Contractor dossier
32 projects on file, including joint ventures this contractor is part of.
Total projects
32
Total budget
₱1.6B
Average progress
83.7%
Completion rate
56.3%
Below 70%
Average risk score
57.8
Medium risk on average, out of 100
Flagged as unusual
2
6.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 30 | ₱1.4B | 57.3 | 2 | 84.2% |
| Region IV-A | 2 | ₱195.3M | 64.3 | 0 | 76.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 18 | ₱1.1B | 53.0 | 0 | 84.9% |
| Roads | 5 | ₱71.5M | 45.2 | 0 | 100.0% |
| Buildings and Facilities | 4 | ₱317.1M | 52.8 | 0 | 82.0% |
| GAA 2025 SSP | 3 | ₱59M | 92.6 | 2 | 52.8% |
| GAA 2025 OO-2 | 2 | ₱105.6M | 89.6 | 0 | 82.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OD0295CONSTRUCTION OF REINFORED CONCRETE BOX CULVERT ALONG 8TH STREET, CALOOCAN CITY (PHASE 2) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱25.9M | 30% | High risk93 | Flagged0.018 |
| 25OD0060CONSTRUCTION OF ROAD AND DRAINAGE ALONG 9TH STREET, BARANGAY 103, 101, 96, 93 & 92, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱26.4M | 100% | High risk93 | —-0.032 |
| 25OD0137CONSTRUCTION OF REINFORCED BOX CULVERT ALONG C-3 ROAD, EAST BOUND, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱6.7M | 28% | High risk92 | Flagged0.018 |
| 25OD0035CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG D. AQUINO STREET, BARANGAY 67, 66, 61, 60, 57, 55, 54 & 53, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱57.6M | 95% | High risk90 | —-0.022 |
| 25OD0206CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ESTERO DE MAYPAJO, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48M | 70% | High risk89 | —-0.016 |
| 25OD0169CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG POLO RIVER (PHASE 20), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱142.1M | 71% | High risk68 | —-0.031 |
| 25OD0170CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 17), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱142.1M | 53% | High risk68 | —-0.026 |
| 24OD0281CONSTRUCTION OF MULTI-PURPOSE BUILDING, (DEPED BUILDING) MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱219.4M | 29% | High risk66 | —-0.012 |
| 24OD0082CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 9), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.072 |
| 23OD0094CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 1), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.3M | 100% | High risk65 | —-0.072 |
| 24DI0116CONSTRUCTION OF RIVER PROTECTION STRUCTURE NEAR SOUTH LUZON EXPRESSWAY (SLEX) MALITLIT BRIDGE, STA. ROSA CITY, LAGUNA (PHASE 1) | Region IV-A | Laguna 2nd DEO | On-Going | ₱96.3M | 53% | High risk64 | —-0.027 |
| 24DI0118CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG MALITLIT WATERWAYS (NEAR RIVERBEND HOMES), STA. ROSA CITY, LAGUNA (PHASE 1) | Region IV-A | Laguna 2nd DEO | On-Going | ₱99M | 100% | High risk64 | —-0.044 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OD0295CONSTRUCTION OF REINFORED CONCRETE BOX CULVERT ALONG 8TH STREET, CALOOCAN CITY (PHASE 2) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱25.9M | 30% | High risk93 | Flagged0.018 |
| 25OD0137CONSTRUCTION OF REINFORCED BOX CULVERT ALONG C-3 ROAD, EAST BOUND, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱6.7M | 28% | High risk92 | Flagged0.018 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23OD0172CONSTRUCTION OF ROADS AND DRAINAGE INCLUDING PATHWALK, BRGY. 28, PHASE 2, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.101 |
| 27 | 23OD0177CONSTRUCTION OF ROADS AND DRAINAGE SYSTEM INCLUDING PATHWALK AT BRGY. 14 (PHASE 3), CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.100 |
| 28 | 23OD0056CONSTRUCTION OF FLOOD CONTROL WALL ALONG COLOONG-MABOLO, BRGY. COLOONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱28.4M | 100% | Medium risk45 | —-0.086 |
| 29 | 23OD0050REHABILITATION OF COLOONG PUMPING STATION, COLOONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱24M | 100% | Medium risk45 | —-0.084 |
| 30 | 23OD0099CONSTRUCTION OF FLOOD CONTROL WALL ALONG PASOLO-MABOLO, BRGY. PASOLO, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.1M | 100% | Medium risk45 | —-0.088 |
| 31 | 24OD0290CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING IN PASOLO NATIONAL HIGH SCHOOL (BLDG.1), BARANGAY PASOLO, VALENZUELA CITY (PHASE 2) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱19.7M | 100% | Medium risk45 | —-0.015 |
| 32 | 24OD0011REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG 3RD AVENUE WEST, BARANGAYS 43, 44, 45, 46, 47, AND 48, (PHASE 2), CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.7M | 100% | Medium risk43 | —-0.099 |