Contractor dossier
16 projects on file, including joint ventures this contractor is part of.
Total projects
16
Total budget
₱138.5M
Average progress
94.1%
Completion rate
62.5%
Below 70%
Average risk score
40.3
Medium risk on average, out of 100
Flagged as unusual
2
12.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 16 | ₱138.5M | 40.3 | 2 | 94.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 8 | ₱45.2M | 30.1 | 0 | 100.0% |
| Roads | 3 | ₱19.6M | 44.5 | 0 | 97.3% |
| GAA 2025 SSP | 2 | ₱53.9M | 94.9 | 2 | 61.8% |
| Water Provision and Storage | 2 | ₱17.3M | 31.8 | 0 | 95.0% |
| Bridges | 1 | ₱2.5M | 17.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KA0062CONSTRUCTION OF MULTI-PURPOSE BUILDING, DEPARTMENT OF EDUCATION (DEPED) - DIVISION OF MALAYBALAY CITY, MALAYBALAY CITY, BUKIDNONDIVISION OF MALAYBALAY CITY, MALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | On-Going | ₱24.5M | 51% | High risk95 | Flagged0.012 |
| 25KK0038CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY POBLACION, BINUANGAN, MISAMIS ORIENTAL (PHASE 2) | Region X | Misamis Oriental 1st DEO | On-Going | ₱29.4M | 73% | High risk95 | Flagged0.007 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KA0062CONSTRUCTION OF MULTI-PURPOSE BUILDING, DEPARTMENT OF EDUCATION (DEPED) - DIVISION OF MALAYBALAY CITY, MALAYBALAY CITY, BUKIDNONDIVISION OF MALAYBALAY CITY, MALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | On-Going | ₱24.5M | 51% | High risk95 | Flagged0.012 |
| 25KK0038CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY POBLACION, BINUANGAN, MISAMIS ORIENTAL (PHASE 2) | Region X | Misamis Oriental 1st DEO | On-Going | ₱29.4M | 73% | High risk95 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25KA0062CONSTRUCTION OF MULTI-PURPOSE BUILDING, DEPARTMENT OF EDUCATION (DEPED) - DIVISION OF MALAYBALAY CITY, MALAYBALAY CITY, BUKIDNONDIVISION OF MALAYBALAY CITY, MALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | On-Going | ₱24.5M | 51% | High risk95 | Flagged0.012 |
| 2 | 25KK0038CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, BARANGAY POBLACION, BINUANGAN, MISAMIS ORIENTAL (PHASE 2) | Region X | Misamis Oriental 1st DEO | On-Going | ₱29.4M | 73% | High risk95 | Flagged0.007 |
| 3 | 25KA0027COMPLETION OF WATER SYSTEM, BRGY. KALAGANGAN, SAN FERNANDO, BUKIDNON, BARANGAY KALAGANGAN, SAN FERNANDO, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | On-Going | ₱14.7M | 90% | Medium risk45 | —-0.025 |
| 4 | 25KD0019CONSTRUCTION OF ROAD/PATHWAYS, BARANGAY GUSA, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱4.9M | 95% | Medium risk45 | —-0.058 |
| 5 | 25KD0028CONSTRUCTION OF ROAD/PATHWAYS, BARANGAY MACABALAN (DPWH CDO II DEO COMPOUND), CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱9.8M | 97% | Medium risk45 | —-0.061 |
| 6 | 24KA0009CONSTRUCTION OF ROAD, BARANGAY LAGUITAS, MALAYBALAY CITY, BUKIDNON, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk44 | —-0.092 |
| 7 | 23KK0147CONSTRUCTION OF MULTI-PURPOSE FACILITY (PUBLIC MARKET), BARANGAY POBLACION, BINUANGAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 1st DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.096 |
| 8 | 22KD0025CONSTRUCTION OF MULTI PURPOSE BUILDING BARANGAY LAPASAN, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱6.9M | 100% | Medium risk43 | —-0.097 |
| 9 | 21KD0043CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY LAPASAN, CDOC | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱6.9M | 100% | Medium risk43 | —-0.097 |
| 10 | 24KA0148CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 6, MALAYBALAY CITY, BUKIDNONBARANGAY 6, MALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱9.9M | 100% | Medium risk42 | —-0.094 |
| 11 | 23KK0157CONSTRUCTION OF MULTI-PURPOSE FACILITY (BASKETBALL COURT), BINUANGAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.096 |
| 12 | 25KD0082RAINWATER COLLECTOR SYSTEMS IN PUBLIC FACILITIES | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱2.6M | 100% | Low risk18 | —-0.032 |
| 13 | 24KA0001REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES: ATUGAN BR. (B01249MN) ALONG SAYRE HIGHWAY, BRGY. LA FORTUNA, IMPASUG-ONG, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱2.5M | 100% | Low risk17 | —-0.059 |
| 14 | 20KD0036CONST OF MULTI PURPOSE BLDG SENIOR CITIZEN BLDG, BRGY LAPASAN, CDOC | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.096 |
| 15 | 22KD0024CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING BARANGAY LAPASAN CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.093 |
| 16 | 20KD0034CONST OF MULTI PURPOSE BUILDING BRGY LAPASAN, CDOC | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱1.9M | 100% | Low risk9 | —-0.097 |