Opening the dossier…
Opening the dossier…
Contractor dossier
167 projects on file, including joint ventures this contractor is part of.
Total projects
167
Total budget
₱7.8B
Average progress
98.5%
Completion rate
92.2%
Average risk score
48.9
Medium risk on average, out of 100
Flagged as unusual
3
1.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 110 | ₱6.3B | 49.1 | 2 | 99.0% |
| Region IX | 36 | ₱1.1B | 52.4 | 0 | 96.1% |
| Region X | 10 | ₱77.4M | 41.3 | 0 | 100.0% |
| Region XIII | 9 | ₱305.4M | 40.0 | 0 | 100.0% |
| Region XII | 2 | ₱133.4M | 54.9 | 1 | 99.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 56 | ₱3.4B | 52.8 | 0 | 97.4% |
| Flood Control and Drainage | 47 | ₱2.5B | 48.0 | 0 | 100.0% |
| Bridges | 37 | ₱630.5M | 48.9 | 0 | 99.3% |
| Buildings and Facilities | 20 | ₱668.6M | 31.3 | 0 | 99.4% |
| OTHER | 3 | ₱248.1M | 77.6 | 2 | 97.5% |
| Bridges, Roads | 3 | ₱259M | 63.9 | 0 | 91.0% |
| GAA 2025 OO-2 | 1 | ₱142.6M | 93.4 | 1 | 60.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LI0078CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER (TIPNASAN CREEK JUNCTION), PHASE 2, POBLACION, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱142.6M | 60% | High risk93 | Flagged0.016 |
| 24MC0010CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1662 + 250 - K1662 + 350, PRES. ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 98% | High risk81 | Flagged0.012 |
| 22L00028CONSTRUCTION OF CONCRETE ROAD - FATIMA-MALABOG ROAD (MALABOG-GUMITAN), PACKAGE G, DAVAO CITY | Region XI | Region XI | On-Going | ₱131.9M | 94% | High risk80 | Flagged0.040 |
| 17LH0011PAVING OF SHOULDERS WITH DRAINAGE IMPROVEMENT AT EDEN-TAGURANO ROAD, TORIL DISTRICT, DAVAO CITY A) 1536+311.000-1537+460.090 B) 1537+804.000-1538+092.070 | Region XI | Davao City 2nd DEO | Completed | ₱19.7M | 100% | High risk72 | —-0.025 |
| 25JI0004CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BUUG BY-PASS ROAD, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱87.3M | 35% | High risk68 | —-0.004 |
| 20L00050CONSTRUCTION OF CONCRETE ROAD FROM SITIO MELUYA, BRGY. MALABOG, PAQUIBATO DISTRICT TO SITIO POLOCON, BRGY. LAMANAN, DAVAO CITY | Region XI | Region XI | Completed | ₱94.1M | 100% | High risk67 | —-0.047 |
| 24LF0080SAN IGNACIO BYPASS ROAD, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱93.6M | 73% | High risk66 | —-0.011 |
| 25JI0002ROAD WIDENING - TERTIARY ROADS - DIPLAHAN JCT. MALANGAS PORT RD - K1742+000 - K1743+160, K1743+220 - K1745+563 | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱88.9M | 50% | High risk65 | —-0.034 |
| 19JI0047ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - LANAO-PAGADIAN-ZAMBOANGA CITY RD - K1725+923, K1726+060 (LS), K1726+737 - K1726+877 (RS), K1750+837- K1750+940 | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱77.2M | 100% | High risk63 | —-0.070 |
| 21LC0062CONSTRUCTION OF FLOOD CONTROL PROJECT (EARTHDIKE WITH ROAD ON TOP) ALONG TUGANAY RIVER (LOCUTAN BRIDGE TO TUGANAY BRIDGE), DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱94.6M | 100% | High risk63 | —-0.060 |
| 21L00011CONSTRUCTION OF ROAD, POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 2, DAVAO DE ORO | Region XI | Region XI | Completed | ₱122.7M | 100% | High risk63 | —-0.039 |
| 20L00074CONSTRUCTION OF CONCRETE ROAD-PANABO CITY BYPASS ROAD, DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱125M | 100% | High risk62 | —-0.069 |
| 23LF0066SURIGAO DEL SUR BDRY - DAVAO OR COASTAL RD - K1690+250 - K1690+550, TARRAGONA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱95.3M | 100% | High risk62 | —-0.061 |
| 23LF0065SURIGAO DEL SUR BDRY - DAVAO OR COASTAL RD - K1689+070 - K1689+130, TARRAGONA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱95.5M | 100% | High risk62 | —-0.061 |
| 23LF0079SURIGAO DEL SUR BDRY - DAVAO OR COASTAL RD - K1688+000 - K1688+439, TARRAGONA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱95.2M | 100% | High risk62 | —-0.062 |
| 20L00048CONSTRUCTION OF CONCRETE ROAD AT SITIO BANBAN TO SITIO AYAGON, BRGY. LUMIAD, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Region XI | Completed | ₱94.2M | 100% | High risk62 | —-0.074 |
| 18JE0031CONSTRUCTION OF CONCRETE ROAD SOMINOT-MAHAYAG ROAD, SOMINOT-MAHAYAG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 1st DEO | Completed | ₱63M | 100% | High risk62 | —-0.080 |
| 21LB0317CONSTRUCTION OF ROAD, BARANGAY SALAPAWAN, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.073 |
| 21LB0318CONSTRUCTION OF ROAD, BARANGAY SALAPAWAN TO SITIO KINSE-KINSE, PAQUIBATO DISTRICT, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.074 |
| 21LB0288CONSTRUCTION OF REVETMENT ALONG MATINA RIVER, MATINA APLAYA SECTION, DAVAO CITY | Region XI | Davao City DEO | On-Going | ₱96.5M | 100% | High risk61 | —-0.008 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22L00028CONSTRUCTION OF CONCRETE ROAD - FATIMA-MALABOG ROAD (MALABOG-GUMITAN), PACKAGE G, DAVAO CITY | Region XI | Region XI | On-Going | ₱131.9M | 94% | High risk80 | Flagged0.040 |
| 25LI0078CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER (TIPNASAN CREEK JUNCTION), PHASE 2, POBLACION, MARAGUSAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱142.6M | 60% | High risk93 | Flagged0.016 |
| 24MC0010CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PACO-ROXAS-ARAKAN VALLEY-JCT DAVAO-BUKIDNON RD - K1662 + 250 - K1662 + 350, PRES. ROXAS, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱96.5M | 98% | High risk81 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 18KL0076RETROFITING/STRENGTHENING OF PERMANENT BRIDGES, PANGAYAWAN BR., (B01327MN) ALONG BUTUAN CITY-CAGAYAN | Region X | Misamis Oriental 2nd DEO | Completed | ₱6.6M | 100% | Medium risk45 | —-0.062 |
| 127 | 18KL0078RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, TAYTAYAN BR. (B01328MN) ALONG BUTUAN CITY-CAGAYAN D | Region X | Misamis Oriental 2nd DEO | Completed | ₱5.9M | 100% | Medium risk45 | —-0.062 |
| 128 | 18KL0077RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, TABO-O BR.(B01329MN) ALONG BUTUAN CITY-CAGAYAN DE O | Region X | Misamis Oriental 2nd DEO | Completed | ₱7.3M | 100% | Medium risk45 | —-0.062 |
| 129 | 18KL0082RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, LUGAIT BR. (B01338MN) ALONG BUTUAN CITY-CAGAYAN DE | Region X | Misamis Oriental 2nd DEO | Completed | ₱7M | 100% | Medium risk45 | —-0.062 |
| 130 | 18KL0080RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, LUG-AN BR. (B01337MN) ALONG BUTUAN CITY-CAGAYAN DE | Region X | Misamis Oriental 2nd DEO | Completed | ₱5.1M | 100% | Medium risk45 | —-0.062 |
| 131 | 17NH0015REHABILITATION/RECONSTRUCTION/UPGADING OF DAMAGED PAVED INCLUDING DRAINAGE ALONG SURIGAO-DAVAO COASTAL ROAD (K1371+254.30 - K1371+358) (K1371+430 - 1371+664.50), LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱11.7M | 100% | Medium risk45 | —-0.043 |
| 132 | 21LF0128CONSTRUCTION OF COASTAL PROTECTION PROTECTING SURIGAO DEL SUR BDRY.-DAVAO ORIENTAL COASTAL ROAD (TARRAGONA SECTION), TARRAGONA, DAVAO ORIENTAL (STA. 0+000-STA. 0+360) | Region XI | Davao Oriental 1st DEO | Completed | ₱31.5M | 100% | Medium risk44 | —-0.062 |
| 133 | 19LH0016CONSTRUCTION OF CONCRETE REVETMENT ALONG TALOMO RIVER, CALINAN SECTION, CALINAN DISTRICT, 3RD CONGRESSIONAL DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱39M | 100% | Medium risk44 | —-0.080 |
| 134 | 22LF0065CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CARAGA RIVER (PANTUYAN SECTION), CARAGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.066 |
| 135 | 21LF0036CONSTRUCTION OF COASTAL PROTECTION PROTECTING SURIGAO DEL SUR BDRY.-DAVAO ORIENTAL COASTAL ROAD (BOSTON SECTION), BOSTON, DAVAO ORIENTAL (STA. 0+300-STA.0+360), BOSTON, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱31.5M | 100% | Medium risk44 | —-0.064 |
| 136 | 21LF0063CONSTRUCTION OF SIBAJAY COASTAL PROTECTION BOSTON, DAVAO ORIENTAL (STA. 0+000 - STA. 0+450) | Region XI | Davao Oriental 1st DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.064 |
| 137 | 20LF0015CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, CATEEL COASTAL PROTECTION CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱39.2M | 100% | Medium risk44 | —-0.065 |
| 138 | 19LB0076CONSTRUCTION OF FLOOD MITIGATION STRUCTURES-BUNAWAN RIVER STA. 2+370-STA. 2+725 (BOTH BANK) WEST SIDE, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱46.3M | 100% | Medium risk44 | —-0.075 |
| 139 | 18LF0011CONSTRUCTION OF REVETMENT ALONG MANAY RIVER, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱28.5M | 100% | Medium risk44 | —-0.065 |
| 140 | 18LF0050CONSTRUCTION OF REVETMENT ON SHEET PILE FOUNDATION, CARAGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱28.4M | 100% | Medium risk44 | —-0.066 |
| 141 | 18LF0004CONSTRUCTION OF REVETMENT ALONG CASAUMAN RIVER, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱31.9M | 100% | Medium risk44 | —-0.066 |
| 142 | 18LF0041CONSTRUCTION OF REVETMENT ALONG MAHAN-UB RIVER, BRGY. CENTRAL, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱19M | 100% | Medium risk44 | —-0.065 |
| 143 | 18LF0005CONSTRUCTION OF BAGANGA SEAWALL, BAGANGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱29.5M | 100% | Medium risk44 | —-0.064 |
| 144 | 21NH0058SURIGAO-DAVAO COASTAL ROAD - K1215+556 - K1217+020, K1217+060 - K1218+000, CARRASCAL, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱71.8M | 100% | Medium risk43 | —-0.081 |
| 145 | 17L00195CONSTRUCTION OF EVACUATION CENTER, BRGY. TINIMBO, CATEEL. DAVAO ORIENTAL | Region XI | Region XI | Completed | ₱34.7M | 100% | Medium risk42 | —-0.043 |
| 146 | 20LB0326CONSTRUCTION OF 3STY-12CL SCHOOL BUILDING, BUHANGIN CES SPED CENTER, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱37.5M | 100% | Medium risk42 | —-0.036 |
| 147 | 22NH0044RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE CARAC-AN BR. (B00659MN) ALONG SURIGAO-DAVAO COASTAL ROAD, MADRID, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱9.8M | 100% | Medium risk41 | —-0.047 |
| 148 | 17LA0122CONSTRUCTION (COMPLETION) OF THE DPWH COMPOSTELA VALLEY DEO BUILDING, NABUNTURAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱16.9M | 100% | Medium risk40 | —-0.052 |
| 149 | 16L00039STANDARD EVACUATION CENTER, BRGY. CANOCOTAN, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱34.7M | 100% | Medium risk40 | —-0.048 |
| 150 | 22NI0036CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT CUMAWAS-POBLACION, STA. 0+000.00 - STA. 2+000.00, BISLIG CITY, SURIGAO DEL SUR | Region XIII | Surigao del Sur 2nd DEO | Completed | ₱49M | 100% | Medium risk38 | —-0.050 |