Contractor dossier
9 projects on file, including joint ventures this contractor is part of.
Total projects
9
Total budget
₱321.2M
Average progress
88.2%
Completion rate
44.4%
Below 70%
Average risk score
63.3
High risk on average, out of 100
Flagged as unusual
2
22.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 9 | ₱321.2M | 63.3 | 2 | 88.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 5 | ₱195.4M | 57.3 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱86.9M | 50.5 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱9.7M | 93.9 | 1 | 29.0% |
| OTHER | 1 | ₱29.3M | 88.4 | 1 | 65.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FA0032CONSTRUCTION OF MULTI-PURPOSE BUILDING ( ADULT DAY CENTER) AT HIRAYA MANAWARI NATURE PARK, SAN VICENTE, TABACO CITY, ALBAY | Region V | Albay 1st DEO | On-Going | ₱9.7M | 29% | High risk94 | Flagged0.016 |
| 24FA0066CONSTRUCTION OF 2-STOREY 8-CLASSROOM SCHOOL BUILDING AT TABACO NATIONAL HIGH SCHOOL, TABACO CITY, ALBAY | Region V | Albay 1st DEO | On-Going | ₱29.3M | 65% | High risk88 | Flagged0.043 |
| 24FA0045CLUSTER 7-ROAD WIDENING-SECONDARY ROADS ALONG LIGAO-TABACO ROAD K0517+348-K0517+912; AND K0519+565.80-K0519+865,K0519+873.20-K0520+000, TABACO CITY, ALBAY | Region V | Albay 1st DEO | Completed | ₱51.7M | 100% | High risk61 | —-0.101 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24FA0066CONSTRUCTION OF 2-STOREY 8-CLASSROOM SCHOOL BUILDING AT TABACO NATIONAL HIGH SCHOOL, TABACO CITY, ALBAY | Region V | Albay 1st DEO | On-Going | ₱29.3M | 65% | High risk88 | Flagged0.043 |
| 25FA0032CONSTRUCTION OF MULTI-PURPOSE BUILDING ( ADULT DAY CENTER) AT HIRAYA MANAWARI NATURE PARK, SAN VICENTE, TABACO CITY, ALBAY | Region V | Albay 1st DEO | On-Going | ₱9.7M | 29% | High risk94 | Flagged0.016 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25FA0032CONSTRUCTION OF MULTI-PURPOSE BUILDING ( ADULT DAY CENTER) AT HIRAYA MANAWARI NATURE PARK, SAN VICENTE, TABACO CITY, ALBAY | Region V | Albay 1st DEO | On-Going | ₱9.7M | 29% | High risk94 | Flagged0.016 |
| 2 | 24FA0066CONSTRUCTION OF 2-STOREY 8-CLASSROOM SCHOOL BUILDING AT TABACO NATIONAL HIGH SCHOOL, TABACO CITY, ALBAY | Region V | Albay 1st DEO | On-Going | ₱29.3M | 65% | High risk88 | Flagged0.043 |
| 3 | 24FA0045CLUSTER 7-ROAD WIDENING-SECONDARY ROADS ALONG LIGAO-TABACO ROAD K0517+348-K0517+912; AND K0519+565.80-K0519+865,K0519+873.20-K0520+000, TABACO CITY, ALBAY | Region V | Albay 1st DEO | Completed | ₱51.7M | 100% | High risk61 | —-0.101 |
| 4 | 24FA0025REHAB./RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS: DAANG MAHARLIKA JCT-LEGAZPI-STO. DOMINGO-TABACO-CAM. SUR BDRY ROAD K0565+243-K0565+415, K0565+702-K0566+140 | Region V | Albay 1st DEO | Completed | ₱60.3M | 100% | Medium risk59 | —-0.098 |
| 5 | 24FA0034CLUSTER 3-REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS ALONG STO. DOMINGO-BUHATAN-CAGRARAY CIRCUMFERENTIAL ROAD, STO. DOMINGO, ALBAY | Region V | Albay 1st DEO | On-Going | ₱38.1M | 100% | Medium risk58 | —-0.068 |
| 6 | 24FA0051REHABILITATION OF ROAD, BANAO-BICAL ROAD, BACACAY & STO. DOMINGO, ALBAY | Region V | Albay 1st DEO | On-Going | ₱29.4M | 100% | Medium risk57 | —-0.070 |
| 7 | 25FA0022REHB./RECONST./UPGRADING OF DAMAGED PAVED RDS.-SECONDARY RDS.: DAANG MAHARLIKA JCT.-LEG.-STO. DOMINGO-TABACO-CAM. SUR BDRY. RD.-K0574+700-K0575+096 | Region V | Albay 1st DEO | On-Going | ₱15.9M | 100% | Medium risk52 | —-0.077 |
| 8 | 24FA0020CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY TANAWAN, MALINAO, ALBAY | Region V | Albay 1st DEO | Completed | ₱48.3M | 100% | Medium risk51 | —-0.088 |
| 9 | 25FA0017CONSTRUCTION OF RIVER CONTROL, MALOLOS, MALINAO, ALBAY | Region V | Albay 1st DEO | Completed | ₱38.6M | 100% | Medium risk50 | —-0.088 |