 3rd DEO | Completed | ₱61.1M | 100% | High risk94 | —-0.027 |
| 25HB0023ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT. (LIR) BUENAVISTA - CARMEN - DANAO - JETAFE RD -K0159 + (-356) - K0159+720 | Region VII | Bohol 3rd DEO | On-Going | ₱49.9M | 98% | High risk94 | —-0.002 |
| 25HB0031ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - LOAY INTERIOR RD - K0160+214- K0160+730 , K0173+474 - K0174+225, K0197+509 - K0198+060 | Region VII | Bohol 3rd DEO | On-Going | ₱112.5M | 99% | High risk94 | Flagged0.007 |
| 25HB0030OO1: ENSURESAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - LOAY INTERIOR RD - K0154 + 000 - K0154 + 583, K0154 + 611 - K0155 + 293, K0156 + 329 - K0156 + 560 , | Region VII | Bohol 3rd DEO | On-Going | ₱132.1M | 98% | High risk94 | Flagged0.013 |
| 25HB0028ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT (TER)-JAGNA-SIERRA BULLONES RD - K0094 + 000 - K0096 + 792 | Region VII | Bohol 3rd DEO | On-Going | ₱83.8M | 45% | High risk94 | Flagged0.018 |
| 25HB0014ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE-SECONDARY ROADS - JCT (LIR) CARMEN - SAGBAYAN - BACANI RD -K0161+743- K0163+592, K0163+625 - K0163+944 | Region VII | Bohol 3rd DEO | On-Going | ₱110.1M | 97% | High risk94 | Flagged0.008 |
| 25HB0032ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0211+578 - K0213 + 767.97 | Region VII | Bohol 3rd DEO | On-Going | ₱101.1M | 99% | High risk94 | Flagged0.007 |
| 25HB0008OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD, K0177+398 - K0178+477, K0184+296 - K0185+157 | Region VII | Bohol 3rd DEO | On-Going | ₱126.2M | 74% | High risk93 | Flagged0.020 |
| 25HB0033ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT DAT-AN-CARMEN-SIERRA BULLONES-PILAR-ALICIA RD - K0079 + 000 - K0079 + 630, K0079 + 872 - K0081 + 270 | Region VII | Bohol 3rd DEO | On-Going | ₱92.3M | 100% | High risk93 | Flagged0.006 |
| 25HB0029ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT DAT-AN-CARMEN-SIERRA BULLONES-PILAR-ALICIA RD - K0066 + 000 - K0066 + 653, K0067 + 440 - K0068 + 330 | Region VII | Bohol 3rd DEO | On-Going | ₱74.1M | 86% | High risk92 | Flagged0.005 |
| 25HB0007OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT. DAT-AN CARMEN- SIERRA BULLONES - PILAR - ALICIA RD - K0072+(-375) - K0073+013, K0075+025 - K0076+108 | Region VII | Bohol 3rd DEO | On-Going | ₱140.5M | 93% | High risk91 | Flagged0.017 |
| 25HB0026ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS -JCT (LIR) -CARMEN -SAGBAYAN - BACANI RD -K0165 + 788 - K0167 + 003, K0167 + 361 - K0168 + 661 | Region VII | Bohol 3rd DEO | On-Going | ₱142.1M | 89% | High risk90 | Flagged0.018 |
| 25HB0038OO!:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT. DAT-AN - CARMEN - SIERRA BULLONES - PILAR - ALICIA RD - K0064+906 - K0066+000 | Region VII | Bohol 3rd DEO | Completed | ₱74.5M | 100% | High risk88 | —-0.026 |
| 24M00074CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER STA. 42 + 296 - STA. 42 + 561 L/S, BARANGAY LABU-O, PRES. ROXAS, COTABATO | Region XII | Region XII | On-Going | ₱95.3M | 96% | High risk82 | Flagged0.012 |
| 24M00075CONSTRUCTION OF FLOOD CONTROL DIKE ALONG RIVER STA. 42 + 355 - STA. 42 + 880 R/S (PHASE II), BARANGAY POBLACION, PRES. ROXAS, COTABATO | Region XII | Region XII | On-Going | ₱96.5M | 99% | High risk82 | Flagged0.010 |
| 25CL0078CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 2, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.1M | 41% | High risk81 | Flagged0.000 |
| 25CL0060CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG TAKAR RIVER PHASE 5, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱97.5M | 35% | High risk80 | —-0.000 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23E00311ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG QUEZON-PUNTA BAJA ROAD, K0147+414-K0150+465, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱202.6M | 66% | High risk66 | Flagged0.057 |
| 23E00310ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASDPHALT OVERLAY) ALONG PPSR JCT. (ABO-ABO)-QUEZON ROAD, K0139+568-K0142+730, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱173.7M | 71% | High risk64 | Flagged0.055 |
| 25LG0073CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PANGYAN UPPER SUMLOG RIVER, LUPON, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱97M | 21% | High risk95 | Flagged0.050 |
| 23E00309ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG PPSR JCT. (ABO-ABO)-QUEZON ROAD, K0130+607-K0133+397, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱144.9M | 81% | High risk61 | Flagged0.048 |
| 25LJ0134CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE (EARTH DIKE) ALONG TAGUM LIBUGANON RIVER BASIN, CARMEN - B.E. JUALI, STO. TOMAS, DAVAO DEL NORTE, SECTION 5, DAVAO DEL NORTE | Region XI | Davao del Norte 2nd DEO | On-Going | ₱96M | 6% | High risk96 | Flagged0.048 |
| 24DD0280ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE J), LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 0% | High risk69 | Flagged0.034 |
| 24DD0292ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE K), LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 2% | High risk69 | Flagged0.033 |
| 24DD0270CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROA | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 26% | High risk69 | Flagged0.029 |
| 24DD0271CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROA | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 24% | High risk69 | Flagged0.029 |
| 24DD0272CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROA | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 24% | High risk69 | Flagged0.029 |
| 24DD0279ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE I), LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 33% | High risk69 | Flagged0.024 |
| 25HB0008OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD, K0177+398 - K0178+477, K0184+296 - K0185+157 | Region VII | Bohol 3rd DEO | On-Going | ₱126.2M | 74% | High risk93 | Flagged0.020 |
| 24DD0203CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF LUMBANG-INOSLUBAN DIVERSI | Region IV-A | Batangas 4th DEO | On-Going | ₱193M | 74% | High risk77 | Flagged0.020 |
| 25HB0028ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - JCT (TER)-JAGNA-SIERRA BULLONES RD - K0094 + 000 - K0096 + 792 | Region VII | Bohol 3rd DEO | On-Going | ₱83.8M | 45% | High risk94 | Flagged0.018 |
| 25HB0026ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS -JCT (LIR) -CARMEN -SAGBAYAN - BACANI RD -K0165 + 788 - K0167 + 003, K0167 + 361 - K0168 + 661 | Region VII | Bohol 3rd DEO | On-Going | ₱142.1M | 89% | High risk90 | Flagged0.018 |
| 25HB0007OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT. DAT-AN CARMEN- SIERRA BULLONES - PILAR - ALICIA RD - K0072+(-375) - K0073+013, K0075+025 - K0076+108 | Region VII | Bohol 3rd DEO | On-Going | ₱140.5M | 93% | High risk91 | Flagged0.017 |
| 22E00125ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BURIRAO-ISUGOD CROSS COUNTRY ROAD, BRGY. BURIRAO NARRA AND BRGY. ISUGOD, QUEZON (VIS BRGY. KALATAGBAK AND BRGY. MAASIN, QUEZON), P | Region IV-B | Region IV-B | On-Going | ₱196.5M | 62% | High risk62 | Flagged0.014 |
| 23HK0068SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF OCOY RIVER CONTROL, MAGATAS, SIBULAN, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱96.5M | 100% | High risk79 | Flagged0.014 |
| 25HB0010ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - SECONDARY ROADS THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0200 + 000 - K0201 + 000, K0208 + 000 - K0209 + 235 | Region VII | Bohol 3rd DEO | On-Going | ₱122.8M | 89% | High risk94 | Flagged0.014 |
| 23HK0058SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF NOVALLAS RIVER CONTROL (STA. CRUZ VIEJO SECTION), TANJAY CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 2nd DEO | On-Going | ₱96.5M | 100% | High risk80 | Flagged0.014 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24DF0107CONVERGENCE AND SPECIAL SUPPORT PROG SUSTAINABLE INFRASTRUCTURE PROJ ALLEVIATING GAPS (SIPAG)SIPAG - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG/ FACILITIES CONST OF R1 - AGUINALDO SHRINE AND MUSEUM - NEW K | Region IV-A | Cavite 1st DEO | On-Going | ₱143.3M | 45% | High risk78 | Flagged0.004 |
| 27 | 24DD0203CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF LUMBANG-INOSLUBAN DIVERSI | Region IV-A | Batangas 4th DEO | On-Going | ₱193M | 74% | High risk77 | Flagged0.020 |
| 28 | 23C00412ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS, BALER-CASIGURAN ROAD (BALER-DINADIAWAN), PROVINCE OF AURORA | Region III | Region III | On-Going | ₱56.7M | 76% | High risk72 | —-0.033 |
| 29 | 23C00408ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS, BALER-CASIGURAN ROAD (BALER-DINADIAWAN), PROVINCE OF AURORA | Region III | Region III | On-Going | ₱56.7M | 89% | High risk72 | —-0.035 |
| 30 | 25DF0132CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF R1 - AGUINALDO SHRINE AND | Region IV-A | Cavite 1st DEO | On-Going | ₱74.8M | 0% | High risk71 | —-0.016 |
| 31 | 25DF0119CONVERGENCE & SPECIAL SUPPORT PROGSUSTAINABLE INFRAS PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS RDS &/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIES CONST OF R1 - AGUINALDO SHRINE & MUSEUM-NEW KAWIT CITY HALL ACCESS | Region IV-A | Cavite 1st DEO | On-Going | ₱79.5M | 0% | High risk71 | —-0.015 |
| 32 | 25DF0120CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF R1 - AGUINALDO SHRINE AND | Region IV-A | Cavite 1st DEO | On-Going | ₱79.5M | 30% | High risk71 | —-0.024 |
| 33 | 24DD0280ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE J), LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 0% | High risk69 | Flagged0.034 |
| 34 | 24DD0292ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE K), LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 2% | High risk69 | Flagged0.033 |
| 35 | 24DD0270CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROA | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 26% | High risk69 | Flagged0.029 |
| 36 | 24DD0271CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROA | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 24% | High risk69 | Flagged0.029 |
| 37 | 24DD0272CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROA | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 24% | High risk69 | Flagged0.029 |
| 38 | 24DD0279ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LUMBANG-INOSLOBAN BYPASS ROAD (PACKAGE I), LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 33% | High risk69 | Flagged0.024 |
| 39 | 24M00076CONSTRUCTION OF FLOOD CONTROL DIKE ALONG KABACAN RIVER STA. 45 + 152 - STA. 45 + 642 R/S (PHASE II), BARANGAY ALEGRIA, PRES. ROXAS, COTABATO | Region XII | Region XII | On-Going | ₱95.4M | 93% | High risk67 | Flagged0.003 |
| 40 | 23E00311ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG QUEZON-PUNTA BAJA ROAD, K0147+414-K0150+465, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱202.6M | 66% | High risk66 | Flagged0.057 |
| 41 | 24DD0273CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, ASPHALT OVERLAY MANILA-BATANGAS BYPASS ROAD | Region IV-A | Batangas 4th DEO | On-Going | ₱93.7M | 91% | High risk66 | Flagged0.001 |
| 42 | 20E00097CLUSTER 4 - CONSTRUCTION OF MISSING LINKS / NEW ROADS SUMBILING STA. 0+000 - 10+000, PALAWAN | Region IV-B | Region IV-B | Completed | ₱106.1M | 100% | High risk66 | Flagged0.008 |
| 43 | 25DD0013CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF LIPA CITY-MATAASNAKAHOY DIVE | Region IV-A | Batangas 4th DEO | On-Going | ₱140.6M | 25% | High risk65 | —-0.032 |
| 44 | 25DD0059CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), LIPA CITY-MATAASNAKAHOY DIVERSION RD LEADING TO TAAL CIRCUMFE | Region IV-A | Batangas 4th DEO | On-Going | ₱140.5M | 35% | High risk65 | —-0.038 |
| 45 | 25DD0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), LIPA CITY-MATAASNAKAHOY DIVERSION RD LEADING TO TAAL CIRCUMFE | Region IV-A | Batangas 4th DEO | On-Going | ₱140.5M | 43% | High risk65 | —-0.041 |
| 46 | 24DF0018CONVERGENCE & SPECIAL SUPPORT PROG SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) SIPAG - ACCESS RDS &/OR BRDGS. FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIES CONST OF R1 - AGUINALDO SHRINE & MUSEUM-NEW KAWIT CI | Region IV-A | Cavite 1st DEO | On-Going | ₱143.3M | 24% | High risk65 | —-0.021 |
| 47 | 24DD0202CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF LUMBANG-INOSLUBAN DIVERSI | Region IV-A | Batangas 4th DEO | On-Going | ₱187.2M | 87% | High risk65 | —-0.041 |
| 48 | 23DF0109CONVERGENCE AND SPECIAL SUPPORT PROGSUSTAINABLE INFRASTRUCTURE PROJS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS./FACILITIESCONST OF ROAD, CARSADANG BAGO R1 BY-PASS,PACKAGE 1, | Region IV-A | Cavite 1st DEO | Completed | ₱144.8M | 100% | High risk65 | —-0.082 |
| 49 | 23DF0110CONVERGENCE AND SPECIAL SUPPORT PROGSUSTAINABLE INFRASTRUCTURE PROJS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS/FACILITIESCONST OF ROAD, CARSADANG BAGO R1 BY-PASS,PACKAGE 2 | Region IV-A | Cavite 1st DEO | On-Going | ₱144.8M | 50% | High risk65 | —-0.028 |
| 50 | 23E00310ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- PREVENTIVE MAINTENANCE (ASDPHALT OVERLAY) ALONG PPSR JCT. (ABO-ABO)-QUEZON ROAD, K0139+568-K0142+730, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱173.7M | 71% | High risk64 | Flagged0.055 |