Opening the dossier…
Opening the dossier…
Contractor dossier
2 projects on file, including joint ventures this contractor is part of.
Total projects
2
Total budget
₱52.3M
Average progress
83.9%
Completion rate
0.0%
Below 70%
Average risk score
93.6
High risk on average, out of 100
Flagged as unusual
2
100.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 2 | ₱52.3M | 93.6 | 2 | 83.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| GAA 2025 SSP | 1 | ₱29M | 94.3 | 1 | 92.0% |
| GAA 2025 OO-1 | 1 | ₱23.3M | 92.8 | 1 | 75.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PF0042CONSTRUCTION OF ROAD ALONG PONGO - COPCOPIT- DANGADANGAN, BAKUN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱29M | 92% | High risk94 | Flagged0.012 |
| 25PF0037PREVENTIVE MAINTENANCE - SECONDARY ROADS: BAGUIO - BONTOC RD - K0308+000 - K0310+042 | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱23.3M | 76% | High risk93 | Flagged0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PF0042CONSTRUCTION OF ROAD ALONG PONGO - COPCOPIT- DANGADANGAN, BAKUN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱29M | 92% | High risk94 | Flagged0.012 |
| 25PF0037PREVENTIVE MAINTENANCE - SECONDARY ROADS: BAGUIO - BONTOC RD - K0308+000 - K0310+042 | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱23.3M | 76% | High risk93 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PF0042CONSTRUCTION OF ROAD ALONG PONGO - COPCOPIT- DANGADANGAN, BAKUN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱29M | 92% | High risk94 | Flagged0.012 |
| 2 | 25PF0037PREVENTIVE MAINTENANCE - SECONDARY ROADS: BAGUIO - BONTOC RD - K0308+000 - K0310+042 | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱23.3M | 76% | High risk93 | Flagged0.001 |