16 projects on file, including joint ventures this contractor is part of.
Total projects
16
Total budget
₱695.9M
Average progress
98.0%
Completion rate
93.8%
Average risk score
34.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 16 | ₱695.9M | 34.5 | 0 | 98.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 8 | ₱472.2M | 44.4 | 0 | 96.1% |
| Roads | 3 | ₱137.3M | 34.4 | 0 | 100.0% |
| Buildings and Facilities | 3 | ₱7.7M | 9.7 | 0 | 100.0% |
| Bridges | 2 | ₱78.8M | 32.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CL0037CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BANCAL DANAC BUNGA SECTION, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱98.9M | 100% | High risk80 | —-0.043 |
| 23C00072FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER NORTH APPROACH DOWNSTREAM, BOTOLAN, ZAMBALES, PROVINCE OF ZAMBALES | Region III | Region III | Completed | ₱96.5M | 100% | High risk62 | —-0.074 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24CL0037CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BANCAL DANAC BUNGA SECTION, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱98.9M | 100% | High risk80 | —-0.043 |
| 2 | 23C00072FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER NORTH APPROACH DOWNSTREAM, BOTOLAN, ZAMBALES, PROVINCE OF ZAMBALES | Region III | Region III | Completed | ₱96.5M | 100% | High risk62 | —-0.074 |
| 3 | 25CI0040FLOOD MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUITANGIL RIVER, DOWNSTREAM OF OF QUITANGIL BRIDGE, MAGALANG, PAMPANGA | Region III | Pampanga 3rd DEO | On-Going | ₱103.1M | 69% | Medium risk58 | —-0.035 |
| 4 | 24CJ0351REPAIR/REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG TARLAC RIVER CONTROL LEFT DIKE, TIBAG SECTION, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱76.9M | 100% | Medium risk38 | —-0.095 |
| 5 | 22C00024BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, SAN FERNANDO FLYOVER ALONG JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA | Region III | Region III | Completed | ₱67.5M | 100% | Medium risk35 | —-0.060 |
| 6 | 22CI0066CONVERGENCE AND SPECIAL SUPPORT PROGRAM; FLOOD MITIGATION STRUCTURES PROTECTING INFRA/FACILITIES, CONST. OF REINFORCED CONCRETE SLOPE PROTECTION ALONG ABACAN RIVER, UPSTREAM OF FRIENDSHIP BRIDGE STA 0+050 TO 0+650 (R/D), BRGY ANUNAS, ANGELES CITY, PAMPANG | Region III | Pampanga 3rd DEO | Completed | ₱57.9M | 100% | Medium risk35 | —-0.087 |
| 7 | 22CG0026SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF TALBA - TINAJERO ROAD INCLUDING DRAINAGE SYSTEM, BACOLOR, PAMPA | Region III | Pampanga 1st DEO | Completed | ₱37.2M | 100% | Medium risk33 | —-0.103 |
| 8 | 24CI0006FLOOD MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION STRUCTURES ALONG ABACAN RIVER, BRGY ANUNAS TO BRGY MALABANAS (PHASEII), ANGELES CITY, PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱49M | 100% | Medium risk32 | —-0.087 |
| 9 | 22CG0196SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF MAPALAD - CANDATING ROAD, ARAYAT, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱23.2M | 100% | Medium risk32 | —-0.106 |
| 10 | 22CH0012CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PORAC RIVER, VALDEZ SECTION, BRGY. VALDEZ, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱19.6M | 100% | Low risk29 | —-0.089 |
| 11 | 22CC0191CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG GUIGUINTO RIVER STA. 01+840 TO STA. 02+040, MALIS SECTION, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱24.5M | 100% | Low risk29 | —-0.091 |
| 12 | 21CG0204LOCAL INFRASTRUCTURE PROGRAM: LOCAL ROADS AND BRIDGES - LOCAL BRIDGES: REPLACEMENT OF BRIDGE (TEMPORARY TO PERMANENT) SAN VICENTE, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱11.3M | 100% | Low risk29 | —-0.067 |
| 13 | 23CC0064CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER AT BANGA 2ND SECTION, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱22.8M | 100% | Low risk29 | —-0.093 |
| 14 | 21CG0220LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES CONSTRUCTION OF MULTI-PURPOSE BUILDING (MOTORPOOL-PHASE III), SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱4.7M | 100% | Low risk14 | —-0.104 |
| 15 | 21CI0067LOCAL INFRA PROGRAM; BUILDING AND OTHER STRUCTURES/MULTI-PURPOSE/FACILITIES; CONST OF MULTI-PURPOSE BUILDING, BRGY MAMATITANG, MABALACAT CITY, PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱1.5M | 100% | Low risk8 | —-0.101 |
| 16 | 21CI0077LOCAL INFRA PROGRAM/BUILDING AND OTHER STRUCTURES/MULTI-PURPOSE/FACILITIES, IMPROVEMENT/REHABILITATION/ OF MULTI-PURPOSE BUILDING, AT BARY MABIGA, MABALACAT CITY, PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱1.5M | 100% | Low risk7 | —-0.101 |